Dano Resource Recovery, Inc. v. District of Columbia

620 A.2d 1346, 1993 D.C. App. LEXIS 42, 1993 WL 47314
CourtDistrict of Columbia Court of Appeals
DecidedFebruary 23, 1993
Docket91-AA-55
StatusPublished
Cited by23 cases

This text of 620 A.2d 1346 (Dano Resource Recovery, Inc. v. District of Columbia) is published on Counsel Stack Legal Research, covering District of Columbia Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dano Resource Recovery, Inc. v. District of Columbia, 620 A.2d 1346, 1993 D.C. App. LEXIS 42, 1993 WL 47314 (D.C. 1993).

Opinion

FARRELL, Associate Judge:

This is a petition for review of a decision by the District of Columbia Contract Appeals Board (the Board) arising from the District government’s termination of a $78,084,193 contract with Dano Resource Recovery, Inc. (Dano) for the processing and disposal of sludge and solid waste. Dano appealed the termination to the Board and sought an award of damages. When the District claimed removal and re-procurement costs from Dano, Dano filed a second appeal with the Board, which was consolidated with the first.

Following 84 days of hearings and review of a vast evidentiary record, the Board upheld the contract termination in a 73-page opinion and sustained the District’s claim for removal costs, but denied its claim for reprocurement costs. Dano now petitions for review of the decision upholding the termination, contending, inter alia, that the Board’s interpretation of the contract’s performance requirements and termination provision was erroneous and that its factual findings as to Dano’s performance under the contract were arbitrary, capricious, and unsupported by the record.

We hold, under the appropriate standard of review, that the Board’s interpretation of the performance requirements and termination provision was reasonable, and sustain it. We also find substantial evidence in the record supporting the Board’s findings that Dano defaulted on the performance requirements, that its default was not waived or excused, and that the District exercised reasonable judgment in terminating the contract despite the forfeiture of Dano’s substantial capital investment which this exacted.

I. FACTUAL BACKGROUND

In March of 1982, Dano entered into a contract with the District to dispose of sludge and solid waste (referred to here collectively as “waste”) by processing it into saleable compost at the District’s Blue Plains water treatment facility. Dano received the contract without competitive bidding, partly in settlement of a breach of contract suit it had filed against the District for termination of two earlier waste processing contracts. 1 Under the present contract, Dano was to invest its own capital in building and operating the facility and recover its investment over time by the disposal and sale of the composted waste. Dano would lease acres from the District at the Blue Plains site, where it would build the waste processing plant. The District would pay Dano for processing and removing a fixed amount of waste, and Dano would sell a specified amount of processed compost each year, with the District sharing in the profits.

*1349 To understand the performance requirements, we briefly outline the “Dano process” set forth in the contract. Dano was to receive daily amounts of waste from the District and place it in large tubular biosta-bilizers, which initiated the composting process by way of tumbling and aeration. The waste was to “stabilize” at a temperature of 140 degrees for twenty-four hours to help eliminate pathogens, then be discharged from the biostabilizers and sifted through grates. Any material not filtered through the grates was a “reject” to be transported to an incinerator or landfill. The remaining waste would be transported to a composting shed and held for twenty-one days at a constant temperature of 131 degrees to reach stabilization. After removal from the shed and screening to filter out unwanted matter, the compost would be hauled from the site for storage and sale.

The project described in the contract had two phases. Phase I was a ninety-day demonstration in which Dano would construct a small facility having two biostabi-lizers and prove the feasibility of the process. 2 If Dano failed this demonstration, it would lose its investment. If the District approved the process after the demonstration, Dano would proceed to Phase II. The first part of that phase was a seven month construction period (“pre-term phase”) during which Dano would expand the facility to a full capacity plant with nine biostabiliz-ers. It would then begin a five year term of operations to process waste into compost, increasing the output from 400 to 1,800 tons per day. All the while, Dano was to be paid for processing and removing the delivered waste from Blue Plains.

The demonstration began on September 17, 1982 and ended on December 2. While awaiting approval of the demonstration, Dano began the Phase II expansion. Although the District expressed concerns about the demonstration, 3 it formally approved the process on January 31, 1983, some two months later than the contract called for. 4 On April 11, 1983, however, the District sent Dano a letter asserting performance deficiencies and insisting that Dano bring itself into compliance within ten days. Dano responded with a letter acknowledging certain deficiencies but denying generally that it had defaulted on the contract requirements. Dano claimed that many of the stated deficiencies had been waived, were partially the fault of the District, or were beyond Dano’s control. The letter proposed a complex ninety-day plan for correcting the compost removal and storage problem (including the temporary use of barges in the Potomac River), which the District reviewed and found to be unsatisfactory.

On May 9, 1983, the District terminated the contract on the ground that Dano had defaulted by failing to perform services required by the contract — specifically, removal of the compost from Blue Plains— within the cyclical required time of twenty-one days. In the termination letter the District stated:

It is now apparent that the District is confronted with an enormous problem as the result of material being stored in the compost sheds for more than 21 days. Therefore, disposing of it will be costly because it is only suitable for removal to a disposal facility such as a landfill or incinerator.
*1350 In addition to the 30,000 tons of material in the compost sheds, Dano has piled approximately 10,000 tons of other material outside the sheds. We estimate that it will cost the District at least $784,000 to dispose of this material which has been on the grounds of Blue Plains for more than 21 days. Because Dano apparently does not have the proper permits to remove the material currently in the compost sheds ... Dano is not in a position to immediately dispose of the tons of material now at Blue Plains in excess of the time permitted by the contract ...
Accordingly ... Dano has defaulted on its contract by failing to remove material from the compost sheds 21 days after the composting process began.

Appealing the termination to the Board, Dano contended that there was no contractual requirement that compost be hauled from the site after twenty-one days. It further argued that even if there had been such a requirement initially, the District had waived it; that the contract did not allow for termination for this reason in any event; and that the District’s notice to cure letter was legally defective. Dano also claimed that the District’s own actions contributed substantially to the default, thus excusing any non-performance.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rustler Construction, Inc. v. District of Columbia
211 A.3d 187 (District of Columbia Court of Appeals, 2019)
MorphoTrust USA, Inc. v. District of Columbia Contract Appeals Board
115 A.3d 571 (District of Columbia Court of Appeals, 2015)
TRG Construction Inc. v. District of Columbia Water & Sewer Authority
70 A.3d 1164 (District of Columbia Court of Appeals, 2013)
In Re Mitrano
952 A.2d 901 (District of Columbia Court of Appeals, 2008)
Eagle Maintenance Services, Inc. v. District of Columbia Contract Appeals Board
893 A.2d 569 (District of Columbia Court of Appeals, 2006)
Township of Monroe v. Gasko
868 A.2d 1022 (Supreme Court of New Jersey, 2005)
Abadie v. District of Columbia Contract Appeals Board
843 A.2d 738 (District of Columbia Court of Appeals, 2004)
Belcon Inc. v. District of Columbia Water & Sewer Authority
826 A.2d 380 (District of Columbia Court of Appeals, 2003)
Abadie v. Organization for Environmental Growth, Inc.
806 A.2d 1225 (District of Columbia Court of Appeals, 2002)
District of Columbia v. Kora & Williams Corp.
743 A.2d 682 (District of Columbia Court of Appeals, 1999)
Mitchell v. District of Columbia
736 A.2d 228 (District of Columbia Court of Appeals, 1999)
District of Columbia v. Organization for Environmental Growth, Inc.
700 A.2d 185 (District of Columbia Court of Appeals, 1997)
Dano Resource Recovery, Inc. v. District of Columbia
923 F. Supp. 249 (District of Columbia, 1996)
American Building Maintenance Co. v. L'Enfant Plaza Properties, Inc.
655 A.2d 858 (District of Columbia Court of Appeals, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
620 A.2d 1346, 1993 D.C. App. LEXIS 42, 1993 WL 47314, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dano-resource-recovery-inc-v-district-of-columbia-dc-1993.