H. N. Bailey & Associates v. The United States

449 F.2d 387, 196 Ct. Cl. 156, 1971 U.S. Ct. Cl. LEXIS 8
CourtUnited States Court of Claims
DecidedOctober 15, 1971
Docket530-69
StatusPublished
Cited by30 cases

This text of 449 F.2d 387 (H. N. Bailey & Associates v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
H. N. Bailey & Associates v. The United States, 449 F.2d 387, 196 Ct. Cl. 156, 1971 U.S. Ct. Cl. LEXIS 8 (cc 1971).

Opinion

NICHOLS, Judge: *

This is a contract action wherein this court, by cross motions for summary judgment, has been asked to review a decision of the Armed Services Board of Contract Appeals (ASBCA) in accordance with the standards established by the Wunderlich Act, 41 U.S.C. §§ 321-322 (1964). Jurisdiction is conferred by 28 U.S.C. § 1491.

The ASBCA upheld the Contracting Officer’s decision to terminate the plaintiff’s contract for default as well as his assessment of excess reprocurement costs in the amount of $2,510.20. Plaintiff asks us to hold that the termination for default was improper, thereby converting it to a termination for convenience, and in addition, it wants to recover the excess reprocurement costs. We agree with plaintiff. The facts, as found by the ASBCA are as follows:

*389 On July 30, 1965, the Air Force awarded plaintiff, as low bidder, contract No. AF 34 (601)-23699, calling for the manufacture and delivery of a quantity of oil seals. In addition to the standard “Disputes”, “Default” and “Termination for Convenience” clauses, the contract contained a “First Article Approval” clause, which is reproduced in part below:

(a) The first 3 articles of Item 1.1 are designated as First Articles and shall be delivered by the Contractor to the Government, all transportation charges prepaid in accordance with the delivery schedule set forth herein, for First Article Engineering Test and approval. The Contractor will be notified in writing, whether or not the First Articles are approved. After testing, said article shall be returned to the Contractor, at the Contractor’s expense, in their then condition for submission as contract items after repairs and modifications, if necessary, have been made by the Contractor. Pending written approval of the First Articles the remaining items of the contract shall not be fabricated or produced but the Contractor may acquire necessary materials for fabrication.

* * * ->:• íf *

(e) If, following any submission or resubmission under this clause, the tests reveal discrepancies in the First Articles from the specification requirements, the Government may, at its option, either (i) terminate this contract in accordance with the terms of (a) (i) of the clause hereof entitled “Default”, or (ii) notify the Contractor in writing of the discrepancies and specify an extension of the time set forth in Part II Page 8, in which event the Contractor shall correct and resubmit the First Articles at no cost to the Government. The number of resubmissions of samples shall be limited to one within fifteen (15) days after the date of receipt by the Contractor of notification of disapproval of test samples by the Government.

We read this as meaning that plaintiff could have a test of “First Articles”. If they failed the test, defendant could default plaintiff without more ado. Or it could notify of the defects, extend the time, and call for resubmission within 15 days. If the second resubmission failed, plaintiff was dead. No discretion was reserved to extend time again and call for a third submission. It is needless to point out that these are more harsh than the usual default clauses and reflect a demand that plaintiff either shape up at once or step aside.

The specifications were in a drawing furnished by the Government and required that the seals be anodized. The time allowed from award date required that three “First Articles” or samples be delivered for testing by November 6, 1965. Delays were encountered, for reasons which are not relevant here, and on October 25, with the deadline near, plaintiff submitted three “First Articles” which were not anodized. The Government held that testing unanodized samples would not produce reliable results, conducted no tests and instructed the plaintiff by telegram that the samples had been “returned to you via parcel post on 1 Nov. 65 for finishing according to contract specifications”. Plaintiff was directed to resubmit them within one week.

Plaintiff completed the anodyzing process and shipped them again. The Government received them after the due date on November 26, and tested without making further objection to doing so.

On January 14, 1966, plaintiff received a letter, dated January 10, 1966, stating that the samples were being returned because they had failed to meet the specifications. A test report listing deficiencies in detail was enclosed with the letter. Plaintiff made some adjustments which it hoped corrected the deficiencies and shipped three more samples to defendant on January 27. Plaintiff at this time proceeded with production in quantity on the assumption that these samples would meet the Government specifications.

*390 On February 4, defendant sent plaintiff a telegram terminating the contract for default because of failure “to deliver acceptable First Articles in accordance with contract terms and conditions”, the “termination contracting officer” being of the opinion that such failure was not the result of causes beyond the contractor’s control and not without its fault or negligence. Subsequently, plaintiff received a letter dated February 21, to the effect that the January 27 samples were being returned untested because the contract had been terminated for default.

Plaintiff appealed the action of that contracting officer but at the same time, offered its inventory of oil seals to defendant at a reduced price. However, this offer was rejected and the Government let a reprocurement contract to the firm which had been the third low bidder on the original contract, but at a price which was higher than its original bid. The consequence to the plaintiff was the assessment of excess reprocurement costs in the amount of $2,510.20.

We find it unnecessary to examine the record to determine whether any of the Board’s findings were arbitary, capricious or unsupported by substantial evidence because we find that the ASBCA decision was based on a misinterpretation of the “First Article Approval” clause of the contract. “The interpretation of the meaning of a contract is a question of law to be determined by the court, and the court is not bound by a decision of the Board with respect thereto”. Bailey Specialized Bldgs., Inc. v. United States, 404 F.2d 355, 360, 186 Ct.Cl. 71, 81 (1968).

Plaintiff’s first duty under the contract was to submit three “First Articles” for testing by November 6. Defendant’s corresponding first duty was to test the samples submitted. The October 25 delivery was not the “first submission” under the contract. Defendant, for reasons we do not challenge, refused to test them, finding them not suited for testing, and returned them to plaintiff for anodyzing and resubmission. At that time plaintiff was not in default. When November 6 came and passed without the submission of three samples suitable for testing, plaintiff would have been technically in default for having made no submission, and it may be that defendant could then have terminated the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Martin Construction, Inc. v. United States
102 Fed. Cl. 562 (Federal Claims, 2011)
Bearingpoint, Inc. v. United States
82 Fed. Cl. 181 (Federal Claims, 2008)
Dan Nelson Construction, Inc. v. Nodland & Dickson
2000 ND 61 (North Dakota Supreme Court, 2000)
Neal & Co. v. United States
41 Cont. Cas. Fed. 77,003 (Federal Claims, 1996)
Case, Incorporated v. United States
62 F.3d 1430 (Federal Circuit, 1995)
Coggeshall Development Corp. v. United States
39 Cont. Cas. Fed. 76,566 (Federal Claims, 1993)
Dano Resource Recovery, Inc. v. District of Columbia
620 A.2d 1346 (District of Columbia Court of Appeals, 1993)
Youngdale & Sons Construction Co. v. United States
38 Cont. Cas. Fed. 76,467 (Federal Claims, 1993)
Western States Construction Co. v. United States
38 Cont. Cas. Fed. 76,376 (Court of Claims, 1992)
International Fidelity Insurance v. United States
37 Cont. Cas. Fed. 76,277 (Court of Claims, 1992)
Municipality of Anchorage v. Frank Coluccio Construction Co.
826 P.2d 316 (Alaska Supreme Court, 1992)
Al Johnson Construction Co. v. United States
36 Cont. Cas. Fed. 75,850 (Court of Claims, 1990)
Universal Contracting & Brick Pointing Co. v. United States
36 Cont. Cas. Fed. 75,832 (Court of Claims, 1990)
Spirit Leveling Contractors v. United States
36 Cont. Cas. Fed. 75,770 (Court of Claims, 1989)
Dawco Construction, Inc. v. United States
35 Cont. Cas. Fed. 75,755 (Court of Claims, 1989)
Russell Corp. v. United States
35 Cont. Cas. Fed. 75,589 (Court of Claims, 1988)
Tilley Constructors & Engineers, Inc. v. United States
35 Cont. Cas. Fed. 75,567 (Court of Claims, 1988)
North Slope Technical Ltd. v. United States
34 Cont. Cas. Fed. 75,430 (Court of Claims, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
449 F.2d 387, 196 Ct. Cl. 156, 1971 U.S. Ct. Cl. LEXIS 8, Counsel Stack Legal Research, https://law.counselstack.com/opinion/h-n-bailey-associates-v-the-united-states-cc-1971.