Studio 76, LLC v. Yiqun Guo

CourtCourt of Appeals of Virginia
DecidedJanuary 20, 2026
Docket1227244
StatusUnpublished

This text of Studio 76, LLC v. Yiqun Guo (Studio 76, LLC v. Yiqun Guo) is published on Counsel Stack Legal Research, covering Court of Appeals of Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Studio 76, LLC v. Yiqun Guo, (Va. Ct. App. 2026).

Opinion

COURT OF APPEALS OF VIRGINIA

Present: Judges Athey, Fulton* and Lorish UNPUBLISHED

Argued at Fairfax, Virginia

STUDIO 76, LLC MEMORANDUM OPINION** BY v. Record No. 1227-24-4 JUDGE CLIFFORD L. ATHEY, JR. JANUARY 20, 2026 YIQUN GUO, ET AL.

FROM THE CIRCUIT COURT OF FAIRFAX COUNTY John M. Tran, Judge

Roya Vasseghi (Vasseghi Law Group, on briefs), for appellant.

Sean Patrick Roche (Joseph R. Coules; Cameron/McEvoy, PLLC, on brief), for appellees.

Studio 76, LLC (“Studio 76”) appeals from a judgment entered against it in the Circuit

Court of Fairfax County (“circuit court”). The judgment arose as a result of a counterclaim for

breach of a construction contract (“Contract”), and the circuit court awarded monetary damages,

attorney fees, and costs to Yiqun Guo (“Guo”) and Ruijing Chen (collectively, “Homeowners”).

On appeal, Studio 76 assigns error to the circuit court for reconsidering, “without a legal basis,”

the court’s initial ruling that neither party could recover damages on their competing breach of

contract claims. Studio 76 also assigns error to the circuit court for failing to find that the

Homeowners’ failure to fully pay the balance due under the Contract barred them from

recovering on their counterclaim. In addition, Studio 76 assigns further error to the circuit court

for failing to hold that the Homeowners materially breached the Contract by interfering with the

* Justice Fulton participated in the hearing and decision of this case prior to his investiture as a Justice of the Supreme Court of Virginia. ** This opinion is not designated for publication. See Code § 17.1-413(A). performance thereof. Finally, Studio 76 contends that the evidence was insufficient to support

the circuit court’s judgment awarding damages on the Homeowners’ counterclaim. Finding no

error, we affirm the circuit court’s judgment.

II. BACKGROUND1

Studio 76 is a design-build construction firm that specializes in designing and constructing

custom-built homes. In May of 2017, Studio 76 entered into the Contract with the Homeowners to

complete the construction of their future home located in Falls Church, Virginia. The Homeowners

had previously entered into a contract with another contractor to build their future home in Falls

Church, but the contractor abandoned the project prior to completing the home. Studio 76 and the

Homeowners entered into the Contract, in part, by incorporating the earlier contract. Thus, Studio

76 obligated itself to complete the construction of the home in accordance with the specifications in

the incorporated contract, along with other additional specified work, for $431,436. The Contract

provided, inter alia, for the replacement of a previously installed HVAC system with a specific type

of HVAC system as well as the revision and installation of related duct work. The replacement

HVAC system specified under the Contract was to consist of two “Carrier Performance 96 gas

furnaces” and two “Carrier Performance 16 heat pumps, 25HCB6 (16.5 SEER).” Thermostats were

also to be installed on the first and second floors, with the first-floor thermostat controlling the

temperature in both the first floor and basement zones. Additionally, the home was required to be

Energy Star certified. Studio 76 was also required to complete the home “in a workmanlike manner

and in compliance with all applicable building, zoning and fire codes.”

The Contract further provided that following lender approval of the Contract, receipt of

applicable permits, and payment of the deposit, Studio 76 was to complete the construction project

1 Under settled appellate principles, we view the evidence in the light most favorable to the Homeowners, the prevailing party in the trial court. See Moncrieffe v. Deno, 76 Va. App. 488, 494 (2023). -2- and obtain a certificate of occupancy within six months, with time being of the essence. A

liquidated damages clause was also included in the Contract and provided that, if Studio 76 failed to

complete work on the project by the six-month deadline, it would owe the Homeowners a “late fee”

of $100 for every day thereafter that the project remained incomplete, unless the Homeowners

caused the delay.

The Contract also provided for the third-party lender to “control[]” payments to Studio 76.

The Contract identified the Homeowners’ bank as the third-party lender and also provided for the

Homeowners’ bank to inspect Studio 76’s work and pay Studio 76 for the work completed

according to a draw schedule. The agreed upon draw schedule consisted of an initial deposit and

four subsequent disbursements based upon the progress made by Studio 76 as certified by the

Homeowners’ bank. Finally, Paragraph 14 of the Contract provided that, in the event of a claim for

breach of contract, the prevailing party “shall be entitled to recover its reasonable expenses,

including actual attorney’s fees, incurred [sic] prosecution or defense of such claim.”

As the project progressed, the Homeowners’ bank disbursed payments to the Homeowners,

who then transferred the payments to Studio 76 as the work was completed. During the project, the

parties also executed several change orders, adjusting the total price of the Contract to $434,302.

On July 31, 2018, Studio 76 obtained a certificate of occupancy for the home from Fairfax

County. Studio 76 then requested payment of the final draw. The final disbursement pursuant to

the draw schedule was to occur in August of 2018, however, rather than paying Studio 76 the

final draw, the Homeowners continued to ask Studio 76 to perform outstanding work on the

project. Initially, Studio 76 continued to work to complete the items requested by the

Homeowners. By October of 2018, Studio 76 ceased work and sent the Homeowners a “material

breach letter” because Studio 76 was “not getting paid per the contract requirement.” The

-3- Homeowners responded that they would pay the withheld amount once Studio 76 completed the

project.

Studio 76 subsequently filed a complaint against the Homeowners alleging a material breach

of contract, breach of contract, quantum meruit, and fraud in the inducement.2 The complaint

alleged that the Homeowners had materially breached the contract by withholding part of the final

disbursement made pursuant to the draw schedule. It also contended that the Homeowners had

committed a breach of contract by requesting additional work outside of the contractual scope of

work and for failing to pay for same.3

In response, the Homeowners filed both an answer to the complaint as well as a

counterclaim alleging that Studio 76 had breached the contract by 1) failing to complete the project

“in a workmanlike manner and/or in accordance with the Construction Agreement”; 2) failing to

timely complete the work; and 3) abandoning the project. The Homeowners also alleged that Studio

76 was “continuously behind schedule” during the project and “frequently” requested payments in

advance of the draw schedule requiring the Homeowners to pay out of pocket. Finally, the

Homeowners alleged that Studio 76 failed to complete work, remediate defective work, and obtain

an Energy Star certificate for the home as required by the contract. The Homeowners sought an

award of compensatory damages, reimbursement of attorney fees, and costs.

A bench trial on the parties’ competing claims began on September 19, 2022. At trial, Nate

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Com. v. Brown
687 S.E.2d 742 (Supreme Court of Virginia, 2010)
Etherton v. Doe
597 S.E.2d 87 (Supreme Court of Virginia, 2004)
Horton v. Horton
487 S.E.2d 200 (Supreme Court of Virginia, 1997)
Richard Douglas Thomas, Jr. v. Commonwealth of Virginia
742 S.E.2d 403 (Court of Appeals of Virginia, 2013)
Brandau v. Brandau
666 S.E.2d 532 (Court of Appeals of Virginia, 2008)
Robbins v. Robbins
632 S.E.2d 615 (Court of Appeals of Virginia, 2006)
Shenk v. Shenk
571 S.E.2d 896 (Court of Appeals of Virginia, 2002)
Hechler Chevrolet, Inc. v. General Motors Corp.
337 S.E.2d 744 (Supreme Court of Virginia, 1985)
Holmes v. Holmes
375 S.E.2d 387 (Court of Appeals of Virginia, 1989)
Erlich v. Hendrick Construction Co.
225 S.E.2d 665 (Supreme Court of Virginia, 1976)
Lochaven Co. v. Master Pools by Schertle, Inc.
357 S.E.2d 534 (Supreme Court of Virginia, 1987)
Spotsylvania County School Board v. Seaboard Surety Co.
415 S.E.2d 120 (Supreme Court of Virginia, 1992)
Pinkard v. Pinkard
407 S.E.2d 339 (Court of Appeals of Virginia, 1991)
Federal Insurance v. Starr Electric Co.
410 S.E.2d 684 (Supreme Court of Virginia, 1991)
Kirk Reid Company v. Fine
139 S.E.2d 829 (Supreme Court of Virginia, 1965)
Whitt v. Godwin
139 S.E.2d 841 (Supreme Court of Virginia, 1965)
Philip deCamp v. Virginia deCamp
765 S.E.2d 863 (Court of Appeals of Virginia, 2014)
Culpeper Regional Hospital v. Cynthia B. Jones, Director
767 S.E.2d 236 (Court of Appeals of Virginia, 2015)
Rafalko v. Georgiadis
777 S.E.2d 870 (Supreme Court of Virginia, 2015)
Freezer v. Miller
176 S.E. 159 (Supreme Court of Virginia, 1934)

Cite This Page — Counsel Stack

Bluebook (online)
Studio 76, LLC v. Yiqun Guo, Counsel Stack Legal Research, https://law.counselstack.com/opinion/studio-76-llc-v-yiqun-guo-vactapp-2026.