Gunnell v. Nello L. Teer Company

135 S.E.2d 104, 205 Va. 28, 1964 Va. LEXIS 141
CourtSupreme Court of Virginia
DecidedMarch 9, 1964
DocketRecord 5668
StatusPublished
Cited by6 cases

This text of 135 S.E.2d 104 (Gunnell v. Nello L. Teer Company) is published on Counsel Stack Legal Research, covering Supreme Court of Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gunnell v. Nello L. Teer Company, 135 S.E.2d 104, 205 Va. 28, 1964 Va. LEXIS 141 (Va. 1964).

Opinion

Spratley, J.,

delivered the opinion of the court.

On March 20, 1960, John Thomas Gould, a civil engineer, employed by and representing Nello L. Teer Company, sometimes hereinafter referred to as the defendant or Teer, sought out Bruce C. Gunnell with reference to the purchase “of fill dirt” or “common borrow” to be used by Teer in the construction of a circumferential highway, also known as Route 413, a project of the State Highway Commission of Virginia. Gunnell owned several tracts of land containing about 125 acres, through which the highway was to be constructed.

There was a series of conferences between Gunnell and Gould, during which the two discussed the terms of a contract for the sale of the dirt. Gunnell knew Teer wanted to get the fill dirt from his land because it was closer to the project involved than another area allocated to Teer by the Highway Commission. During the negotiations, Francis L. Holloway, a civil engineer, who qualified as an expert in the field of soil mechanics, geology, engineering and road construction, at the direction of Teer, tested the soil of Gunnell for gravel. He satisfied himself that the gravel was suitable for use in the construction of the proposed road; but did not undertake to determine whether the common dirt was suitable. Gould also went upon plaintiffs’ lands and made a visual and physical examination of the soil. Gunnell agreed that he would hold his land available for the exclusive use of Teer, and allow the latter a free hand in connection with the removal of the dirt; but that he would have to be paid “for tying up his land for the benefit of” Teer. He said that he would require Teer to provide for the payment of a minimum sum of money, regardless of whether it removed any dirt. In addition, Teer was to build a road on plaintiffs’ land to haul the dirt to the highway under construction.

A contract embodying the agreement between Gould and Gunnell was executed on July 29, 1960, by the Nello L. Teer Company on the one part, and Bruce C. Gunnell and Virginia Burt Gunnell, his wife, hereinafter sometimes referred to as plaintiffs, parties of the second part. The contract contained the following recitals and provisions: a description of the Gunnell land involved, permission for *30 Teer to go on said property to remove dirt fill therefrom for the period of two years, or until it had completed its work on Highway Route 413; a provision that Teer would “remove 250,000 cubic yards of borrow, or in the alternative, pay Gunnell for 250,000 cubic yards of borrow [$12,500.00] as a minimum payment thereunder;” that Gunnell would make available 400,000 cubic yards of dirt fill, for which Teer would pay “5<£ per cubic yard, as measured in the pit for the borrow,” or “minimum payment of Twelve Thousand, Five Hundred Dollars at the termination of this agreement or operation;” and that Gunnell would cooperate with Teer in acquiring necessary permits for the removal of the dirt. In addition, Teer agreed that it would construct “a haul road with a 70-foot wide right of way” from Gunnell’s land to the intersection of Route 413 with Clermont Drive, and leave the road at the termination of the agreement “in good repair and passable.”

After the execution of the contract, tests were run by defendant’s agents on plaintiffs’ land to ascertain the quality of the dirt, and although it was agreed between the parties that such tests should be submitted to the plaintiffs, no reports thereof were ever submitted. On the basis of the test results, the Highway Commission refused to allow the soil on plaintiffs’ land to be used by Teer in the construction of the highway. Thereupon, Teer declined to take any dirt from plaintiffs’ property, refused to pay them any sum of money, or to proceed with the construction of the proposed haul road. In the meantime, at the request of Teer, it had been given permission at least three times to delay the construction of the haul road, at which times it made no complaint that the contract was not to be regarded as in full force and effect.

On April 26, 1961, counsel for Teer, in reply to a demand from Gunnell that it perform its obligations under the contract, wrote a letter to Gunnell asserting that there “was a mutual mistake concerning the substance of the contract, because both parties were under the impression, at the time of entering into the contract, that Teer could and would use the borrow from Gunnell’s property on the said project;” that since the dirt did not meet the specifications of the “State Highway Department,” and it, Teer, was not allowed to use same, there was a failure of consideration; that, therefore, the contract had become impossible of performance; and Teer would not proceed with the construction of the haul road or pay the Gunnells any sum of money.

*31 Plaintiffs, during this time, withheld the development of their property and kept it exclusively for the use of Teer until November, 1961. In March, 1961, a portion of their land had been rezoned from industrial to residential property, and plaintiffs claimed this reduced its value.

On November 6, 1961, Bruce C. Gunnell and Virginia Burt Gunnell, his wife, instituted this proceeding, by motion for judgment against Nello L. Teer Company for damages for breach of the above mentioned contract. They claimed that they were entitled to recover $12,500.00, regardless of whether any dirt was taken by Teer; and the further sum of $7,226.00 damages alleged to have been sustained by the failure of Teer to construct the said haul road, which latter amount represented the estimated cost of constructing the road.

Teer answered and for its defense relied upon the same grounds asserted in the letter of its counsel dated April 26, 1961.

At the conclusion of plaintiffs’ evidence, the court reserved its ruling on a motion of defendant to strike the evidence. At the conclusion of all of the evidence, each party moved to strike the evidence of the other. The court, expressing doubt as to whether its conclusion was in conflict “with some mighty good law,” overruled the motion of the plaintiffs, granted the defendant’s motion, and entered judgment for the defendant. Plaintiffs excepted to each ruling of the court, and upon their petition, we granted this writ of error.

The controlling issue for our determination is, as stated by Teer in its brief: “Whether the contract in question was void and unenforceable on the grounds of mutual mistake, or impossibility of performance, due to a mutual mistake as to the existence of ‘fill dirt’ or ‘borrow,’ which would meet Virginia Department of Highways specifications.”

The facts are not in material conflict. The lands of the plaintiffs contained sufficient deposits of fill dirt to satisfy the requirements of the contract. The only mistake was as to the quality of the fill dirt. The bargain between the parties was at arm’s length. There was no warranty of quality. There was no evidence that the sellers were familiar with the special quality of their dirt, or with the specifications of the Highway Commission. Teer was familiar with those specifications, and if it had desired to make proper tests of the soil, it could have done so before signing the contract. It was admitted by Teer’s representatives that there had been no discussion between the parties relative to the quality of the dirt. The State *32

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Conway v. Peace
28 Va. Cir. 226 (Chesterfield County Circuit Court, 1992)
In Re Schenck Tours, Inc.
69 B.R. 906 (E.D. New York, 1987)
Juarez v. Hamner
674 S.W.2d 856 (Court of Appeals of Texas, 1984)
Mobil Oil Corporation v. Tennessee Valley Authority
387 F. Supp. 498 (N.D. Alabama, 1974)
Green v. Burkholder
160 S.E.2d 765 (Supreme Court of Virginia, 1968)
Holz v. Coates Motor Co.
147 S.E.2d 152 (Supreme Court of Virginia, 1966)

Cite This Page — Counsel Stack

Bluebook (online)
135 S.E.2d 104, 205 Va. 28, 1964 Va. LEXIS 141, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gunnell-v-nello-l-teer-company-va-1964.