Federal Insurance v. Starr Electric Co.

410 S.E.2d 684, 242 Va. 459, 8 Va. Law Rep. 1407, 1991 Va. LEXIS 160
CourtSupreme Court of Virginia
DecidedNovember 8, 1991
DocketRecord 901589
StatusPublished
Cited by24 cases

This text of 410 S.E.2d 684 (Federal Insurance v. Starr Electric Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Federal Insurance v. Starr Electric Co., 410 S.E.2d 684, 242 Va. 459, 8 Va. Law Rep. 1407, 1991 Va. LEXIS 160 (Va. 1991).

Opinion

SENIOR JUSTICE POFF

delivered the opinion of the Court.

The issues we consider in this appeal arise out of a dispute between two insurance carriers concerning a subcontractor’s claim against a general contractor seeking payment for electrical work performed and materials supplied in a building renovation project.

In December 1986, the owner of the Cohen building entered into a renovation contract with Dixie Constructors, Inc. (Dixie). Corroon & Black of Ohio, Inc., an insurance agency, furnished Dixie’s parent corporation an installation floater insurance policy *462 issued by Aetna Casualty and Surety Company (Aetna) listing Dixie as a named insured.

In a subcontract drafted by Dixie which incorporated the terms of the general contract and the conditions attached thereto, Dixie engaged Starr Electric Company, Inc. (Starr), to perform the electrical work and supply the materials required by the renovation project at a cost of $250,000. Dixie then obtained through Corroon & Black a performance bond and a payment bond issued by Federal Insurance Company (Federal). Starr was insured under its own installation floater policy and a property package policy issued 18 years earlier by Aetna and sold by Corroon & Black.

On January 13, 1987, during the course of the renovation, the Cohen building was destroyed by fire, and the project was abandoned. At that point, Starr had completed most of the work contemplated by the subcontract.

In response to a fire-damage claim filed by Dixie, Aetna refused coverage and filed a suit for declaratory judgment against Dixie, Corroon & Black, the owner, the project lender, and others. Aetna asked the court to declare that its policy with Dixie did not cover the Cohen project. The suit was compromised and settled out of court by the parties.

On April 10, 1987, three months after the fire, Starr asked Dixie for a copy of the payment bond, “if any”. Dixie did not respond to Starr’s request. Starr then filed a claim under its own policies with Aetna, and Aetna paid Starr $201,280.56 for loss of its work and the electrical materials and equipment consumed in the fire.

On April 4, 1988, Federal mailed Starr a copy of the payment bond. On May 20, 1988, more than a year after the fire, Aetna attached Federal’s copy of the payment bond to a motion for judgment against Federal, Dixie’s surety, seeking payment in Starr’s name of $206,074.38, the balance due under the subcontract. Page two of that copy contained a clause limiting the right to file suit on the bond to two years.

A year later, on June 2, 1989, Federal learned for the first time that Corroon & Black had supplied it with an incorrect copy of the payment bond, and that page two of the original executed by the parties contained a clause limiting the right to file suit to one year. Federal so advised the court and opposing counsel, the court allowed the correct page to be substituted in the record, and Fed *463 eral made a motion to amend its grounds of defense in order to assert the one-year time limitation defense.

The trial court ruled that such a defense must be pled specially, denied the motion to amend, and held that Federal was estopped to plead such a defense. Having considered the evidence stipulated by the parties, the court rejected Federal’s several grounds of defense on the merits and entered judgment against Federal in the sum of $203,984.38. We granted Federal’s petition for appeal.

I. ESTOPPEL

In its first two assignments of error, Federal contends that the trial court erred “in ruling that the contractual limitations period had to be specially pleaded”; that the court erred “in denying Federal’s motion for leave to amend” its grounds of defense to plead that defense; and that the court erred “in ruling that Federal is estopped from asserting the contractual one (1) year limitations period defense”. Because we conclude that the court’s estoppel ruling was correct, we do not reach the other two rulings.

On brief, Federal argues that the estoppel ruling was in error “because Federal acted reasonably and in good faith in discovering that the parties were litigating an incorrect copy of the payment bond.” The delay in the discovery, Federal says, was due to the fact that its own bonding agent “had sent incorrect copies to both Federal and Dixie after the bond was executed.” As soon as Federal discovered the error, it continues, it “gave notice . . . more than five (5) months prior to the previously scheduled trial date.” That notice, Federal submits, “was . . . adequate” and, once the trial court had agreed to substitute the correct page for the erroneous page, the court should have allowed Federal to assert the limitations defense.

In essence, Federal contends that its good faith excuses its delay in discovering the error in its own contract document. In response, Starr argues that the record shows “a negligent course of dealing by Federal which amply supports the trial court’s . . . finding that Federal ... is barred and estopped from raising any limitation defense.” We agree with Starr.

In Contee Sand v. Reliance Ins., 209 Va. 672, 166 S.E.2d 290 (1969), a subcontractor sued a contractor’s surety on a payment bond containing a time limitation clause like that in issue here. The evidence showed that the subcontractor, unable to collect from the contractor, had asked the surety’s bonding agent whether *464 the contractor had acquired a payment bond. The agent reported that the contractor had a performance bond but no payment bond. More than a year later, the agent discovered that he had overlooked the payment bond which he found “ ‘stuck’ in the file along with the performance bond” and that “the home office was never advised of the substituted [payment] bond”. Id. at 674, 166 S.E.2d at 291-92. When the agent told the subcontractor of his mistake, the subcontractor filed its action against the surety. Invoking the one-year time limitation in the bond, the surety moved to dismiss, and the trial court granted the motion.

On appeal, we recognized that the agent’s initial response to the subcontractor’s inquiry was not an act of “fraud” or one “intentionally designed to mislead” but simply one that “constituted negligence.” Id. at 676, 166 S.E.2d at 293. Yet, we said that the subcontractor “had a right to rely on a statement of fact made to him ... by the person in a position to know the facts”; that the subcontractor “was prejudiced by the failure of [the agent] and [the surety] to provide correct information”; that “[t]he delay in bringing action can be attributed directly to the lack of knowledge by [the subcontractor] ... of the existence of the bond”; and that “[t]his was the fault of the [surety’s] agent”. Id. at 675, 166 S.E.2d at 292.

Reversing the judgment below and remanding the case for further proceedings, we held that, because “the negligence of the agent of [the surety] . . . caused the failure of [the subcontractor] to bring appropriate action . . . [the surety] is es-topped ...

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Studio 76, LLC v. Yiqun Guo
Court of Appeals of Virginia, 2026
Callender v. Callender
D. Maryland, 2020
Culpeper Regional Hospital v. Cynthia B. Jones, Director
767 S.E.2d 236 (Court of Appeals of Virginia, 2015)
Brent C. Bousman v. Caitlin K. Lhommedieu
Court of Appeals of Virginia, 2012
Psychiatric Solutions of Virginia, Inc. v. Finnerty
676 S.E.2d 358 (Court of Appeals of Virginia, 2009)
Weiss v. E.V.M.S. Academic Physicians & Surgeons Health Service Foundation
68 Va. Cir. 433 (Norfolk County Circuit Court, 2005)
Ripley Heatwole Co. v. John E. Hall Electrical Contractor, Inc.
69 Va. Cir. 69 (Norfolk County Circuit Court, 2005)
South Auburn, L.P. v. Old Auburn Mills, L.P.
68 Va. Cir. 145 (Loudoun County Circuit Court, 2005)
Video Zone, Inc. v. KF&F Properties, L.C.
594 S.E.2d 921 (Supreme Court of Virginia, 2004)
Llewellyn v. Moyer
59 Va. Cir. 141 (Virginia Circuit Court, 2002)
Shen Valley Masonry, Inc. v. S. P. Cahill & Associates, Inc.
57 Va. Cir. 189 (Virginia Circuit Court, 2001)
Hanson Pipe & Products, Inc. v. Falcon Construction Corp.
55 Va. Cir. 347 (Norfolk County Circuit Court, 2001)
Countryside Orthopaedics, P.C. v. Peyton
541 S.E.2d 279 (Supreme Court of Virginia, 2001)
Moore Brothers Co v. Brown & Root Inc
207 F.3d 717 (Fourth Circuit, 2000)
Whitaker v. Nationwide Mutual Fire Insurance
115 F. Supp. 2d 612 (E.D. Virginia, 1999)
Apartment Investment & Management Co. v. National Loan Investors
518 S.E.2d 627 (Supreme Court of Virginia, 1999)
Jessup-Morgan v. America Online, Inc.
20 F. Supp. 2d 1105 (E.D. Michigan, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
410 S.E.2d 684, 242 Va. 459, 8 Va. Law Rep. 1407, 1991 Va. LEXIS 160, Counsel Stack Legal Research, https://law.counselstack.com/opinion/federal-insurance-v-starr-electric-co-va-1991.