Inviting Structures, Inc., d/b/a State of the Art Landscape v. Margit E. Royal

Court of Appeals of Virginia·Decided June 23, 2026·No. 0116254·Unpublished

Opinion

COURT OF APPEALS OF VIRGINIA Record No. 0116-25-4

INVITING STRUCTURES, INC., d/b/a STATE OF THE ART LANDSCAPE v.

MARGIT E. ROYAL, ET AL.

Present: Judges Lorish, Callins and White Argued at Alexandria, Virginia Opinion Issued June 23, 2026*

FROM THE CIRCUIT COURT OF LOUDOUN COUNTY Matthew P. Snow, Judge

Warren R. Stein (Warren R. Stein, P.C., on briefs), for appellant. Stephen C. Price (Theresa D. Small; McCandlish and Lillard, P.C., on brief), for appellees.

MEMORANDUM OPINION BY

JUDGE KIMBERLEY SLAYTON WHITE

Inviting Structures, Inc., d/b/a State of the Art Landscape (SOTAL) appeals the circuit court’s judgment awarding Margit Royal and Jerry Wolford (Homeowners) monetary damages on their complaint for breach of a landscaping contract and barring SOTAL’s counterclaim. SOTAL argues that the circuit court erred by finding that it had committed the first material breaches of the contract and improperly awarded Homeowners damages on their claims for allegedly defective and incomplete work. SOTAL also challenges the circuit court’s finding that the contract required formal written change orders. Homeowners assign cross-error to the circuit court’s refusal to award them damages to replace a spa tub. For the reasons stated below, we

*

This opinion is not designated for publication. See Code § 17.1-413(A).

affirm in part, reverse in part, and remand to the circuit court for further proceedings consistent with this opinion.

BACKGROUND1

SOTAL provides landscaping services in Virginia. In July 2018, SOTAL contracted with Homeowners to complete a landscaping project and build an outdoor spa tub on Homeowners’ property. The contract provided that SOTAL would construct a bluestone terrace, patio, and step sections on the property; plant a Japanese garden; install lighting and a wind chime mount in the garden; accept delivery of the spa tub from the manufacturer and install it on the property; build a structure to house the spa tub mechanics; and complete other specified items for a total price of $232,180. SOTAL was to plant the garden according to a specific plan included in the contract, which designated the number and location of the flowers and trees to be planted.

The contract also provided that Homeowners would pay SOTAL according to a draw schedule. The schedule consisted of an initial deposit of $60,0002 and four subsequent payments to be made upon completion of different stages of the project. Homeowners would pay $60,000 after concrete subslabs were poured; $60,000 after the veneer stones were laid on the concrete foundation; $40,000 after the spa tub was delivered; and $12,180 after the planting was completed. In the event Homeowners did not pay an invoice when due, SOTAL “reserved the right to cease all work on the project without breaching this agreement until the outstanding balance is settled” and Homeowners would “remain liable for the outstanding balance in the event work must be stopped due to lack of payment.”

1 Under settled appellate principles, we view the evidence in the light most favorable to Homeowners, the prevailing party in the trial court. Moncrieffe v. Deno, 76 Va. App. 488, 496 (2023).

2 The initial deposit included a 50% down payment to order the spa tub.

The contract further specified that any changes to the scope of the work or contract price after the contract’s execution “may be accomplished” by change order. The change order “shall be in writing, signed by both parties or approved via email, and shall specify the change in the [w]ork, amount of any adjustment to the [c]ontract price, necessary deposits and the extent of any adjustment in the completion date.” The contract did not impose a firm deadline for completing the project but stated that SOTAL anticipated substantial completion by November 2018.

The parties signed the contract, and Homeowners paid the initial $60,000 deposit. Soon after signing, the parties agreed by email that SOTAL would not build the structure to house the spa tub mechanics as specified in the contract, and instead, the mechanics would be placed in a crawl space in the home’s basement. The emails did not indicate any agreement to adjust the contract price accordingly. In September 2018, SOTAL sent a subcontractor to the property to begin planting the garden. Later that month, Royal sent an email informing SOTAL that the subcontractor was not planting the garden according to the landscape plan in the contract. Specifically, Royal noted that some Hakone grasses had been planted in the wrong location and that a different plant had been installed in the location where mops were to be planted. Royal instructed SOTAL to halt the planting for two weeks while she was out of town and to not resume the work until she had returned.

On October 4, 2018, SOTAL began pouring concrete subslabs and issued an invoice for the first $60,000 progress payment. Homeowners paid the invoice on October 15, although emails sent on October 21 and 22 warned SOTAL that the weather may soon become too cold to continue pouring concrete. On October 23, the parties agreed by email that Homeowners would pay $1,900 for additional sod installation in the garden and $4,800 for rock removal and additional masonry work on the property—items which were not originally included in the contract. Homeowners also requested that the sod be watered but did not specify a price for the watering. On October 30, Royal

sent SOTAL an email stating that, while the landscape plan in the contract was an “excellent guide,” adjustments could be made to the plan where necessary. Royal suggested specific changes to the plan, including using sedum in place of liriope and relocating two cypress trees. She also asked SOTAL to stop planting and ordering new plant material until the sod installation was complete and the parties decided on the placement of the spa tub.

On November 5, 2018, SOTAL issued an invoice for the second $60,000 progress payment, the additional fees agreed to for the sod installation and masonry work, and an additional charge of $2,400 for watering the sod; the invoice reflected a total balance due of $69,100. Homeowners paid $62,000 towards the balance due on this invoice. On November 7, 2018, SOTAL sent an email proposing a $3,450 charge to build an additional wall on the terrace, but Homeowners did not respond. On November 12, 2018, SOTAL sent an email informing Homeowners that a shipment of bluestones needed to complete the masonry work would be delayed. On December 5, 2018, the parties agreed by email to eliminate the wind chime mount from the contract. On February 6, 2019, SOTAL informed Homeowners that the spa tub would be delivered to the property soon and issued an invoice for the third progress payment of $40,000, plus the proposed $3,450 charge for the additional terrace work. On March 6, 2019, SOTAL issued an invoice for the last progress payment of $12,180. Homeowners never paid the last two invoices.

When Homeowners raised concerns about the spa tub delivery and the outstanding invoices, SOTAL proposed an addendum to the contract specifying that the third progress payment would be due only after SOTAL had accepted delivery of the spa tub from the manufacturer, transported the spa tub to the property, completed all plumbing and electric installation, filled the spa tub with water, and rendered the spa tub in a fully operational condition. But Homeowners never signed the addendum or agreed to its terms. On March 7, 2019, Royal sent SOTAL an email expressing her concern that no progress was being made on the landscaping and planting work. SOTAL received

the spa tub from the manufacturer later that month3 and delivered it to Homeowners on May 3, 2019.

Free access — add to your briefcase to read the full text and ask questions with AI

Inviting Structures, Inc., d/b/a State of the Art Landscape v. Margit E. Royal, (Va. Ct. App. 2026).

Inviting Structures, Inc., d/b/a State of the Art Landscape v. Margit E. Royal (Inviting Structures, Inc., d/b/a State of the Art Landscape v. Margit E. Royal) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Napper v. ABM JANITORIAL SERVICES
726 S.E.2d 313 (Supreme Court of Virginia, 2012)
Nichols Const. v. Virginia MacHine Tool
661 S.E.2d 467 (Supreme Court of Virginia, 2008)
PMA Capital Ins. Co. v. US Airways, Inc.
626 S.E.2d 369 (Supreme Court of Virginia, 2006)
Reid v. Boyle
527 S.E.2d 137 (Supreme Court of Virginia, 2000)
Horton v. Horton
487 S.E.2d 200 (Supreme Court of Virginia, 1997)
Mann v. Clowser
59 S.E.2d 78 (Supreme Court of Virginia, 1950)
Clevert v. Jeff W. Soden, Inc.
400 S.E.2d 181 (Supreme Court of Virginia, 1991)
Lochaven Co. v. Master Pools by Schertle, Inc.
357 S.E.2d 534 (Supreme Court of Virginia, 1987)
Kirk Reid Company v. Fine
139 S.E.2d 829 (Supreme Court of Virginia, 1965)
RESTON SURGERY CENTER v. CITY OF ALEXANDRIA and PMA Management Corp.
750 S.E.2d 214 (Court of Appeals of Virginia, 2013)
Commonwealth v. Swann (ORDER)
776 S.E.2d 265 (Supreme Court of Virginia, 2015)
Neely v. White
14 S.E.2d 337 (Supreme Court of Virginia, 1941)