Intercounty Construction Corp. v. District of Columbia

443 A.2d 29, 1982 D.C. App. LEXIS 308
CourtDistrict of Columbia Court of Appeals
DecidedMarch 15, 1982
Docket80-1004
StatusPublished
Cited by51 cases

This text of 443 A.2d 29 (Intercounty Construction Corp. v. District of Columbia) is published on Counsel Stack Legal Research, covering District of Columbia Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Intercounty Construction Corp. v. District of Columbia, 443 A.2d 29, 1982 D.C. App. LEXIS 308 (D.C. 1982).

Opinions

MACK, Associate Judge:

In this contract dispute, Intercounty Construction Corporation appeals from an order of the Superior Court granting the District of Columbia’s motion for summary judgment, denying Intercounty’s motion for summary judgment and affirming the judgment of the Contract Appeals Board in favor of the District. Appeal of Intercounty Construction Corp., CAB No. 500 (Jan. 30, 1979). Specifically, Intercounty argues that Paragraph 12(f) of the Special Provisions of the District’s standard highway construction contract is ambiguous, that In-tercounty’s interpretation is reasonable, and, as such, that it is entitled to recover additional monies under the contract. We find that on this record summary judgment for appellee was improperly granted and we therefore reverse and remand.

Intercounty entered into a contract with the District in May 1974 for the construction of the H Street overpass. The contract contained the standard governmental construction projects changes clause, the pertinent section of which is as follows:

Article 3. Changes. — The Contracting Officer may at any time, by written order, and without notice to the sureties, make changes in the drawings and/or specifications of this contract and within the general scope thereof. If such changes cause an increase or decrease in the cost of performing the work under this contract, or in the time required for its performance, an equitable adjustment shall be made and the contract shall be modified in writing accordingly....

If the parties could not reach an “equitable adjustment” resort was to be made to other provisions of the contract. One such provision [Paragraph 12(f) of the Special Provisions] provided the method for calculating the rate at which the contractor or his subsidiary should be paid for the use of their equipment in the event of government requested contract changes. Such payment [31]*31will be based on an hourly rate derived by dividing the current appropriate monthly rate from the Associated Equipment Distributors’ Manual by 176 hours.... The hourly rate shall include all repair costs, freight and transportation charges, fuel, lubricants, taxes, insurance and other incidentals. No additional allowance will be made for overhead and profit.

On September 12, 1974, the District notified Intercounty to proceed with a change to the contract and to relocate steam and air lines. Subsequently, a dispute arose between Intercounty and the District as to the amount to be paid to Intercounty for work performed by its subcontractor, John J. Wilson, Inc., with respect to the change. The District paid Intercounty $146,228.00. Wilson, however, claimed it was owed an additional $16,174.15, plus interest, for the use of its equipment in performing the change order and on September 19, 1975, Intercounty, on behalf of Wilson, requested the Contracting Officer for the District to render a final decision on its claim. The Contracting Officer denied Intercounty’s claim ruling that payment was made in accordance with Paragraph 12(f) and represented an equitable adjustment for the work performed.

Intercounty appealed this decision to the Contract Appeals Board which affirmed, ruling, as a matter of law, that Paragraph 12(f) was not ambiguous, that the term “include” connoted a limitation, not an expansion and that the term “hourly rate” included “all repair costs, freight and transportation charges, fuel, lubricants, taxes, insurance and other incidentals [and that the appellant was] not entitled to additional compensation.” Appeal of Intercounty Construction Corp., supra at 6, 10-11.

Eight months thereafter, Intercounty filed a complaint in the Superior Court seeking to reverse the Board’s decision as erroneous as a matter of law. Both parties filed cross-motions for summary judgment and the court, without opinion, granted the District’s motion and entered the summary judgment from which the appellant appeals. Intercounty Construction Corp. v. District of Columbia, No. 15984-79 (July 9, 1980).

Superior Court Civil Rule 56(c) provides that summary judgment shall be granted if the materials submitted show that there is no genuine issue as to any material fact and that the moving party is entitled to a judgment as a matter of law.

The crux of this controversy, from the legal standpoint, is whether the additional costs (as of repair, freight, etc.) enumerated in Paragraph 12(f) are included or excluded from the Associated Equipment Distributors’ Manual-based hourly rate to be paid for contractor-owned equipment.1 The appellant asserts that its subcontractor is entitled to the additional costs over and above the AED-based hourly rate while the District contends that the appellant’s award is limited to the AED-based hourly rate. Thus, the appellant argues that the “based on” language of Paragraph 12(f) indicates that other charges will be added onto the AED hourly rate and that the provision’s “included” language indicates an intent to expand upon the hourly rate and, therefore, allow for greater remuneration to contractors performing change orders. On the other hand, the District interprets “included” to mean confine or contain; in other words, that the AED hourly rate is to embrace repair costs, etc. while retaining its character as an hourly rate.2

At this level we are persuaded by the logic of appellant’s argument. In our view, the most reasonable language interpretation, read narrowly from hindsight, is that the only additional costs which shall not be paid to a contractor pursuant to a change order are those for overhead and profit.

Clearly, if, as the District concludes, the costs of repair, freight and transportation, fuel, lubrication, taxes, insurance and other incidentals are to be excluded they would, or should, have been treated as were over[32]*32head and allowance costs. In other words, that the drafters specifically excluded two types of costs from payment by stating “no additional allowance will be made for overhead and profit” leads inexorably to the conclusion that repair costs, etc., are not to be subsumed by the AED hourly rate but are to be paid to contractors performing change orders over and above the AED hourly rate. Any other interpretation would tend to leave Paragraph 12(f)’s “[n]o additional allowance” language useless, inexplicable, inoperative, meaningless or superfluous and, hence, should be rejected. Ball State University v. United States, 488 F.2d 1014, 1016 (Ct.Cl.1973). See generally Moran v. Audette, D.C.App., 217 A.2d 653 (1966). Therefore, as Paragraph 12(f) is now drafted, the AED based-rate does not include the costs of repair, etc. If the District intended to limit payment to the AED-based rate it could easily have done so and, exercising its legislative prerogative, could now redraft Paragraph 12(f) to reflect that intent more clearly.

Our analysis does not end here, however. While we view Intercounty’s interpretation of Paragraph 12(f) as the more reasonable one, the court’s ruling with respect to the grant of summary judgment deserves closer scrutiny.

The first step in contract interpretation is determining what a reasonable person in the position of the parties would have thought the disputed language meant. District of Columbia Department of Housing and Community Development v. Pitts,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

David Kirdassi v. Mitchell Scott White, DC
Court of Appeals of Virginia, 2025
Carome v. Carome
District of Columbia Court of Appeals, 2023
Girma Aboye v. United States
121 A.3d 1245 (District of Columbia Court of Appeals, 2015)
NEST AND TOTAH VENTURE, LLC v. Deutsch
31 A.3d 1211 (District of Columbia Court of Appeals, 2011)
DLY-Adams Place, LLC v. Waste Manangement of MaryLand, Inc.
2 A.3d 163 (District of Columbia Court of Appeals, 2010)
Tsintolas Realty Co. v. Mendez
984 A.2d 181 (District of Columbia Court of Appeals, 2009)
Cevasco v. National Railroad Passenger Corp.
606 F. Supp. 2d 401 (S.D. New York, 2009)
United States v. Allegheny Jefferson Millwork, LLC
540 F. Supp. 2d 165 (District of Columbia, 2008)
Steele Foundations, Inc. v. Clark Construction Group, Inc.
937 A.2d 148 (District of Columbia Court of Appeals, 2007)
C & E SERVICES, INC. v. Ashland, Inc.
498 F. Supp. 2d 242 (District of Columbia, 2007)
Anderson v. District of Columbia Housing Authority
923 A.2d 853 (District of Columbia Court of Appeals, 2007)
Anderson v. DIST. OF COL. HOUS. AUTH.
923 A.2d 853 (District of Columbia Court of Appeals, 2007)
Segar v. Ashcroft
422 F. Supp. 2d 117 (District of Columbia, 2006)
Akassy v. William Penn Apartments Ltd. Partnership
891 A.2d 291 (District of Columbia Court of Appeals, 2006)
In Re Bailey
883 A.2d 106 (District of Columbia Court of Appeals, 2005)
Richardson v. Nationwide Mutual Insurance
826 A.2d 310 (District of Columbia Court of Appeals, 2003)
Greene v. Rumsfeld
266 F. Supp. 2d 125 (District of Columbia, 2003)
Potomac Electric Power Co. v. Mirant Corporation
251 F. Supp. 2d 144 (District of Columbia, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
443 A.2d 29, 1982 D.C. App. LEXIS 308, Counsel Stack Legal Research, https://law.counselstack.com/opinion/intercounty-construction-corp-v-district-of-columbia-dc-1982.