Shen Valley Masonry, Inc. v. S. P. Cahill & Associates, Inc.

57 Va. Cir. 189, 2001 Va. Cir. LEXIS 431
CourtVirginia Circuit Court
DecidedDecember 11, 2001
DocketCase No. (Law) 00-75
StatusPublished
Cited by3 cases

This text of 57 Va. Cir. 189 (Shen Valley Masonry, Inc. v. S. P. Cahill & Associates, Inc.) is published on Counsel Stack Legal Research, covering Virginia Circuit Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Shen Valley Masonry, Inc. v. S. P. Cahill & Associates, Inc., 57 Va. Cir. 189, 2001 Va. Cir. LEXIS 431 (Va. Super. Ct. 2001).

Opinion

BY JUDGE EDWARD L. HOGSHIRE

The instant action arose from a dispute between a general contractor and a subcontractor who undertook to construct the University of Virginia student residence facility now known as Woody Hall. At issue is the effect of the mutual breaches and termination on the partially-completed contract. Final briefs were submitted by the parties on October 31, 2001, after certain preliminary findings were made by the Court. After due consideration of the record, including evidence introduced at trial, closing briefs, exhibits, trial transcript, and applicable law, this Court awards the subcontractor $336,618 plus interest. The Court’s reasoning behind the final decision follows herein below.

Procedural History

Plaintiff, Shen Valley Masonry, Inc. (“Subcontractor”), filed amotion for judgment agaihst Defendant S. P. Cahill & Associates, Inc. (“Contractor”), its bonding company, Great American Insurance Company, and the University of Virginia (“UVA”) for breach of contract. Subcontractor prayed that this Court would impose damages of $332,033 in completed but unpaid labor, $51,539 in lost profit, $4,585 in clean up and equipment removal costs, and interest.

[190]*190Contractor filed a counterclaim against Subcontractor and its bonding company, American Casualty Company, for breach of contract. Contractor sought damages for the cost to complete and repair Subcontractor’s masonry work, $5,000 per day liquidated damages for each day the project was pushed over schedule by Subcontractor, and attorney’s fees.

This Court issued an opinion dated July 31,2000, dismissing UVA with prejudice from the action on grounds ofboth failure to state a cause of action and sovereign immunity.

A bench trial was held before this Court on January 25 and 26, 2001.

I. Statement and Findings of Fact

A. Overview

In an effort to house their ever-expanding student body, UVA accepted a bid from Contractor to build a new student residence facility (“Woody Hall”). Pursuant to the Virginia Public Procurement Act, Virginia Code § 11-35 et seq., UVA and Contractor executed a $4,484,275 contract for the dorm’s construction (“Prime Contract”) on March 17, 1999.

The Prime Contract provided that Woody Hall was to be constructed and substantially completed by June 30,2000. (Form of Agreement, 1.) As added incentive to meet this deadline, UVA reserved the right to charge Contractor $5,000 per day liquidated damages if Woody Hall was not constructed in time. (Prime Contract § 43, Tr. Trans. 727.) To ensure that these penalties would not accrue, Contractor designed an aggressive schedule which substantially improved on UVA’s timetable (“April schedule”).2 (Tr. Trans. 705,708.)

This compacted schedule was presented to five interested masonry subcontractors, each of whom submitted bids based on this timeline. (Tr. Trans. 603-04.) The two low bidders were within $60,000 of one another; the lowest was submitted by Subcontractor. On April 9, 1999, Contractor and Subcontractor entered into an agreement (“Subcontract”) to perform all requisite masonry work on Woody Hall for $1,048,176. The Subcontract [191]*191likewise contained a $5,000 per day liquidated damages provision mirroring the Prime Contract. (Subcontract § 2.1.)

Immediately acting on UVA’s notice to proceed, on April 5, 1999, Contractor began the process of preparing the project site by erecting a safety fence and clearing the topsoil. (Tr. Trans. 793.) Following the May departure of the students, the excavation subcontractor started digging. (Tr. Trans. 691.) Although UVA performed three boring tests which determined that there was no rock under the construction site, Cahill had seen rock sticking out of the ground and suspected its existence. (Tr. Trans. 678-79.) His suspicion was soon confirmed by the excavation subcontractor whose backhoe was ineffective on the subterrain material.3 A trackhoe, a heavy digging machine, which accomplishes what a backhoe cannot, was imported from Virginia Beach in order to conquer the rock. (Tr. Trans. 888.) While UVA had protected itself from this possibility with a rock clause in the Prime Contract, the compressed April schedule was susceptible to rock-related delays.

B. Decision to Split Woody Hall into Two Sections

As in all construction projects, there was a critical path, or necessary order, in which the Woody Hall construction needed to proceed, to wit: first, the site needed to be dug by the excavation subcontractor, so that the footers4 could be poured by Contractor. This would then permit Subcontractor to lay block on top of the footers to create bearing walls. (Tr. Trans. 911.) The extensive rock removal process significantly delayed the project, thus nullifying the April schedule timeline. Due to the absence of the April schedule, the exact delay caused by the rock removal is unknown; however, the footers were not fully complete until August 23,1999, approximately 30 to 45 days behind schedule. (Tr. Trans. 332-33.) As a direct consequence, Contractor was delayed in pouring the footers and Subcontractor in laying block.

Subcontractor initially arrived on the site June 7, 1999, prior to any request by Contractor. (Tr. Trans. 68.) Upon discovering that Contractor was not ready for the masonry work to begin, Subcontractor’s crew departed but returned, again unsought, on June 16,1999. (Tr. Trans. 795-96.) By that time, there were enough solidified footers in the south section of the building for a [192]*192reduced masonry crew to start work. Jerry Neff, Subcontractor’s owner, admitted that he was eager to begin because of a conflict with another masonry project. (Tr. Trans. 175-77.) Scott Cahill, Contractor’s owner, was also anxious to commence construction in order to get die project on-track and avoid UVA’s liquidated damages.5 In satisfaction of both objectives, Contractor devised a plan to divide the building construction into distinct north and south sections.6 (Tr. Trans. 303-05,433.) This new plan of action entailed stair-stepping the building; Woody Hall’s south section would always remain one floor ahead of the north section.

Coinciding with Subcontractor’s arrival, the June 18 schedule (“June schedule”) was created, reflecting the north-south division. A flurry of schedules was created to accommodate the increasing delays; a new schedule was frequently produced (Tr. Trans. 299) to the detriment of Contractor’s credibility.7 (Tr. Trans. 627.) All schedule changes were discussed at regular meetings and Subcontractor was given a chance to dispute allotted timeframes. (Tr. Trans. 721.) Furthermore, an official schedule was not approved by UVA until December 23,2000. (Tr. Trans. 362.)

C. Masonry Crew’s Size

Although the north-south division’s intrinsic space constraints and critical path implications directly affected the size of the masonry crew,8 the Contractor contended that delays on the project were due to Subcontractor’s inability to provide a large enough masonry crew despite these space constraints. (Tr. Trans. 621.) Cahill testified he and Neff made an extra-contractual agreement stipulating that Subcontractor would provide 25 masons per day. (Tr. Trans.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Builders By Design, L.L.C. v. Wilson
83 Va. Cir. 195 (Norfolk County Circuit Court, 2011)
Kiszely v. Yi
70 Va. Cir. 364 (Fairfax County Circuit Court, 2006)
Shen Valley Masonry, Inc. v. S. P. Cahill & Associates, Inc.
58 Va. Cir. 396 (Virginia Circuit Court, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
57 Va. Cir. 189, 2001 Va. Cir. LEXIS 431, Counsel Stack Legal Research, https://law.counselstack.com/opinion/shen-valley-masonry-inc-v-s-p-cahill-associates-inc-vacc-2001.