Dorey Electric Co. v. Pittman Mechanical Contractors, Inc.

789 F. Supp. 734, 1992 U.S. Dist. LEXIS 5801, 1992 WL 77922
CourtDistrict Court, E.D. Virginia
DecidedApril 16, 1992
DocketCiv. A. 91-332-N
StatusPublished
Cited by2 cases

This text of 789 F. Supp. 734 (Dorey Electric Co. v. Pittman Mechanical Contractors, Inc.) is published on Counsel Stack Legal Research, covering District Court, E.D. Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dorey Electric Co. v. Pittman Mechanical Contractors, Inc., 789 F. Supp. 734, 1992 U.S. Dist. LEXIS 5801, 1992 WL 77922 (E.D. Va. 1992).

Opinion

MEMORANDUM OPINION AND ORDER

PRINCE, United States Magistrate Judge.

This matter comes before the Court on the cross motions of plaintiff Dorey Electric Company (“Dorey”) and defendant Reliance Insurance Company (“Reliance”) for Summary Judgment. The parties have consented to proceed before a United States Magistrate Judge pursuant to 28 U.S.C. § 636(c). A hearing was held on March 26, 1992, at which Dorey was represented by Patrick H. O’Donnell, Esquire, and Reliance was represented by Richard S. Gordon, Esquire, and Richard W. Schwartzman, Esquire.

STATEMENT OF THE CASE .

A. Factual Background

In June 1988, the United States Department of the Navy (“Navy”) awarded to Dorey Electric Company a contract (“Prime Contract”) for the repair of two piers at the Norfolk Naval Station. As required by law, the prime contract contained a stipulation that the primary contractor, in this case Dorey, and all subcontractors hired by Dorey to perform work on the contract would comply with the provisions of the Davis-Bacon Act, 40 U.S.C. § 276a et seq., and the Contract Work Hours and Safety Standards Act (CWHSSA), 40 U.S.C. § 327 et seq. Those statutes set out certain wage and hour requirements for mechanics, laborers and other private-sector employees performing work on certain government contracts.

Dorey subsequently entered into a subcontract with Pittman Mechanical Contractors, Inc. (“Pittman”) in which Pittman agreed to perform the mechanical work required on the two piers under the prime contract in exchange for payment of $1,238,945.00. Under the terms of the subcontract, Pittman was obligated to comply with the Davis-Bacon Act and the CWHSSA. Dorey also required that Pittman post a bond in the amount of the subcontract guaranteeing Pittman’s prompt and faithful performance of its obligations under the subcontract. Reliance was named surety on the bond provided by Pittman.

By letter dated September 19, 1990, the contracting officer for the Navy informed Dorey that a preliminary investigation of *736 Pittman revealed violations of the Davis-Bacon Act and the CWHSSA and that certain Pittman employees were entitled to restitution totalling $106,867.26 in Davis-Bacon Act violations and $770.00 in liquidated damages for CWHSSA violations. At that time, the Navy informed Dorey that, as provided by the prime contract, the remainder of the amount due Dorey under the prime contract, $25,220.00, would be withheld until Pittman made the required restitution to its employees. Further, the September 19, 1990 letter informed Dorey that any restitution not made by Pittman would be deducted from other government contracts on which Dorey was the prime contractor.

On March 12, 1992, well after the filing of this lawsuit and only days before the filing of the motions currently before this Court, the Navy issued a revised determination of the restitution due to Pittman employees for work done under the subcontract with Dorey. The Navy currently maintains that certain Pittman employees are due a total of $102,406.83 in restitution for Davis-Bacon Act violations and $800.00 in liquidated damages under the CWHSSA. The March 12 letter also stated that all but $2004.39 of the payments to Dorey previously withheld by the Navy had been applied to reimburse various employees for federal violations committed by Dorey. Thus, $2004.39 due to Dorey is being held by the Navy, pending a final decision by the Secretary of Labor, to provide restitution to employees of Pittman; an additional $101,202.44 is subject to being withheld from payments on current and future government contracts held by Dorey.

B. Procedural History

Dorey filed its complaint in this Court on May 30, 1991. Count One of the complaint seeks damages in the amount of $107,-637.26 1 for breach of contract jointly and severally against Pittman and Reliance. Count Two seeks a declaratory judgment against the defendants, holding them liable to Dorey in the same amount for Davis-Bacon and CWHSSA violations.

Neither defendant filed responsive pleadings within the time permitted by the Federal Rules of Civil Procedure, and their defaults were noted on the docket on July 18, 1991. Reliance subsequently moved to set aside the default against it. That motion was granted and Reliance’s answer was filed on October 9, 1991. A default judgment was entered against Pittman on November 22, 1991. According to the parties, Pittman is currently in Chapter 7 bankruptcy. Dorey filed its Motion for Summary Judgment on March 13, 1992, to which Reliance responded on March 24, 1992. Reliance filed its Motion for Summary Judgment on March 20, 1992; 2 Do-rey filed its response on March 25, 1992.

DISCUSSION

Reliance contends that this Court is without subject-matter jurisdiction over this action. Dorey alleges in its complaint that this action arises under the Miller Act, 40 U.S.C. § 270a et seq., the Davis-Bacon Act, 40 U.S.C. § 276a, and the Federal Declaratory Judgment Act, 28 U.S.C. § 2201. Implicit in this allegation is the contention that federal jurisdiction is thereby conferred by 28 U.S.C. § 1331 3 and 28 U.S.C. § 1337. 4

The parties are in agreement that the Federal Declaratory Judgment Act is not in and of itself an independent source of jurisdiction. Rather, the Act provides a *737 procedural remedy in certain cases already within the jurisdiction of the district court. See 28 U.S.C. § 2201. Nor does the Miller Act provide for federal jurisdiction over this action. The Miller Act requires a prime contractor to post a performance bond prior to being awarded a government contract over $25,000 in amount for the construction or repair of any public work of the United States. 40 U.S.C. § 270a. The Act provides federal jurisdiction over actions brought by subcontractors, laborers and materialmen, in the name of the United States, for nonpayment by the prime contractor in lieu of a state law mechanic’s lien. See 28 U.S.C.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Allegheny Jefferson Millwork, LLC
540 F. Supp. 2d 165 (District of Columbia, 2008)
Handyman Network, Inc. v. Westinghouse Savannah River Co.
868 F. Supp. 151 (D. South Carolina, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
789 F. Supp. 734, 1992 U.S. Dist. LEXIS 5801, 1992 WL 77922, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dorey-electric-co-v-pittman-mechanical-contractors-inc-vaed-1992.