Vecco Construction Industries, Inc. v. Century Construction Co. of Washington (In Re Vecco Construction Industries, Inc.)

30 B.R. 945, 1983 Bankr. LEXIS 5959
CourtUnited States Bankruptcy Court, E.D. Virginia
DecidedJune 21, 1983
Docket15-34933
StatusPublished
Cited by8 cases

This text of 30 B.R. 945 (Vecco Construction Industries, Inc. v. Century Construction Co. of Washington (In Re Vecco Construction Industries, Inc.)) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, E.D. Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Vecco Construction Industries, Inc. v. Century Construction Co. of Washington (In Re Vecco Construction Industries, Inc.), 30 B.R. 945, 1983 Bankr. LEXIS 5959 (Va. 1983).

Opinion

MEMORANDUM OPINION

MARTIN V.B. BOSTETTER, Jr., Bankruptcy Judge.

This case arises from a dispute between a general contractor and a concrete subcontractor over the dismissal of the subcontractor. At issue are the propriety of the termination and the amount and value of the work performed by the subcontractor.

The plaintiff, Vecco Construction Industries, Inc. (“Vecco”), was the concrete subcontractor and the defendant, Century Construction Company of Washington, D.C., Inc. (“Century”), the general contractor on a project known as The Flour Mill in Washington, D.C. Vecco began work on October 23, 1978, pursuant to oral notice from Century to proceed. On January 12, 1979, the parties executed a written contract which is dated December 8, 1978. Century terminated Vecco on April 27,1979 before Vecco had completed its work on the project.

On March 14, 1979, approximately six weeks prior to the termination, Vecco had filed a Chapter XI reorganization proceeding in this Court. Century eventually filed a proof of claim in Veeco’s Chapter XI proceeding in a final amended amount of $3,721,579.89 which Century attributed to concrete cost overruns and delay damages caused by Vecco. Vecco objected to the claim and filed a counterclaim amended in amount during this proceeding to $440,-767.30, which Vecco asserts is due under its contract and for its materials not returned from the job site. Prior to trial, this Court granted summary judgment against Century on the concrete cost overruns and delay damages issues based upon the fact that Century had been reimbursed by the owner for the concrete cost overruns and has not yet suffered a judgment or otherwise paid any delay damages. 1

Vecco argues that its termination was improper because Century failed to give seven days written notice of the termination, as required by the contract, and that Vecco had cured any default involving manpower shortage prior to termination. In addition, Vecco argues that Century had materially breached the contract prior to terminating Vecco by failing to pay Vecco’s requisitions as they become due and, therefore, could not demand adherence to the terms of the contract by Vecco.

*948 Century argues that Vecco failed to maintain the mutually-agreed work schedule or provide adequate manpower for the job, and that Vecco had become “insolvent” by the time of the filing for relief under Chapter XI, any of which defaults could trigger Century’s right to terminate if not cured within seven days following written notice of the default. Century next contends that Vecco over-billed for its work and billed in a manner at variance with the contract.

It is Century’s position that Vecco waived any automatic right to payment by the tenth of the month by accepting varying terms, including direct funding of Vecco’s payroll by Century. In addition, Century argues that any one of several documents, beginning with a December 28, 1978 telegram demanding more Vecco workers, satisfied the requirement of written notice and gave Century the right to terminate after seven days if the condition had not been remedied.

Vecco contends that Century’s failure to pay Vecco’s requisitions promptly, according to the terms of the contract, was a material breach of that contract which prevents any subsequent breach by Vecco from being asserted as a ground for termination. Vecco’s requisitions were due to Century by the twenty-fifth of the month in which the work was performed. Under the original draft of the Vecco-Century contract, Century’s payments to Vecco would not have been due until five days after Century received payment from the owner. Vecco requested and Century agreed to an alteration of this provision that made payments to Vecco due no later than the tenth day of the month following submission of the requisition.

It is Vecco’s position that the contract, as altered and ultimately executed, creates in Vecco an unconditional right to payment on the tenth day of the month following presentation of the requisition. In support, Vecco cites United States v. Curtis T. Bedwell & Sons, Inc., 506 F.Supp. 1324, 1327 (E.D.Pa.1981), and United States v. Community Science Technology, Inc., 574 F.2d 1292, 1295 n. 3 (5th Cir.1978). Vecco asserts further that any delay by Vecco in submitting a requisition should be disregarded because Century, in fact, included Vecco’s requisition amount in Century’s own requisitions to the owner. Lastly, Vecco argues that Century is estopped from challenging the amounts of the requisitions because Century always billed the owner an amount equal to or greater than that billed by Vecco. 2 Zulla Steel, Inc. v. A.M. Gregos, Inc., 174 N.J.Super. 124, 415 A.2d 1183 (N.J.Super. A.D.1980); Blake Construction Co., Inc. v. C.J. Coakley Co., Inc., 431 A.2d 569 (D.C.App.1981).

Century notes that Vecco began work and submitted two requisitions before the parties executed the written contract. In fact, Vecco worked on the job for approximately six weeks before even a draft contract was prepared. Thus, Century argues that the first two Vecco requisitions were submitted without any agreed terms or time for payment and, therefore, payment was due in a reasonable time and in an amount approved by Century. In addition, Century argues that Vecco waived any pri- or default by Century regarding payment when Vecco obtained the agreement of Century to fund Vecco’s weekly payroll and make direct payments to Vecco’s suppliers, beginning in mid-March of 1979.

Failure of a prime contractor to make progress payments as due to subcontractors is a material breach of the contract. Bedwell, Community Science and Zulla, supra. Corbin, in Contracts, § 754, however, states that conduct by one party which leads the other reasonably to believe that “performance on time will not be insisted on will operate as a waiver of the time condition, as to subsequent defaults as well as antecedent ones.” Corbin, Contracts (1 Vol. ed.) § 754 (1952). Century argues that this rule operates to excuse its *949 late payments, especially in light of the later Vecco-Century agreement for Century to fund Veeco’s payroll and pay Vecco’s suppliers. The same rule and agreement to modify the payment terms, however, would operate also to excuse Vecco’s late requisitions. Nothing in the rule would excuse Century’s failure to make full payment. Accordingly, the Court finds that Century breached the contract by failing to pay in full Vecco’s January and February 1979 requisitions according to the terms of the contract, which by then had been executed.

Century contends that Vecco breached the contract by failing to adhere to the mutually agreed completion schedule. Century also contends that Vecco failed to put enough men on the job and attributes Vec-co’s inability to maintain the construction schedule to its under-manning of the project.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
30 B.R. 945, 1983 Bankr. LEXIS 5959, Counsel Stack Legal Research, https://law.counselstack.com/opinion/vecco-construction-industries-inc-v-century-construction-co-of-vaeb-1983.