Oertel v. Ransone

52 Va. Cir. 543, 1997 Va. Cir. LEXIS 588
CourtFairfax County Circuit Court
DecidedMarch 27, 1997
DocketCase No. (Law) 143176
StatusPublished

This text of 52 Va. Cir. 543 (Oertel v. Ransone) is published on Counsel Stack Legal Research, covering Fairfax County Circuit Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Oertel v. Ransone, 52 Va. Cir. 543, 1997 Va. Cir. LEXIS 588 (Va. Super. Ct. 1997).

Opinion

BY JUDGE STANLEY P. KLEIN

This case is before Court on Plaintiffs Motion for Reconsideration of the Court’s ruling and final order of October 28, 1996, finding in favor of the Defendant. The Plaintiff Joseph A. Oertel sued the Defendant Scott Ransone for damages resulting from a breach of contract for failure to complete construction of a house. In rendering its decision, this Court found that Ransone had breached the contract but that Oertel had failed to prove damages resulting therefrom. As Oertel had failed to terminate the contract as provided for in Article 15.1 of the contract between the parties (the Contract), he was not entitled to invoke the terms of that article. In addition, Oertel had failed to present sufficient evidence to establish the reasonable cost of completion of the structure according to the original contract terms. Consequently, he was not entitled to compensatory damages under Virginia common law.

Plaintiff’s Motion for Reconsideration raises three issues. First, Plaintiff contends that the Court erred in placing the onus on him to terminate the contract before seeking recovery pursuant to Article 15.1 of the Contract. [544]*544Second, Plaintiff argues that the Court incorrectly assigned to him the burden of proving the reasonableness of the damages claimed. Finally, Plaintiff argues that the Court erred by not ordering Defendant to reimburse him at least for the costs of water, sewer, and building permit fees, as well as for costs expended by him to satisfy certain mechanics liens placed on the subject property as a result of Defendant’s failure to pay subcontractors. After due consideration of the written and oral arguments of the parties, the Motion for Reconsideration is denied.

I. Termination of the Contract

Pursuant to Article 15.1 of the Contract, Oertei asserted at trial that he is entitled to recover all sums paid by him to Ransone above and beyond what Ransone paid to his subcontractors and suppliers. In his Motion for Reconsideration, Oertei acquiesces to the Court’s ruling that if Article 15.1 is controlling, Ransone is entitled to retain some funds for the work he performed on the house. Nonetheless, Oertei still claims that he is entitled to recover $20,252.60 for sums paid by him to Ransone. Motion for Reconsideration, pp. 8-9, n. 1. The evidence at trial was clear that Oertei never terminated the Contract. Oertei argues that Ransone’s breach of contract obviated the need for him to terminate.

Article 15.1 of the parties’ contract is entitled “Termination and Suspension” and reads as follows:

If the Contractor fails to perform his obligations as are required by the contract documents, the Owner may terminate the contract. In that case, the Owner will be required to compensate the Contractor for the cost of the work completed and the materials ordered, but will not be obligated to pay the Contractor any other sums.

This clause clearly states that the Owner may terminate the contract, and in that case, he will be required to pay the contractor solely for the cost of work completed. The Court notes first, that by the language of the Contract, termination for Defendant’s failure to perform was at the election of the Plaintiff (“Owner”). Second, the failure to perform can only be understood as a condition precedent to an election to terminate the contract. Therefore, Oertei’s contention that the Defendant’s breach made useless his terminating the contract is without merit. Under Virginia law, unless contrary to public policy, the contract, itself, provides the framework for legal analysis. See McClain v. Arlington County, 249 Va. 131, 452 S.E.2d 659 (1995). [545]*545Generally, there exists a presumption that parties have not used words needlessly. See Winn v. Aleda Constr. Co., 227 Va. 304, 307, 315 S.E.2d 193 (1984). Thus, no words or provisions of a contract will be construed as meaningless if a reasonable meaning can be discerned. Id. Moreover, any ambiguity in the contract will be construed against Oertel, the party who drafted it. Id. While the Plaintiff argues that no one should be required by law to do a useless act, it is the Plaintiff who imposed the burden upon himself to terminate for failure to perform prior to invoking the terms of Article 15.1. Inasmuch as he was bound to render performance on the Contract as a whole, he was bound by this provision as well. Thus, terminating the Contract as a condition precedent to seeking recovery of sums paid out in draws cannot fairly be interpreted as a useless act.

In American Chlorophyll, Inc. v. Schertz, 176 Va. 362, 11 S.E.2d 625 (1940), the Virginia Supreme Court addressed the argument advanced by Oertel herein. Schertz had contracted with American Chlorophyll for royalties stemming from the disclosure of the details of a secret substance for extracting vegetable leaf matter under a formula developed by him. Schertz supplied the formula but was never paid any royalties. The contract contained a termination clause stating that no breach of contract would automatically terminate the contract and that termination required notice to the offending party. Schertz never gave notice to American Chlorophyll that it was in breach of the contract but filed an action for damages. In answer to Schertz’s complaint, the defendant alleged that Schertz, in violation of his contractual duty to maintain secrecy, had knowingly caused the secret formula to be published in a magazine. Schertz argued that the defendant’s breach precluded them from complaining of his non-compliance with the terms of the contract and obviated the need for his providing notice of termination. The Court rejected this argument stating:

This is an obvious non-sequitur, for by the terms [of the contract notice and termination provision]... compliance or non-compliance could come only when the defendant was in default. The default was a condition precedent to the operation of [the provision], and if defendant’s default should preclude its objecting to complainants non-compliance, the [provision] is a nullity. It is, by its very clear terms not a nullity, but is one of the operative terms of the contract.

Id. at 371 (emphasis in original). Oertel cannot avail himself of a remedy established by his contract without complying with the requirements of the specific article providing the contractual remedy. As Oertel’s trial testimony [546]*546clearly established that he has always contended that Ransone abandoned the project and that Oertel never terminated the contract, Oertel’s request for reconsideration on this issue is denied.

II. Burden of Proving Damages

Oertel next asserts that his expenditure of some $70,000.00 above the maximum guaranteed contract price with Ransone established prima facie evidence of his common law or contractual damages and the Court therefore erred in ruling that he had not proven damages. The Virginia Supreme Court has consistently held that it is the plaintiff who has the burden of proving damages with reasonable certainty. See e.g. Taylor v. Flair Prop. Assoc., 248 Va.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dillingham v. Hall
365 S.E.2d 738 (Supreme Court of Virginia, 1988)
Hailes v. Gonzales
151 S.E.2d 388 (Supreme Court of Virginia, 1966)
Gwaltney v. Reed
84 S.E.2d 501 (Supreme Court of Virginia, 1954)
Brown v. Brown by Beacham
422 S.E.2d 375 (Supreme Court of Virginia, 1992)
Green v. Burkholder
160 S.E.2d 765 (Supreme Court of Virginia, 1968)
Lochaven Co. v. Master Pools by Schertle, Inc.
357 S.E.2d 534 (Supreme Court of Virginia, 1987)
D.C. McClain, Inc. v. Arlington County
452 S.E.2d 659 (Supreme Court of Virginia, 1995)
Estate of Taylor v. Flair Property Associates
448 S.E.2d 413 (Supreme Court of Virginia, 1994)
Winn v. Aleda Const. Co., Inc.
315 S.E.2d 193 (Supreme Court of Virginia, 1984)
Kirk Reid Company v. Fine
139 S.E.2d 829 (Supreme Court of Virginia, 1965)
American Chlorophyll, Inc. v. Schertz
11 S.E.2d 625 (Supreme Court of Virginia, 1940)
Sligo Parkway Apartments v. Landscape Engineering Co.
94 S.E.2d 208 (Supreme Court of Virginia, 1956)

Cite This Page — Counsel Stack

Bluebook (online)
52 Va. Cir. 543, 1997 Va. Cir. LEXIS 588, Counsel Stack Legal Research, https://law.counselstack.com/opinion/oertel-v-ransone-vaccfairfax-1997.