Green v. Burkholder

160 S.E.2d 765, 208 Va. 768, 1968 Va. LEXIS 180
CourtSupreme Court of Virginia
DecidedApril 22, 1968
DocketRecord 6570
StatusPublished
Cited by12 cases

This text of 160 S.E.2d 765 (Green v. Burkholder) is published on Counsel Stack Legal Research, covering Supreme Court of Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Green v. Burkholder, 160 S.E.2d 765, 208 Va. 768, 1968 Va. LEXIS 180 (Va. 1968).

Opinion

Buchanan, J.,

delivered the opinion of the court.

This is an action for the breach of a written contract, and the issue to be decided is whether the plaintiffs sufficiently proved damages.

By a written agreement dated June 22, 1964, Green and others, plaintiffs, granted to Burkholder and Burkholder, a partnership, referred to herein as Burkholder or defendants, the right to remove *769 gravel and other material from gravel pits on the land of plaintiffs for use in the construction of Interstate Highway 95, in Stafford county. The Fidelity & Casualty Company of New York, the other defendant, was surety on the Burkholder payment and performance bond for the construction of said highway. For the right so granted, Burkholder agreed to pay plaintiffs eighteen cents per cubic yard for the material removed and in addition to smooth over the surface from which the materials were taken by Burkholder, as well as by prior lessees, and to replace, spread and level off the stored topsoil, to pile all oversize rocks and perform other duties as described in Paragraph 10 of the contract. *

In November, 1965, plaintiffs filed a motion for judgment against Burkholder and the Surety Company, alleging that Burkholder had failed to pay all of the money consideration for the contract and had failed to perform the cleanup and smoothing operations required by the contract. Plaintiffs sought damages in the sum of $85,000 for these breaches of the contract. The defendants filed answers, a jury was waived, the court heard the evidence and entered judgment for the plaintiffs against Burkholder and the Surety Company in the amount of $2,764.20, of which $1,744.20 was for materials excavated and not paid for, and $1,020.00 was for cost incurred by the plaintiffs in obtaining certain cross-sections.

The court held, however, that the plaintiffs had “failed to meet the burden of proof with respect to damages resulting from the failure of Burkholder & Burkholder to complete the smoothing-over operations and other duties called for in Paragraph 10 of the contract”; *770 and the court ordered that no damages be awarded to the plaintiffs therefor. From this holding the plaintiffs have appealed.

Both plaintiffs and defendants presented witnesses who testified without objection as to their estimates of the cost of smoothing over the land and doing the other operations required by said Paragraph 10 of the contract. No evidence was offered by either party as to the value of the land itself.

Two witnesses, experienced contractors, who had examined the premises, were called by the plaintiffs. They testified as to the quantities of materials involved and the machinery and work required to do the leveling, smoothing and other operations required by Paragraph 10 of the contract. One testified that the area involved was about twenty-five acres and it looked to him like it was “going to be somewhere around fifty-two thousand dollars” to do the work. He conceded, however, that he based his calculation on the most expensive method of doing the work, and that it was possible that other methods and means could be employed which would reduce his estimate materially. The other witness for plaintiffs estimated that the smoothing over and the piling of the rocks would cost from ten to twelve thousand dollars for one of the pits, plus fifty to sixty cents per cubic yard for moving the topsoil.

Three witnesses were introduced by the defendants on the subject. The first was Robert Burkholder, one of defendants, who testified that he had made an estimate of the cost of smoothing over the surface, spreading the topsoil and picking up the rocks as required by the contract, and his estimate was $9,000.00. This witness was asked by his counsel whether he would have been able to acquire this particular gravel from the Green property at the price of eighteen cents a cubic yard without the provision for smoothing out. He replied, “The answer is no. It’s obvious.”

The second witness placed the cost of doing the required work at $10,000.00; and the third testified that he was president of a company which specialized in earth moving, that he had examined the property, had read the provisions of the contract,, and his total estimate for doing the work required by the contract was $9,750.00, and that he “would be very happy to sign a contract for that effect this morning.”

The court below did not state in its judgment order the basis of its holding that the plaintiffs had failed to meet the burden of proof in respect to damages. In their brief in support of the judgment the defendants say: “The entire record is bereft of testimony offered by *771 the plaintiffs demonstrating that the market value of plaintiffs’ property was diminished because the pits were not smoothed over or that the market value of the property would be increased upon completion of the smoothing-over operations.”

Presumably this was the reason for the court’s ruling that the plaintiffs had not carried the burden of proof with respect to damages.

[ 1 ] But that was not the theory on which the case was tried. As stated, no evidence was offered as to the value of the plaintiffs’ property. Both parties introduced evidence only on the question of the cost to the plaintiffs of completing the work which the defendants had contracted to do but did not do. Plaving accepted that as the issue and tried the case on that theory, it is late for the defendants to say that the proper measure of damages was the difference between the before and after value of the property. Cf. Barcroft Woods v. Francis, 201 Va. 405, 410, 111 S.E.2d 512, 517.

[2] But aside from that, we hold that the proper measure of damages was the reasonable cost of completing the work the defendants contracted to do but did not do.

In Mann v. Clowser, 190 Va. 887, 904, 59 S.E.2d 78, 86, we quoted with approval from 5 Williston on Contracts, Rev. Ed., § 1363, pp. 3825-6, the statement that where the contractor fails to keep his agreement, the measure of the employer’s damages “is always the sum which will put him in as good a position as rf the contract had been performed. If the defect is remediable from a practical standpoint, recovery generally will be based on the market price of completing or correcting the performance, and this will generally be shown by the cost of getting (the) work done or completed by another person. If the defect is not thus remediable, damages are based on the difference between the value of the defective structure and that of the structure if properly completed. * *”

We also approved the principle stated in Restatement of the Law of Contracts, § 346, that for defective or unfinished construction the owner can get judgment for the reasonable cost of construction and completion in accordance with the contract, if this is possible, and does not involve “unreasonable economic waste”; otherwise, for the difference in value between the product contracted for and the one produced.

We said in the Mann

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Harrell v. Deluca
E.D. Virginia, 2022
Calderone v. TAC Construction, L.L.C.
82 Va. Cir. 585 (Nelson County Circuit Court, 2008)
Nichols Const. v. Virginia MacHine Tool
661 S.E.2d 467 (Supreme Court of Virginia, 2008)
Klaiber v. Freemason Associates, Inc.
587 S.E.2d 555 (Supreme Court of Virginia, 2003)
Steffan v. Freemason Assocs., Inc.
61 Va. Cir. 247 (Virginia Circuit Court, 2003)
Oertel v. Ransone
52 Va. Cir. 543 (Fairfax County Circuit Court, 1997)
Lee v. Bell
379 S.E.2d 464 (Supreme Court of Virginia, 1989)
Lochaven Co. v. Master Pools by Schertle, Inc.
357 S.E.2d 534 (Supreme Court of Virginia, 1987)
Lacks v. Bottled Gas Corp.
205 S.E.2d 671 (Supreme Court of Virginia, 1974)

Cite This Page — Counsel Stack

Bluebook (online)
160 S.E.2d 765, 208 Va. 768, 1968 Va. LEXIS 180, Counsel Stack Legal Research, https://law.counselstack.com/opinion/green-v-burkholder-va-1968.