Moore Bros. Construction Co. v. Brown & Root, Inc.

962 F. Supp. 838, 1997 U.S. Dist. LEXIS 10901
CourtDistrict Court, E.D. Virginia
DecidedApril 22, 1997
DocketCivil Action 96-1809-A, 96-1810-A
StatusPublished
Cited by1 cases

This text of 962 F. Supp. 838 (Moore Bros. Construction Co. v. Brown & Root, Inc.) is published on Counsel Stack Legal Research, covering District Court, E.D. Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Moore Bros. Construction Co. v. Brown & Root, Inc., 962 F. Supp. 838, 1997 U.S. Dist. LEXIS 10901 (E.D. Va. 1997).

Opinion

MEMORANDUM OPINION

BRINKEMA, District Judge.

This case arises out of the construction of the Dulles Toll Road Extension (DTRE). Two subcontractors, Moore Brothers Construction Company (Moore) and The Lane Construction Company (Lane), have sued the general contractor, Brown & Root, Inc., and the surety, Highlands Insurance Co. (Highlands), alleging that they have not been fully paid. The case comes before this Court on plaintiffs’ Joint Motion for Summary Judgment and Highlands’ Cross-Motion for Summary Judgment. At issue between these parties is whether Highlands is bound by its contract payment bond for the project to pay the plaintiffs for work they performed under their subcontracts with Brown & Root.

I.

The DTRE is a 14-mile long private toll road between Dulles International Airport and Leesburg, Virginia. It was built and is operated by the Toll Road Investors Partnership II (TRIP). In 1993, TRIP awarded the general toll road construction contract to defendant Brown & Root. Brown & Root Ln turn entered subcontracts with Moore and Lane to build parts of the road.

Defendant Highlands issued a contract payment bond as surety. The contract payment bond states:

*840 The above-named Principal [Brown & Root] and Surety [Highlands] hereby jointly and severally agree with the Obligees that every claimant as herein defined, who has not been paid in full before the expiration of a period of ninety (90) days after the date on which the last of such claimant’s work or labor was done or performed, or materials were furnished by such claimant, may sue on this bond for the use of such claimant, prosecute the suit to final judgment for such sum or sums as may be justly due claimant, and have execution thereon.

A claimant is defined as “one having a direct contract with the Principal or with a Subcontractor ... of the Principal for labor, material or both, used or reasonably required for use in the performance of the Construction Contract.” It is uncontested that Moore and Lane are claimants under the payment bond because they have direct contracts with Brown & Root.

The bond becomes void only when Brown & Root pays the claimants:

if the above bounden Principal shall (I) promptly pay all just claims for labor and material (including public utility services and reasonable rental or equipment when such equipment is actually used at the site) performed to or supplied to said principal or any subconti'actor or any supplier in the prosecution of the work contracted for under the Construction Contract., then this obligation is to be void, otherwise, this obligation shall be and remain in full force....

The parties agree that Brown and Root paid Moore and Lane their base contract prices, respectively, $34,015,112.50 and $39,-532,000.00. Plaintiffs allege that they are owed more for their work under the contract. Specifically, Moore claims it is owed $4,584,-147.01 and Lane claims it is owed $3,904,-530.30 based on various change orders. These unpaid amounts arose in two contexts. Under the subcontracts, both Brown a Root and the plaintiffs were to complete all work by March 30, 1996. On September 30, 1994, Brown & Root entered subcontract change orders with each plaintiff providing for early completion bonuses of $13,500.00 per day or 31.5% of the Incentive Bonus Monies paid to Brown & Root by TRIP for early completion. Both plaintiffs completed their sections of the road on September 29, 1995, 180 days ahead of schedule. The next day TRIP issued a Certificate of Substantial Completion certifying that September 30, 1995 was the commencement date for computation of the early completion bonus. Moore and Lane claim that they are each entitled to an early completion bonus of $2,430,00o. 1

In addition, plaintiffs claim they are entitled to additional compensation for extra work they were required to perform. Brown & Root and TRIP disputed whether the original contract included this work. The dispute eventually went to arbitration. The arbitrator issued an award to Brown & Root, including $2,279,147.01 specifically for the benefit of Moore and $1,624,530.30 for the benefit of Lane. The arbitrator reduced these awards for an equipment deduction in a supplemental report. He reduced Moore’s award by $125,000 and Lane’s award by $150,000; therefore, Moore’s final award was $2,154,147.01 and Lane’s final award was $1,474,530.30. The Loudoun County Circuit Court confirmed the arbitration award and no appeal of that confirmation was taken. Neither Brown & Root nor Highlands has paid the plaintiffs the early completion bonus or the amounts awarded in the arbitration.

II. Analysis

Because there are no disputes as to the facts of this case, it is appropriate to resolve this case by summary judgment. Highlands argues that it does not have to pay Moore and Lane because the principal, Brown & Root, has not yet been paid by TRIP which is now unable to pay its debts. Highlands relies on Section 3.1.4 of each plaintiffs subcontract with Brown & Root, which provides:

Notwithstanding any other provision hereof, payment by Owner to General Contractor is a condition precedent to any ob *841 ligation of General Contractor to make payment hereunder; General Contractor shall have no obligation to make payment to Subcontractor for any portion of the Sublet Work for which General Contractor has not received payment from the Owner.

Highlands argues that it is entitled to the benefit of this “pay-when-paid” clause and that it does not have to pay Moore and Lane because the condition precedent for payment by Brown & Root has not been satisfied. Resolution of the motions for summary judgment essentially turns on whether Highlands can assert the affirmative “pay-when-paid” defense found in plaintiffs’ subcontracts with Brown & Root. Highlands argues that it is not liable to the plaintiffs because it has the right to raise all defenses the principal could raise.

Most of the courts which have dealt with this argument do not allow sureties to invoke “pay-when-paid” defenses appearing in subcontracts, especially when the subcontract is not explicitly incorporated into the payment bond. In OBS Company v. Pace Construction Corporation, 558 So.2d 404 (Fla.1990), a dispute arose over whether a surety had to pay subcontractors on a bond containing identical language to the bond signed by Highlands. The Florida Supreme Court held that “[t]he payment Bond is a separate agreement, and any inability to proceed against the general contractor does not necessarily prevent recovery against the sureties under the Bond.” 558 So.2d at 408. In reaching that conclusion, the court noted that, like here, the payment bond did not incorporate the terms of the subcontracts.

At least two federal district courts have reached the same conclusion. Brown & Kerr Inc. v. St. Paul Fire and Marine Insurance Company, 940 F.Supp. 1245 (N.D.Ill.1996) (not permitting a commercial surety to assert the subcontract “pay-when-paid” clause to escape payment bond liability); Shearman & Associates, Inc. v. Continental Casualty Company, 901 F.Supp. 199 (D.Vi.1995) (same).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lane Construction Corp. v. Brown & Root, Inc.
29 F. Supp. 2d 707 (E.D. Virginia, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
962 F. Supp. 838, 1997 U.S. Dist. LEXIS 10901, Counsel Stack Legal Research, https://law.counselstack.com/opinion/moore-bros-construction-co-v-brown-root-inc-vaed-1997.