Bailey Specialized Buildings, Inc. v. The United States

404 F.2d 355, 186 Ct. Cl. 71, 1968 U.S. Ct. Cl. LEXIS 212
CourtUnited States Court of Claims
DecidedDecember 13, 1968
Docket90-67
StatusPublished
Cited by31 cases

This text of 404 F.2d 355 (Bailey Specialized Buildings, Inc. v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bailey Specialized Buildings, Inc. v. The United States, 404 F.2d 355, 186 Ct. Cl. 71, 1968 U.S. Ct. Cl. LEXIS 212 (cc 1968).

Opinion

SKELTON, Judge.

This is a contract case wherein the plaintiff seeks damages for a breach of contract or an equitable adjustment under the contract resulting from an alleged wrongful termination for default of the contract by the defendant. The defendant asserts a counterclaim growing out of excess costs suffered by it when required to pay an amount above plaintiff’s contract price to another contractor who supplied the products involved after plaintiff’s contract was terminated by the Government.

The facts involved in this case are substantially as follows:

The plaintiff was engaged in the business of fabrication and erection of steel structures. The defendant awarded firm fixed price Contract No. DA-36-109ENG-7523 on September 26, 1963, for the fabrication of three unassembled Radome Support Towers at a unit price of $12,400 each or a total contract price of $37,200. These towers will be referred to as production towers. Two of them were to be delivered on August 27, 1964, and the third on September 27, 1964. Each tower was to contain approximately 25,000 pieces of material and would weigh about 30 tons. The towers were to be 25 feet high and 50 feet in diameter and were to be fabricated in accordance with drawings and specifications furnished by defendant’s contracting officer. As a part of the contract, it was agreed that the plaintiff would furnish a preproduction model to the defendant for examination and tests. This portion of the contract was stated in the following language:

As soon as practicable after award of the contract and prior to submission of any units for final acceptance, the contractor shall furnish a preproduction model for examination and test to determine conformance to this purchase description.

On November 1, 1963, the parties agreed that the first production model would be considered to be the preproduction model. 1 The contract contained standard “dispute,” “default,” and “termination for convenience” clauses. Pertinent portions of the default clause of the contract are as follows:

11. Default

(a) The Government may, subject to the provisions of paragraph (c) below, by written Notice of Default to the Contractor terminate the whole or any part of this contract in any one of the following circumstances:

(i) if the Contractor fails to make delivery of the supplies or to perform the services within the time specified herein or any extension thereof; or

*357 (ii) if the Contractor fails to perform any of the other provisions of this contract, or so fails to make progress as to endanger performance of this contract in accordance with its terms, and in either of these two circumstances does not cure such failure within a period of 10 days (or such longer period as the Contracting Officer may authorize in writing) after receipt of notice from the Contracting Officer specifying such failure.

(b) In the event the Government terminates this contract in whole or in part as provided in paragraph (a) of this clause, the Government may procure, upon such terms and in such manner as the Contracting Officer may deem appropriate, supplies or services similar to those so terminated, and the Contractor shall be liable to the Government for any excess costs for such similar supplies or services, Provided, That the Contractor shall continue the performance of this contract to the extent not terminated under the provisions of this clause.

(c) Except with respect to defaults of subcontractors, the Contractor shall not be liable for any excess costs if the failure to perform the contract arises out of causes beyond the control and without the fault or negligence of the Contractor. Such causes may include, but are not restricted to, acts of God or of the public enemy, acts of the Government in either its sovereign or contractual capacity, fires, floods, epidemics, quarantine restrictions, strikes, freight embargoes, and unusually severe weather; but in every case the failure to perform must be beyond the control and without the fault or negligence of the Contractor. If the failure to perform is caused by the default of a subcontractor, and if such default arises out of causes beyond the control of both the Contractor and subcontractor, and without the fault or negligence of either of them, the Contractor shall not be liable for any excess costs

for failure to perform, unless the supplies or services to be furnished by the subcontractor were obtainable from other sources in sufficient time to permit the Contractor to meet the required delivery schedule.

* * * * * *

(e) If, after notice of termination of this contract under the provisions of this clause, it is determined for any reason that the Contractor was not in default under the provisions of this clause, or that the default was excusable under the provisions of this clause, the rights and obligations of the parties shall, if the contract contains a clause providing for termination for convenience of the Government, be the same as if the notice of termination had been issued pursuant to such clause.

*•»•***

The plaintiff entered upon the performance of the contract and in due time discovered errors in the drawings that had been furnished to it by the Government. This discovery was made after the plaintiff had fabricated a substantial portion of the 75,000 parts which were required for the construction of the towers. The errors were called to the attention of the contracting officer of the defendant and he furnished revised drawings to the plaintiff on August 26, 1964. These revised drawings caused the plaintiff to scrap many parts already fabricated and it was required to remake many of such parts in order to comply with the new drawings. These changes caused serious delay in the production of the required parts. In the meantime, the delivery date for the first two production towers, namely, August 27/ 1964, had passed and four weeks later the date of delivery of the third tower had also passed without the plaintiff being able to make delivery. The parties exchanged various letters and had numerous conversations during this period of time and it became clear that the defendant had *358 waived the original contract delivery-dates. 2

On October 9, 1964, the contracting officer wrote a letter to plaintiff requesting a new delivery schedule. This letter briefly reviewed the history of the dealings between the parties and stated:

Accordingly, you are directed within 14 calendar days after receipt of this letter to present a completely acceptable preproduction model in accordance with Paragraph 3.2 in the purchase description and to furnish evidence of your* ability to make delivery of the 3 units within a reasonable time thereafter.
Your failure to comply with the foregoing will result in termination in accordance with Paragraph 11, Default, of the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

5860 Chicago Ridge, LLC v. United States
104 Fed. Cl. 740 (Federal Claims, 2012)
NCLN20, Inc. v. United States
99 Fed. Cl. 734 (Federal Claims, 2011)
In Re NextWave Personal Communications Inc.
244 B.R. 253 (S.D. New York, 2000)
Dano Resource Recovery, Inc. v. District of Columbia
620 A.2d 1346 (District of Columbia Court of Appeals, 1993)
Composite Laminates, Inc. v. United States
38 Cont. Cas. Fed. 76,453 (Federal Claims, 1992)
Al Johnson Construction Co. v. United States
36 Cont. Cas. Fed. 75,850 (Court of Claims, 1990)
Jackson v. United States
12 Cl. Ct. 363 (Court of Claims, 1987)
Timberland Paving & Construction Co. v. United States
33 Cont. Cas. Fed. 73,781 (Court of Claims, 1985)
Stoner-Caroga Corp. v. United States
31 Cont. Cas. Fed. 71,370 (Court of Claims, 1983)
Cervetto Building Maintenance Co. v. United States
30 Cont. Cas. Fed. 71,058 (Court of Claims, 1983)
Pinewood Realty Ltd. Partnership v. United States
617 F.2d 211 (Court of Claims, 1980)
Inforex, Inc.
650 F.2d 286 (Court of Claims, 1980)
Kisco Co. v. United States
610 F.2d 742 (Court of Claims, 1979)
Simmonds Precision Products, Inc. v. United States
546 F.2d 886 (Court of Claims, 1976)
Kaminer Construction Corp. v. United States
488 F.2d 980 (Court of Claims, 1973)
Astro Science Corp. v. United States
471 F.2d 624 (Court of Claims, 1973)
Doyle Shirt Manufacturing Corp. v. United States
462 F.2d 1150 (Court of Claims, 1972)
The Beryllium Corporation v. The United States
449 F.2d 362 (Court of Claims, 1971)

Cite This Page — Counsel Stack

Bluebook (online)
404 F.2d 355, 186 Ct. Cl. 71, 1968 U.S. Ct. Cl. LEXIS 212, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bailey-specialized-buildings-inc-v-the-united-states-cc-1968.