Ball, Ball & Brosamer, Inc. v. Robert B. Reich, Secretary of Labor

24 F.3d 1447, 39 Cont. Cas. Fed. 76,669, 306 U.S. App. D.C. 339, 2 Wage & Hour Cas.2d (BNA) 132, 1994 U.S. App. LEXIS 14195, 1994 WL 247128
CourtCourt of Appeals for the D.C. Circuit
DecidedJune 10, 1994
Docket92-5366
StatusPublished
Cited by30 cases

This text of 24 F.3d 1447 (Ball, Ball & Brosamer, Inc. v. Robert B. Reich, Secretary of Labor) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ball, Ball & Brosamer, Inc. v. Robert B. Reich, Secretary of Labor, 24 F.3d 1447, 39 Cont. Cas. Fed. 76,669, 306 U.S. App. D.C. 339, 2 Wage & Hour Cas.2d (BNA) 132, 1994 U.S. App. LEXIS 14195, 1994 WL 247128 (D.C. Cir. 1994).

Opinion

Opinion for the Court filed by Circuit Judge SENTELLE.

SENTELLE, Circuit Judge:

Appellant Ball, Ball & Brosamer, Inc. (“Ball”) appeals from an order of the district court granting summary judgment in favor of the Secretary of Labor in an action to review the Secretary’s determination that Ball and its subcontractor violated the Davis-Bacon Act while performing work on a federal construction project. Ball maintains that the district court erred in concluding that the terms of its contract with the government barred judicial review of its claims and that the regulations under which the Secretary acted were a reasonable interpretation of the Davis-Bacon Act. For the reasons set forth below, we conclude that appellant is correct on both counts and order the district court to enter summary judgment in Ball’s favor.

I. BACKGROUND

In September 1985, Ball entered into a $14.5 million contract with the Department of Interior’s Bureau of Reclamation to construct thirteen miles of the Tucson Aqueduct between Phoenix and Tucson, Arizona. Ball subcontracted with Red Rock Products, Inc., an Arizona-based company, for the concrete and gravel it needed for the project. Red *1449 Rock obtained raw materials from a local sand and gravel pit and set up a portable batch plant for mixing concrete. The borrow pit and batch plant were located about two miles from the construction site at its nearest point.

The Wage and Hour Division of the Department of Labor began an investigation to determine whether Red Rock’s pay practices conformed with the Davis-Bacon Act, 40 U.S.C. § 276a(a) (1988). The Act requires generally that laborers and mechanics under covered government contracts will be paid at least the prevailing wages for corresponding classes in the area of performance of the contract as determined by the Secretary of Labor. See id. By its terms, it applies to “all mechanics and laborers employed directly upon the site of the work.” Id. (emphasis added). The Division found Red Rock’s employees to be covered by the Act. As the Division also found that they had not received prevailing wages, it concluded that Red Rock and Ball 1 had violated the Act. The Division notified the Bureau of Reclamation of its findings, and the Bureau of Reclamation withheld $60,976.71 from the contract price owed to Ball for back wages relating to the alleged Davis-Bacon violations. See id. §§ 276a(a) & 276a-2(a) (authorizing withholding and repayment of wages due under Act).

Ball filed a petition for review with the Wage Appeals Board, 2 arguing that the Red Rock batch plant and borrow pit were not “directly upon the site of the work” within the meaning of the Act. The Board denied the petition, stating that the facts of record supported a finding that Red Rock’s borrow pit and batch plant were on the site of the work, as the Secretary’s regulations define that phrase. The Secretary’s regulations provide:

Except as provided in paragraph (l )(3) of this section, fabrication plants, mobile factories, batch plants, borrow pits, job headquarters, tool yards, etc., are part of the site of the work provided they are dedicated exclusively, or nearly so, to performance of the contract or project, and are so located in proximity to the actual construction location that it would be reasonable to include them.

29 C.F.R. § 5.2(1 )(2) (1993).

After the Wage Appeals Board denied the petition for review, Ball brought suit in the U.S. District Court for the District of Columbia. On cross-motions for summary judgment, the District Court ruled in favor of the Secretary. See Ball, Ball & Brosamer, Inc. v. Martin, 800 F.Supp. 967 (D.D.C.1992). The district court first held that Ball’s challenge to the validity of the Secretary’s regulations was precluded by the terms of its contract with the government. Paragraph 1.7.9 of Ball’s contract with the Bureau of Reclamation, referred to by the parties as the “incorporation clause,” provided that “[a]ll rulings and interpretations of the Davis-Bacon and Related Acts contained in 29 C.F.R. Parts 1, 3, and 5 are herein incorporated by reference in this contract.” The district court accepted the Secretary’s position that in the incorporation clause, Ball agreed to abide by the Secretary’s definition of “site of the work” found in Part 5 of the regulations and therefore could not challenge the regulations as inconsistent with the Davis-Bacon Act. Id. at 971-73.

The district court also held that even if Ball were not contractually precluded from bringing its challenge, the Secretary’s regulations at § 5.2(1 )(2) were a reasonable interpretation of the statutory phrase “directly upon the site of the work.” Id. at 976. In so holding, the district court rejected Ball’s argument that this court’s opinion in Building & Construction Trades Dep’t., AFL-CIO v. United States Dep’t. of Labor Wage Appeals Board, 932 F.2d 985 (D.C.Cir.1991) (the *1450 “Midway ” decision), required a strict geographical proximity test for evaluating what areas are “directly upon the site of the work” for purposes of the Davis-Bacon Act. Id. at 973-75.

II. Discussion

A. Standard of Review

Because the parties agree that there are no genuine issues of material fact in dispute here, this court’s only task on appeal is to ensure that the district court properly applied the relevant law to the undisputed facts. Beckett v. Air Line Pilots Ass’n, 995 F.2d 280, 284 (D.C.Cir.1993). Like the district court, our review of the Secretary’s conclusion that Ball violated the Davis-Bacon Act is limited to determining whether the Secretary’s decision was arbitrary, capricious, or contrary to law within the meaning of the APA. Dr. Pepper/Seven-Up Companies v. FTC, 991 F.2d 859, 862 (D.C.Cir.1993); 5 U.S.C. § 706(2)(A) (1988). We examine de novo the legal question whether judicial review of Ball’s claims can be limited pursuant to the terms of its contract with the government. See HOH Co. v. Travelers In-dem. Co., 903 F.2d 8, 12 n. 6 (D.C.Cir.1990).

B. The Reviewability of Ball’s APA Claims

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Judith Pietersen v. DOS
138 F.4th 552 (D.C. Circuit, 2025)
Felix Payan v. Warden
C.D. California, 2025
Hikvision USA, Inc. v. FCC
97 F.4th 938 (D.C. Circuit, 2024)
United States v. Antoinette Adair
38 F.4th 341 (Third Circuit, 2022)
Sheet Metal Workers' International Ass'n, Local 104 v. Duncan
229 Cal. App. 4th 192 (California Court of Appeal, 2014)
Del Villar v. Flynn Architectural Finishes, Inc.
893 F. Supp. 2d 201 (District of Columbia, 2012)
Bockelman Trucking v. Pennsylvania Prevailing Wage Appeals Board
30 A.3d 616 (Commonwealth Court of Pennsylvania, 2011)
United States Ex Rel. Wall v. Circle Construction, LLC
700 F. Supp. 2d 926 (M.D. Tennessee, 2010)
Sykes v. Dudas
573 F. Supp. 2d 191 (District of Columbia, 2008)
United States v. Allegheny Jefferson Millwork, LLC
540 F. Supp. 2d 165 (District of Columbia, 2008)
Abhe & Svoboda, Inc. v. Chao
508 F.3d 1052 (D.C. Circuit, 2007)
Mistick PBT v. Chao, Elaine
440 F.3d 503 (D.C. Circuit, 2006)
Phoenix-Griffin Group II, Ltd. v. Chao
376 F. Supp. 2d 234 (D. Rhode Island, 2005)
McBride Cotton and Cattle Corp. v. Veneman
296 F. Supp. 2d 1125 (D. Arizona, 2003)
Glazer Construction Co. v. United States
52 Fed. Cl. 513 (Federal Claims, 2002)
Long v. Interstate Ready-Mix, L.L.C.
83 S.W.3d 571 (Missouri Court of Appeals, 2002)
State, Bus. & Indus. v. Granite Constr. Co.
40 P.3d 423 (Nevada Supreme Court, 2002)
Chevron U.S.A., Inc. v. Federal Energy Regulatory Commission
193 F. Supp. 2d 54 (District of Columbia, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
24 F.3d 1447, 39 Cont. Cas. Fed. 76,669, 306 U.S. App. D.C. 339, 2 Wage & Hour Cas.2d (BNA) 132, 1994 U.S. App. LEXIS 14195, 1994 WL 247128, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ball-ball-brosamer-inc-v-robert-b-reich-secretary-of-labor-cadc-1994.