Builders By Design, L.L.C. v. Wilson

83 Va. Cir. 195, 2011 WL 8947416, 2011 Va. Cir. LEXIS 194
CourtNorfolk County Circuit Court
DecidedJuly 25, 2011
DocketCase No. (Civil) CL10-3765; Case No. (Civil) CL10-3830
StatusPublished

This text of 83 Va. Cir. 195 (Builders By Design, L.L.C. v. Wilson) is published on Counsel Stack Legal Research, covering Norfolk County Circuit Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Builders By Design, L.L.C. v. Wilson, 83 Va. Cir. 195, 2011 WL 8947416, 2011 Va. Cir. LEXIS 194 (Va. Super. Ct. 2011).

Opinion

By Judge Jerome James

This matter came before the Court on April 26, 2011, for a three-day consolidated trial on the parties’ Complaints. Builders by Design, L.L.C. (hereinafter “Builders”) has filed a Complaint for breach of contract by the homeowner, Mr. Robert Wilson. Wilson also filed a Complaint against Builders in which he seeks damages for breach of contract and fraud by Builders. The cases were consolidated for trial, and both parties presented evidence over the course of the three-day trial. On the final day of trial, Mr. Carnes, counsel for Wilson, withdrew the claim for fraud and for damages based on delay of performance by Builders, leaving only the claims for breach of contract, damages, and attorney’s fees to be decided by the Court in this letter opinion.

[196]*196 Background

These claims arise from a contractual relationship between Builders and Wilson that was memorialized on May 20, 2009, with a seven-page contract, entered into evidence as Builders’ exhibit 1. The parties had discussions regarding the scope of the project prior to signing the contract in May 2009. During these discussions, the parties agreed to the scope of the project and the expectations for the renovations. The contract outlined the work to be performed by Builders at Wilson’s residence, located at 9345 Sturgis Street, Norfolk, Virginia 23503. The contract included building a poolroom addition, constructing a hallway leading into the poolroom addition from the original structure, building a master suite addition, converting a bedroom into a bathroom, and a number of other smaller renovations and repairs to the existing structure.

During the course of the project, there were a number of change orders agreed to by the parties. (See Pl.’s Ex. 8.) Some of these change orders came at a cost to the homeowner, and some were completed by Builders without any additional charge. There came a time during the construction when the parties began to disagree as to some aspects of the project and how the project was being carried out. After multiple disagreements between the parties and after being kicked off the project site once before, Builders received an e-mail from Wilson on March 28, 2010, directing Builders: “not to order any more material for this job or to perform any further work and [that Builders] will not enter the job site without [Wilson’s] permission in writing.” (Pl.’s Ex. 12.) This e-mail marked the last communication between Builders and Wilson until their Complaints were filed in this Court in the spring of 2010.

Builders filed a Complaint contending that the e-mail sent by Wilson on March 28, 2010, was a material breach of their contract. Based on this breach, Builders’ has requested that the Court award it lost profits on the remainder of the project, which was left unfinished as of the date of Wilson’s breach, and to award it costs for work it performed, but which Wilson has not yet paid. The final aspect of Builders’ claim is a request for attorney’s fees pursuant to their contractual agreement.

Wilson also filed a Complaint alleging breach of contract and fraud by Builders. After Builders was asked to leave the jobsite by Wilson, he hired another building company, Meadow Green Builders (hereinafter “Meadow Green”), to come survey the jobsite and finish the work that remained to be completed under the original contract between Wilson and Builders. Meadow Green testified that much of the work performed by Builders was not completed in a workmanlike manner. Wilson alleges that Builders is responsible for the amounts he paid Meadow Green to complete the renovations, which were within the scope of the original contract, and for repairs to remedy the structural deficiencies found by Meadow Green.

[197]*197 Analysis

A. Breach

One of the remaining issues in this case is which party or parties breached the contract, and which, if any, of these breaches was a material breach of the contract. Therefore, the temporal order of the breaches is significant in this case.

It is well established in Virginia that the party who commits the first breach is not entitled to enforce the contract against the other party for a subsequent breach of the same contract. Hurley v. Bennett, Receiver for First Nat’l Bank of Grundy, Va., 163 Va. 241, 253, 176 S.E. 171, 175 (1934); Shen Valley Masonry, Inc. v. S. P. Cahill & Associates, Inc., 57 Va. Cir. 189, 198 (Charlottesville 2001). The exception to this general rule is when the first breach did not amount to a material breach but only affected a minor aspect of the contract. Shen Valley, 57 Va. Cir. at 198. However, if the first breaching party materially breaches the contract, the other party is excused from performing their obligations under the contract. Id. “A material breach is a failure to do something that is so fundamental to the contract that the failure to perform that obligation defeats an essential purpose of the contract.” Horton v. Horton, 254 Va. 111, 115, 487 S.E.2d 200, 204 (1997); Countryside Orthopaedics, P.C. v. Peyton, 261 Va. 142, 154, 541 S.E.2d 279, 285 (2001).

Wilson alleges that Builders breached the contract when it performed work on his residence that he believes was not completed in a workmanlike manner. Most significantly, Wilson alleges that the roof on the poolroom was not completed in a workmanlike manner, because his second contractor, Meadow Green, described the roof as “spongy” and not structurally sound. Wilson’s experts also testified that other areas of the home were not fit for habitation and that there were a number of significant structural deficiencies in the work completed by Builders.

However, Wilson’s contention that Builders was the first party to breach the contract is flawed. Wilson did not learn of Builders’ alleged breach until sometime after he sent Builders an e-mail forbidding it from returning to his property or working on this project without future written permission. Note that no evidence was presented at trial that showed Wilson had any indication that Builders’ work was not being done to an acceptable standard in the construction industry before he executed the e-mail. The only testimony regarding Wilson’s knowledge about the quality of Builders’ work was from Guy Sorenson and Dennis Murtland. The testimony from these witnesses, both employed by Meadow Green, was that they came to know Wilson sometime in April or early May 2010 when they visited Wilson’s residence to determine the scope of the remaining home renovation project. It was not until the inspection by Sorenson and Murtland, which occurred [198]*198after Wilson kicked Builders off the project on March 28,2010, that Wilson was put on notice of the alleged structural deficiencies.

Builders’ knowledge regarding the structural soundness of the renovations and poolroom roof came from two sources only, its observations and oversight of the jobsite as well as from the work passing city inspections. On March 26,2010, William P. Johnson, Jr., Senior Code Specialist for the City of Norfolk, approved Builders’ framing work at Wilson’s residence, including the poolroom roof.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Chesapeake & Ohio Railway Co. v. Kelly
241 U.S. 485 (Supreme Court, 1916)
DUNN CONST. CO. v. Cloney
682 S.E.2d 943 (Supreme Court of Virginia, 2009)
Nichols Const. v. Virginia MacHine Tool
661 S.E.2d 467 (Supreme Court of Virginia, 2008)
Countryside Orthopaedics, P.C. v. Peyton
541 S.E.2d 279 (Supreme Court of Virginia, 2001)
Horton v. Horton
487 S.E.2d 200 (Supreme Court of Virginia, 1997)
Clevert v. Jeff W. Soden, Inc.
400 S.E.2d 181 (Supreme Court of Virginia, 1991)
CSX Transportation, Inc. v. Casale
441 S.E.2d 212 (Supreme Court of Virginia, 1994)
Schwab v. Norris
231 S.E.2d 222 (Supreme Court of Virginia, 1977)
East Texas Salvage & MacHine v. Duncan
306 S.E.2d 896 (Supreme Court of Virginia, 1983)
Kamlar Corp. v. Haley
299 S.E.2d 514 (Supreme Court of Virginia, 1983)
Gilmore v. Basic Industries, Inc.
357 S.E.2d 514 (Supreme Court of Virginia, 1987)
Hannan v. Dusch
153 S.E. 824 (Supreme Court of Virginia, 1930)
Hurley v. Bennett
176 S.E. 171 (Supreme Court of Virginia, 1934)
Richardson v. Breeding
187 S.E. 454 (Supreme Court of Virginia, 1936)
Elstner v. Golden
56 Va. Cir. 378 (Spotsylvania County Circuit Court, 2001)
Shen Valley Masonry, Inc. v. S. P. Cahill & Associates, Inc.
57 Va. Cir. 189 (Virginia Circuit Court, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
83 Va. Cir. 195, 2011 WL 8947416, 2011 Va. Cir. LEXIS 194, Counsel Stack Legal Research, https://law.counselstack.com/opinion/builders-by-design-llc-v-wilson-vaccnorfolk-2011.