Brown & Kerr Inc. v. St. Paul Fire and Marine Ins. Co.

940 F. Supp. 1245, 1996 U.S. Dist. LEXIS 13290, 1996 WL 526785
CourtDistrict Court, N.D. Illinois
DecidedSeptember 12, 1996
Docket95 C 1119
StatusPublished
Cited by18 cases

This text of 940 F. Supp. 1245 (Brown & Kerr Inc. v. St. Paul Fire and Marine Ins. Co.) is published on Counsel Stack Legal Research, covering District Court, N.D. Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brown & Kerr Inc. v. St. Paul Fire and Marine Ins. Co., 940 F. Supp. 1245, 1996 U.S. Dist. LEXIS 13290, 1996 WL 526785 (N.D. Ill. 1996).

Opinion

MEMORANDUM OPINION AND ORDER

ANDERSEN, District Judge.

Plaintiff Brown & Kerr, Inc. (“BKI”) moves for partial summary judgment on Count I of its Amended Complaint against defendant St. Paul Fire and Marine Insurance Company (“St. Paul”). For the following reasons, the motion for partial summary judgment is granted.

BACKGROUND

The following facts, taken from plaintiffs Amended Complaint and the parties’ Local Rule 12M and 12N statements, are undisputed. On February 18,1993, Bucon, Inc. (“Bu-con”) entered into a multi-million dollar design/build contract with Vernon Hills III Limited Partnership (“Vernon Hills”) to perform various construction services for a project known as “The Marketplace” in Vernon Hills, Illinois. Pursuant to the terms of the contract with Vernon Hills, Bucon was to act as general contractor for the Marketplace project.

At the inception of the contract, the sole owner of the premises was Vernon Hills. In 1994, K Mart Corporation (“K Mart”) and Northwestern Mutual Life Insurance Company (“Northwestern Mutual”) also acquired ownership interests in the premises.

On April 6, 1993, defendant St. Paul, as surety, issued a “Labor and Material Payment Bond” (the “Bond”) for the Marketplace project in the amount of $15,735,307 with Bucon as the principal. The owners or obligees on the Bond are Vernon Hills, Northwestern Mutual, and K Mart. The Bond provides in part:

The above named Principal and Surety hereby jointly and severally agree with the Owner that every claimant, as herein defined, who has not been paid in full before the expiration of a period of ninety (90) days after the date on which the last of such claimant’s work or labor was done or performed, or materials were furnished by such claimant, may sue on this bond for *1247 the use of such claimant, prosecute the suit to final judgment for such sum or sums as may be justly due claimant, and have execution thereon. The Owner shall not be liable for the payment of any costs or expenses of any such suit.

(Pl.’s App.Supp.Summ.J.Ex. A at ¶ 2). Claimants are defined to include subcontractors. (Id. at ¶ 1). The Bond further provides that no claimant may bring suit unless that claimant has “given written notice to any two of the following: the Principal, the Owner, or the Surety above named, within ninety (90) days after such claimant did or performed the last of the work or labor” under the contract. (Id. at ¶ 3(a)).

On May 17, 1993, Bucon, as general contractor, entered into two subcontracts with plaintiff BKI totalling $598,603. Pursuant to the subcontracts, BKI was to supply labor and materials for a complete roofing system of the Marketplace project. One subcontract concerned the Super K Mart portion of the project, and the other subcontract concerned the Builders Square Marketplace portion. Article 9.1 of the subcontracts provides in part:

Final Payment constituting the entire unpaid balance of the Subcontract Sum, shall be made by the Contractor to the Subcontractor when the Subcontractor’s Work is fully performed in accordance with the requirements of the Subcontract Documente, the Customer or Customer’s representative has issued its approval for payment covering the Subcontractor’s completed work and the Contractor has received final payment from the Customer under the Prime Contract.

(Def.’s Mem.Opp’n Summ.J. at 3). The subcontracts further provide that, as a condition to the Contractor’s issuance of final payment, the subcontractor shall provide all applicable warranties and guarantees. (Id. at 4).

On October 25, 1994, BKI completed performance under the subcontracts and even performed extras, at the request of Bucon, in the amount of $51,848. BKI subsequently received payments of 544,035.70, and remains owed a total amount of $106,415.30. According to Bucon, there is an unpaid balance on the subcontracts in the amount of $86,879.30. St. Paul does not dispute this amount. Further, as of the filing of the instant motion, Bucon has not received any payment from the owners for work performed at the Marketplace project.

On or about December 16, 1994, BKI forwarded to Bucon the manufacturer’s warranty for the roofing system issued by Firestone Building Products Company. Paragraph 3 of the warranty provides that Firestone has no obligation under the warranty until both Firestone and BKI have been paid in full. (Pl.’s Reply Br.Supp.Summ.J.Ex. B at ¶3). BKI also forwarded to Bucon its own warranty for the roofing system.

On January 9, 1995, BKI served notice of its demand for payment of the remaining balance on the subcontracts, via certified mail, on the three owners and Bucon as required by the Bond. BKI served an additional notice to St. Paul on January 20,1995.

BKI subsequently received no payment after serving its demand notices on the owners, Bucon, and St. Paul. On February 22, 1995, BKI filed a one-count complaint against St. Paul seeking payment of $106,415.30 under the Bond for its completed work under the subcontracts and “extras.” Jurisdiction was based on diversity of citizenship pursuant to 28 U.S.C. § 1332.

As of April 1995, BKI had still not received the balance due under the subcontracts. Consequently, BKI suspended both the Firestone and BKI warranties.

On June 15, 1995, BKI filed an Amended Complaint adding a second count against St. Paul for vexatious delay in paying BKI’s claim under the Bond in violation of section 155 of the Illinois Insurance Code, 215 ILCS 5/155. This Court dismissed the section 155 vexatious delay claim in Count II for lack of standing on August 12, 1996. See Brown & Kerr, Inc. v. St Paul Fire & Marine Ins. Co., No. 95 C 1119, 1996 WL 464212, at *2 (N.D.Ill. Aug. 12, 1996).

BKI now moves for partial summary judgment on Count I of the Amended Complaint pursuant to Fed.R.Civ.P. 56. SpecificaUy, BKI does not seek to recover the entire $106,415.30 which is aUegedly owed for completed work under the subcontracts and for *1248 “extras” performed at the request of Bucon. Rather, BKI seeks only the final balance of $86,879.30 due under the subcontracts which Bucon has admitted it owes BKI and which St. Paul does not dispute. In sum, BKI requests that we enter partial summary judgment for this undisputed balance of $86,-879.30 due under the subcontracts after whieh “[t]he parties can then thrash out the rest of BKI’s claims.” Presumably, the only remaining claim would be the $51,848 in “extras” performed by BKI at Bucon’s request.

St. Paul argues that BKI is not entitled to partial summary judgment on the following grounds: (1) any defenses under the subcontracts available to Bucon are also available to St. Paul as a surety; (2) because Bucon has not been paid by the owners, St.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Beal Bank Nevada v. NorthShore Center THC, LLC
2016 IL App (1st) 151697 (Appellate Court of Illinois, 2016)
BMD CONTRACTORS v. Fidelity and Deposit Co. of Md.
679 F.3d 643 (Seventh Circuit, 2012)
Evans, Mechwart, Hambleton & Tilton, Inc. v. Triad Architects, Ltd.
965 N.E.2d 1007 (Ohio Court of Appeals, 2011)
BMD Contractors, Inc. v. Fidelity & Deposit Co.
828 F. Supp. 2d 978 (S.D. Indiana, 2011)
Hartford Accident & Indemnity Co. v. Cochran Plastering Co.
935 So. 2d 462 (Court of Civil Appeals of Alabama, 2006)
Wellington Power Corp. v. CNA Surety Corp.
614 S.E.2d 680 (West Virginia Supreme Court, 2005)
Federal Insurance Co. v. I. Kruger, Inc.
829 So. 2d 732 (Supreme Court of Alabama, 2002)
Moore Brothers Co v. Brown & Root Inc
207 F.3d 717 (Fourth Circuit, 2000)
Moore Bros. Construction Co. v. Brown & Root, Inc.
962 F. Supp. 838 (E.D. Virginia, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
940 F. Supp. 1245, 1996 U.S. Dist. LEXIS 13290, 1996 WL 526785, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brown-kerr-inc-v-st-paul-fire-and-marine-ins-co-ilnd-1996.