United States v. Allegheny Jefferson Millwork, LLC

540 F. Supp. 2d 165, 2008 U.S. Dist. LEXIS 25851
CourtDistrict Court, District of Columbia
DecidedMarch 31, 2008
DocketCivil Action 06-875(RCL)
StatusPublished
Cited by2 cases

This text of 540 F. Supp. 2d 165 (United States v. Allegheny Jefferson Millwork, LLC) is published on Counsel Stack Legal Research, covering District Court, District of Columbia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Allegheny Jefferson Millwork, LLC, 540 F. Supp. 2d 165, 2008 U.S. Dist. LEXIS 25851 (D.D.C. 2008).

Opinion

MEMORANDUM OPINION

ROYCE C. LAMBERTH, District Judge.

This matter comes before the Court on the parties’ cross-motions for partial summary judgment. The Court has considered defendants’ motion [25], plaintiffs consolidated opposition and motion [28, 29], defendants’ consolidated reply and opposition [30, 31, 33], plaintiffs consolidated *167 surreply and reply [32, 34], the entire record herein, and the applicable law. For the reasons set forth below, defendants’ motion [25] will be GRANTED in part and DENIED in part; plaintiffs motion [28] will be DENIED.

BACKGROUND

This contract dispute arises from the recently-completed construction of an annex to the E. Barrett Prettyman Courthouse on Constitution Avenue in Washington, D.C. — in which, incidentally, this Court now sits. After securing the principal contract from the General Services Administration (“GSA”), Centex Construction Company (“Centex”) engaged subcontractors to complete the project’s various elements. 1 (Compl. ¶¶ 8,10.) On October 17, 2004, Centex selected Allegheny Jefferson Millwork, LLC (“Allegheny”), a joint venture formed by two Pennsylvania corporations, to fabricate and install architectural millwork and casework. 2 (Def. Statement of Undisputed Mat. Facts ¶¶ 1, 2.) Allegheny turned to plaintiff D.L.I. Incorporated (“DLI”) to supply labor for its portion of the project, and DLI then contracted (sub-sub-subcontracted) with Craftsmanship Unlimited (“Craftsmanship”) and Shalom Carpentry (“Shalom”). (Id ¶¶ 4, 5.)

Except where expressly indicated, the following facts are not in dispute.

1. Lump-Sum & Time and Materials Contracts

Allegheny subcontracted two groups of tasks to DLI: installation of materials fabricated by Allegheny on the first, fifth, and sixth floors, under a lump-sum contract, and installation of materials fabricated by another company on the second, third, and fourth floors, on a time and materials (“T & M”) basis. (Corrigan Dep. 8-9; Lacy Dep. 13-14.) Initially, the parties verbally agreed to a price of $1,175,000 for the lump-sum contract work and to specific per hour rates for the T & M portion. (Compl. ¶ 12; Corrigan Dep. 24; Def. Statement of Undisputed Mat. Facts ¶ 8; PI. Second Consol. Mem. 4.) DLI commenced performance on approximately December 5, 2004. (Id at 20.) Allegheny emailed DLI a “scope of work” document four days later (Lacy Dep. 77-78.)

One of the joint venturers, Jefferson Millwork & Design, Inc. (“Jefferson”), had previously collaborated with DLI on construction of the Smithsonian’s National Museum of the American Indian, and as of early 2005, Jefferson still owed DLI some amount of money for its services on that project. (See Corrigan Dep. 24, 27; PL Ex. 1.) In an email on December 22, 2004, Michael Corrigan — Jefferson’s general manager and a manager of Allegheny— proposed that if Jefferson failed to remit the balance to DLI by January 9, 2005 (which it did not do), the Allegheny-DLI lump-sum contract price would rise to $1,250,000. (Corrigan Dep. 5, 6, 27, 29; Def. Ex. 11; Pl. Ex. 1.)

On February 12, 2005, Allegheny sent DLI a nine-page, unsigned, standard form subcontract. (Compl. ¶ 14; Def. Ex. 5.) DLI’s president, Dale Lacy, signed and returned the contract, with extensive mark-ups and revisions, on April 5, 2005. (See Def. Ex. 5 at 1; Def. Ex. 6; Compl. ¶ 14.) Corrigan testified he signed the altered version on Allegheny’s behalf “when we received it or thereafter” and *168 filed it for accounting purposes. (Corrigan Dep. 37.) Allegheny did not return a signed copy to DLI until after DLI filed its complaint in this case, but Lacy apparently assumed his changes had been accepted in April. (Lacy Dep. 76; Def. Ex. 6.) DLI nonetheless asserts the parties have no valid written contract because it never received a signed copy back from Allegheny. (Lacy Dep. 76; PI. First Con-sol. Mem. 13.)

To date, Allegheny has paid DLI $1,163,250 on the lump-sum contract. (See Def. Statement of Undisputed Facts ¶ 2; PI. First Consol. Mem. 3.) Allegheny contends only $11,750 remains due. (Def. Statement of Undisputed Mat. Facts ¶ 11.) DLI, however, insists the true contract price is $1,250,000, and thus Allegheny still owes it $86,750. (PI. Second Consol. Mem. 5.) DLI now seeks summary judgment on this issue. (PI. First Consol. Mem. 2.)

2. Davis-Bacon Issues

The Davis-Bacon Act (“Davis-Bacon”), 40 U.S.C. section 3141 et seq., requires that workers on most District of Columbia or federally-assisted construction contracts be paid no less than the prevailing wage and fringe benefit rates in their project’s geographic area. 40 U.S.C. § 3142 (2008). See also 29 C.F.R. § 5.5 (2008) (implementing regulations).

At their first meeting on October 5, 2004, Centex informed Allegheny that Davis-Bacon rates would apply to the courthouse project. (Corrigan Dep. 39-40.) Allegheny, in turn, notified DLI, faxing the appropriate wage tables on October 5, 2004 and again on January 5, 2005. (Def. Statement of Undisputed Mat. Facts ¶¶ 15, 16; PI. First Consol. Mem. 2.) Lacy, however, claims he first learned Davis-Bacon applied to the courthouse project in February 2005. (Lacy Dep. 29-30, 39-40.) Around that time, two laborers employed by one of DLI’s subcontractors complained of underpayment to a GSA representative. (Lacy Dep. 30-32; Corrigan Dep. 48.)

Many of DLI’s own laborers and its subcontractors’ laborers had traveled from outside the Washington, D.C. area to work on the courthouse project. (Lacy Dep. 52-53.) Thus, they received per diem in addition to their wages and other fringe benefits. (See id.) Allegheny and DLI initially assumed that this per diem could count toward the Davis-Bacon minimum fringe benefit figure, but first GSA, and later the Department of Labor (“DOL”), disagreed. (PI. First Consol. Mem. 4; Def. Resp. to Pl.’s Statement of Undisputed Mat. Facts 6.) Over the next few months, the parties discussed the Davis-Bacon issue repeatedly, (Lacy Dep. 35-37; Corrigan Dep. 50-52), and Lacy claims he informed Corrigan verbally, though never in writing, that if DOL’s position was correct, DLI would need to stop work and renegotiate the entire project, (Lacy Dep. 35-37). Throughout this period, Corrigan represented to Lacy that Allegheny would continue to advocate the parties’ joint position to DOL and suggested that it might shoulder some portion of any ultimate liability. 3 (Corrigan Dep. 55-56.) To assist with its advocacy efforts, Allegheny retained counsel who produced two documents — an “advocacy letter” marshaling legal authority for the parties’ position and a client opinion letter acknowledging the issue was, legally, an open one — both of which Allegheny provided to DLI. (Corrigan Dep.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
540 F. Supp. 2d 165, 2008 U.S. Dist. LEXIS 25851, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-allegheny-jefferson-millwork-llc-dcd-2008.