Universal Contracting & Brick Pointing Co. v. United States

36 Cont. Cas. Fed. 75,832, 19 Cl. Ct. 785, 1990 U.S. Claims LEXIS 81, 1990 WL 33683
CourtUnited States Court of Claims
DecidedMarch 26, 1990
DocketNo. 4-86C
StatusPublished
Cited by5 cases

This text of 36 Cont. Cas. Fed. 75,832 (Universal Contracting & Brick Pointing Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Universal Contracting & Brick Pointing Co. v. United States, 36 Cont. Cas. Fed. 75,832, 19 Cl. Ct. 785, 1990 U.S. Claims LEXIS 81, 1990 WL 33683 (cc 1990).

Opinion

ORDER

LYDON, Senior Judge:

This contract case comes before the court on motions for summary judgment filed by the parties. Defendant’s motion for summary judgment seeks dismissal of [786]*786all four counts of the complaint, whereas plaintiff seeks summary judgment on only one count of the complaint. Plaintiff asserts that factual disputes preclude the granting of summary judgment on the other three counts of the complaint. Upon consideration of the submissions of the parties and oral argument, the court concludes that factual disputes warrant denial of the parties’ motions for summary judgment.

FACTS

On September 7, 1982, the Veterans Administration (VA) awarded contract number V533C465 to plaintiff Universal Contracting and Brick Pointing Company, Inc. (Universal). The contract states, in relevant part, “Contract For (Work to be performed) Chemical removal of paint for exterior of Bldgs # 15, # 17 and # 16.”

Section 4.03 of the contract provides: BUILDING DESCRIPTION AND BACKGROUND:
The building is a three-story building with a flat roof, parapet walls, cornice, aluminum windows, with exterior face brick. The face brick has a glazed coating and has been painted several times with a Renuit paint system. The paint system has failed in many spots and has peeled; however, in some areas the paint has bonded to the brick. Recently, the building was scraped mechanically to remove the loose paint. The purpose of this specification is to remove the rest of the paint by chemical means and hydro cleaning.

Section 4.11 of the contract provides, in part, as follows:

CLEANING PROCESS:
A. Cleaning materials shall be thoroughly mixed according to instructions on manufacturer’s printed label (container label).
B. Paint stripper shall be applied by brush. Apply a heavy thick coating. Allow the paint stripper to remain on the surface for a sufficient time as determined during the tests. The coated areas shall be rinsed from the bottom up with clear water applied at a pressure of 300 to 500 PSI. Gun used to apply water shall be equipped with not less than a 15 [degree] spray tip. All tips shall be fan type. Re-apply paint stripper where necessary. Remove all paint coatings using this product and process. Under no circumstances shall the water pressure be high enough to erode or harm the face brick or damage the mortar joints to any appreciable extent.

Prior to 1982, certain buildings at the VA Medical Center (VAMC) in Castle Point, New York, had two coats of Renuit Exteri- or Wall Resurfacer (Renuit) applied to their exterior walls in the years 1959-1960, 1970 and 1975. At least six coats of Renuit were applied to the three buildings covered by Universal’s contract, buildings 15, 16, and 17, between those years. Defendant maintains that VA records show that buildings 15, 16, 17 and 18 received identical Renuit treatments.1 Renuit contains a “chemical base incorporating mica, silicious minerals, pure earth, and chemically-treated pigments, which are embedded together in a waterproof vehicle.” Renuit also contains asbestos.2

In 1981, the VA decided to remove the Renuit “paint system” from the buildings so treated at the VAMC.3 In the spring of 1982 the VA, through Joseph Kajor (Kajor), Chief of Engineering Service, retained a laboratory in New York City to advise the VA on the proper chemical remover for Renuit. Kajor’s affidavit states that the VA received a lab report which recommended Sears’ and Formby’s paint rem[787]*787overs to remove Renuit. Kajor’s affidavit also states that the VA was informed by the lab over the phone that Renuit contains asbestos. The affidavit also states that the manufacturer of Renuit would not recommend a chemical remover or reveal the chemical contents of Renuit when requested to do so by the VA. It was not until April 15, 1986, that the makers of Renuit disclosed to the VA by letter that in 1959 Renuit contained 21.64% asbestos, and from 1970 through 1975 Renuit contained 15.67% asbestos.4

The VA awarded a total of four contracts between 1982 and 1983, including Universal’s, to remove exterior materials from the walls of buildings 8, 9,15,16,17,18, 44 and 54 at the VAMC.5

The VA awarded the first contract for removal of the Renuit “paint system” to Merritt-Meridian Construction Corporation (Merritt-Meridian) on August 31, 1982, for building 18. The second contract for removal of the Renuit “paint system” was awarded to Universal on September 7, 1982, for buildings 15, 16, and 17. Both of these contracts contain specifications which state that “[t]he paint removal materials shall be Formby’s ... Sears ... or SI No. 6 paint and varnish remover ... or their equals.”

The VA awarded a contract for “paint removal” to Chris Waterproofing Corporation (CW) for buildings 8 and 9 on July 7, 1983, and the VA awarded a contract for “paint removal” to Ganem Contracting Corporation (Ganem) for buildings 44, 54 and the penthouses of buildings 15, 16 and 17 on August 12, 1983. Neither of these contracts mentions Renuit, and both contracts contain identical specifications which state that “[t]he paint removal materials shall be Sure Klean Heavy Duty Paint Stripper ... or their equals.”

Like Universal’s contract, Merritt-Meridian’s contract specifications did not specify or mention Sure Klean, but the subcontractor for Merritt-Meridian proposed to use Sure Klean as the chemical remover under the “or their equals” clause in the contract, and after a successful test, the VA approved its use. Merritt-Meridian’s contract was completed without difficulty on August 9, 1983, although work was suspended during cold weather. Merritt-Meridian used high pressure hot water to flush Renuit off the brick, although like Universal’s contract, Merritt-Meridian’s contract does not specify a water temperature for the rinsing process.

Defendant contends that all of the buildings covered by these four contracts were treated with Renuit in various amounts, but plaintiff correctly points out that neither CW's nor Ganem’s contract specifications mention' Renuit, while the contract specifications in the contracts of Universal and Merritt-Meridian expressly state that the buildings have been treated with the “Renuit paint system.”

On October 20, 1982, about forty-five days after Universal was awarded the contract in dispute, the VA issued Universal a Notice to Proceed, which established December 4, 1982 as a completion date (forty-five calendar days). Universal proposed to use the chemical remover KRC MC-25, under the “or their equal” clause of the contract specifications for chemical removers. The proposed remover was tested and approved for Universal’s use by the VA.

On November 17, 1982, due to cold weather, the VA’s contracting officer (CO) granted Universal a time extension of 210 calendar days, and established a new completion date of June 30, 1983. Although Universal requested that it be allowed to resume work earlier in May, work was actually resumed on May 31, 1983. When Universal began to have problems removing the exterior material from the buildings, the VA’s Resident Engineer Ronald Klimas (Klimas) recommended that Univer[788]*788sal use the chemical remover Sure Klean, and on June 1, 1983 Klimas approved Universal’s use of this remover.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Conner Brothers Construction Co. v. United States
65 Fed. Cl. 657 (Federal Claims, 2005)
Becho, Inc. v. United States
47 Fed. Cl. 595 (Federal Claims, 2000)
ThermoCor, Inc. v. United States
40 Cont. Cas. Fed. 76,955 (Federal Claims, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
36 Cont. Cas. Fed. 75,832, 19 Cl. Ct. 785, 1990 U.S. Claims LEXIS 81, 1990 WL 33683, Counsel Stack Legal Research, https://law.counselstack.com/opinion/universal-contracting-brick-pointing-co-v-united-states-cc-1990.