Lochaven Co. v. Master Pools by Schertle, Inc.

357 S.E.2d 534, 233 Va. 537, 3 Va. Law Rep. 2811, 1987 Va. LEXIS 223
CourtSupreme Court of Virginia
DecidedJune 12, 1987
DocketRecord 831822
StatusPublished
Cited by20 cases

This text of 357 S.E.2d 534 (Lochaven Co. v. Master Pools by Schertle, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lochaven Co. v. Master Pools by Schertle, Inc., 357 S.E.2d 534, 233 Va. 537, 3 Va. Law Rep. 2811, 1987 Va. LEXIS 223 (Va. 1987).

Opinion

THOMAS, J.,

delivered the opinion of the Court.

Lochaven Company (Lochaven) sued Master Pools by Schertle, Inc. (Master Pools), for breach of a written contract to construct a swimming pool at Lochaven’s apartment complex. In the contract action, Master Pools filed a counterclaim for extra work it was required to do in building the pool. Lochaven also filed a separate suit, in tort, against Virginia Pool Services, Inc. (VPS), alleging negligence in the cleaning of the same pool. Master Pools and VPS were related business entities and the two suits were consolidated for a bench trial.

Lochaven prevailed on both claims. However, it appeals because it contends the trial court awarded inadequate damages. On the contract claim, the ad damnum was $25,000; Lochaven’s proof was approximately $21,500; Master Pools did not adduce any damage evidence other than on its counterclaim; the trial court awarded damages of $3,000 less $1,732.10 based on the counterclaim, resulting in a net award of $1,267.90. On the tort claim, the ad damnum was $30,000; Lochaven’s proof was approximately $18,000; VPS did not adduce any damage evidence; the trial court awarded $5,350 with a $350 setoff for the cost of cleaning the pool, resulting in a net award of $5,000. Thus, based on a total ad damnum of $55,000 and total proof of approximately $39,500, Lochaven recovered a judgment of $6,267.90. We granted the appeal to consider the damage issues. For reasons stated below, we will affirm the judgment in the contract case but reverse the judgment in the tort case.

On July 24, 1978, Master Pools agreed, by written contract, to construct the swimming pool here in issue. The pool was to have *539 been 8’6” deep at its deepest point. It was also to have had a diving board. The contract price was $18,537.

The pool was constructed in 1979. It was situated on a piece of land bordering a man-made lake. It opened for use in late August 1979. When the pool opened there were problems with the water flow, the water clarity, the skimmers, and the water filtration system. Ultimately, these problems were substantially corrected. In late summer 1979, the pool was closed and drained for the winter.

In the spring of 1980, Lochaven hired VPS to clean the pool at a cost of $350. When the cleaning was completed, a VPS employee turned on the water to refill the pool, left the pool site, and locked the gate. This was on a Saturday. A hydrostatic valve at the bottom of the deep end of the pool was left open. As a result, the water ran out through the valve. By Sunday evening, part of the earthen embankment which separated the pool from the man-made lake had washed away. The washout carried away soil that supported part of the concrete apron that surrounded the pool.

Lochaven took immediate steps to stabilize the embankment by placing riprap, dirt, and railroad ties in the washed-out area. Lochaven’s witnesses testified that it cost $2,101.07 to stabilize the embankment. VPS did not dispute this figure.

One month after the washout, major cracks began developing in the portion of the concrete apron on the side of the pool where the washout had occurred. In 1982, Lochaven spent $16,000 to remove the fence, break up and remove the cracked concrete, pour a replacement apron, and replace the fence. VPS did not dispute this evidence. On brief, however, Lochaven conceded that $1,100 of the $16,000 figure was spent on work other than replacing the damaged concrete apron and submitted that the proper figure attributable to the damaged portion of the concrete apron was $14,900. In addition, Lochaven proved that 161,000 gallons of water poured out through the open valve and that the lost water cost $206.21. The only thing that VPS contended with regard to damages in the tort action was that it had never been paid the $350 for cleaning the pool.

While work was underway to correct the cracks in the concrete apron, Lochaven learned that the pool was not 8’6” deep as required by the contract. Instead, the pool was only 7’9” deep. The actual depth of the pool was insufficient to permit the use of the diving board — which had to be removed. Lochaven adduced evidence that it would cost $21,500 to reconstruct the pool to con *540 tract depth. This would be done by raising the sides of the pool. The fence would be removed, the concrete apron broken up, the coping around the top edge of the pool removed, a portion of the tiles removed, the skimmers raised, the sides of the walls raised, the concrete apron repoured, and the fence replaced. Master Pools did not develop evidence to challenge the $21,500 estimate.

As noted above, the only evidence of damages adduced by Master Pools in the contract case concerned its counterclaim for extra costs it said it incurred because it ran into excess ground water in building the pool. Master Pools claimed $1,732.10 for that work.

The trial court ruled from the bench concerning both claims. With regard to the tort claim, the trial court stated as follows:

I don’t believe that all the damage that the Plaintiff has attributed to this, in particular $16,000 worth of decking, can be attributed to this incident completely.
So I feel that they would be entitled to the $310, which amounts to the water that was let out, plus what it cost them to fix that place. And I think they’re entitled to some damage for some of the contracting that occurred. So the Court has a figure of $5,350, and I’m going to subtract $350 as being the price due Virginia Pool Service for cleaning and, therefore, give judgment for the Plaintiff in that case of $5,000.

With regard to the breach of contract claim, the trial court stated as follows:

In the Master Pool case, the only damage that I see that the Plaintiff is asking me to assess is because the pool isn’t deep enough and, therefore, does not carry a diving board, and wants to spend $21,500 to fix that remedy, when the contract on the original pool was something like $18,000 to build the whole thing to begin with.
So, gentlemen, that’s rather ridiculous[.] I feel they’re entitled to something because of that error and something for the inconveniences that have occurred in some of the building of the pool, and I have placed a value of damage on that of $3,000.

The trial court awarded Master Pool the full $1,732.10 claimed in its counterclaim.

*541 In our opinion, the trial court erred in assessing damages in the tort action. However, there was no error with respect to the award of damages on the breach of contract claim.

The measure of damages in a negligence action is that amount necessary to compensate the injured party for the damages proximately caused by the tortious conduct. See Younger v. Appalachian Power Co., 214 Va. 662, 663, 202 S.E.2d 866, 867 (1974).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Studio 76, LLC v. Yiqun Guo
Court of Appeals of Virginia, 2026
Vasterling v. Dirle
E.D. Virginia, 2023
Germano v. Taishan Gypsum Co.
706 F. Supp. 2d 655 (E.D. Louisiana, 2010)
In Re Chinese Manufactured Drywall Products
706 F. Supp. 2d 655 (E.D. Louisiana, 2010)
Nichols Const. v. Virginia MacHine Tool
661 S.E.2d 467 (Supreme Court of Virginia, 2008)
Westlake Properties v. Westlake Pointe Ass'n
639 S.E.2d 257 (Supreme Court of Virginia, 2007)
7-Eleven, Inc. v. Department of Environmental Quality
590 S.E.2d 84 (Court of Appeals of Virginia, 2003)
Pocahontas Mining, L.L.C. v. Jewell Ridge Coal Corp.
66 Va. Cir. 498 (Buchanan County Circuit Court, 2003)
Klaiber v. Freemason Associates, Inc.
587 S.E.2d 555 (Supreme Court of Virginia, 2003)
Steffan v. Freemason Assocs., Inc.
61 Va. Cir. 247 (Virginia Circuit Court, 2003)
Oertel v. Ransone
52 Va. Cir. 543 (Fairfax County Circuit Court, 1997)
Transdulles Center, Inc. v. USX Corp.
976 F.2d 219 (Fourth Circuit, 1992)
Harrell Builders, Inc. v. Watters
27 Va. Cir. 275 (Fredericksburg County Circuit Court, 1992)
Tipco Homes, Inc. v. Professional Service Indus., Inc.
16 Va. Cir. 365 (Fairfax County Circuit Court, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
357 S.E.2d 534, 233 Va. 537, 3 Va. Law Rep. 2811, 1987 Va. LEXIS 223, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lochaven-co-v-master-pools-by-schertle-inc-va-1987.