A. A. Conte, Inc. v. Campbell-Lowrie-Lautermilch Corp.

477 N.E.2d 30, 132 Ill. App. 3d 325, 87 Ill. Dec. 429, 1985 Ill. App. LEXIS 1812
CourtAppellate Court of Illinois
DecidedMarch 28, 1985
Docket83-2765
StatusPublished
Cited by47 cases

This text of 477 N.E.2d 30 (A. A. Conte, Inc. v. Campbell-Lowrie-Lautermilch Corp.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
A. A. Conte, Inc. v. Campbell-Lowrie-Lautermilch Corp., 477 N.E.2d 30, 132 Ill. App. 3d 325, 87 Ill. Dec. 429, 1985 Ill. App. LEXIS 1812 (Ill. Ct. App. 1985).

Opinions

JUSTICE JOHNSON

delivered the opinion of the court:

This appeal arose from a dispute between A. A. Conte, Inc. (Conte), the plaintiff, and Campbell-Lowrie-Lautermilch Corporation (Campbell-Lowrie), the defendant, wherein Conte sought to recover $83,596 which it claimed was owed by Campbell-Lowrie. The trial court granted Campbell-Lowrie’s motion for summary judgment, and Conte brought this appeal.

We are asked to consider whether the trial court erred in granting summary judgment to defendant.

We affirm.

The facts are not in dispute. Campbell-Lowrie was the contractor for a construction project in Northlake. In July 1974, Conte and Campbell-Lowrie entered into a contractual agreement whereby Conte would perform certain work as a subcontractor for Campbell-Lowrie at the construction site. Conte performed excavating work at the construction site between July and December 1974. Campbell-Lowrie had other subcontractors besides Conte, and payments were made to the subcontractors on a monthly basis upon the contractors’ submission of bills to Campbell-Lowrie.

The construction project was owned by La Salle National Bank, as trustee, and three individuals who were beneficial interest owners. In November 1974, the owners defaulted on payments and the project was terminated. Campbell-Lowrie informed its subcontractors, including Conte, that the owners had defaulted and advised the subcontractors to cease work immediately. Conte was owed a sum of $83,956 for work already performed when the project was terminated.

The owners were later determined to be insolvent. Campbell-Lowrie submitted a bill for $149,714.68 to the owners for work done. That bill included the $83,956 owed to Conte. Campbell-Lowrie was not paid by the owners and in turn made no payment to Conte. Subsequently, Conte instituted a claim for a mechanic’s lien against the project for the amount due on its contract with Campbell-Lowrie.

Foreclosure proceedings were instituted against the owners of the project, and Conte sought to execute the mechanic’s lien in those proceedings. The judge in the foreclosure proceedings found that Conte was owed $83,956 for work performed under its subcontract with Campbell-Lowrie. The judge recognized Conte’s mechanic’s lien against the project, but found that the lien was inferior and subordinate to the lien for $610,000 held against the project by Associates Capital Company, Inc. The liens held by Conte and other subcontractors for the project could not be satisfied ahead of that held by Associates Capital. The project was foreclosed and sold early in 1979. Conte unsuccessfully attempted to collect the $83,956 directly from Campbell-Lowrie.

In July 1979, Conte filed suit against Campbell-Lowrie in the circuit court of Cook County seeking to recover the amount in question. Campbell-Lowrie denied indebtedness to Conte and raised an affirmative defense to Conte’s claim. The gist of Campbell-Lowrie’s affirmative defense was that article 18 of its contract with Conte set forth a condition precedent to payment. The condition was that Campbell-Lowrie must first receive payment from the owners of the project under the general contract before it was obligated to pay its subcontractors. The owners had not paid Campbell-Lowrie; therefore, Conte was not entitled to payment from Campbell-Lowrie.

Both parties moved for summary judgment. Conte sought to have the trial court declare that Campbell-Lowrie was obligated to Conte for $83,956. Campbell-Lowrie cited articles 5 and 18 of its contract with Conte, which state:

“ARTICLE 5: Material invoices submitted before the 25th of the current month will be paid by the 28th of the following month, provided the material so delivered is acceptable, and if payment for invoiced material has been received by CampbellLowrie-Lautermilch Corporation under its general contract. Discountable bills will be paid as stipulated in the order.
* * *
ARTICLE 18: *** [I]f the work has been satisfactorily performed and invoice as rendered is approved and if payment for such labor and material so invoiced has been received by Campbell-Lowrie-Lcmtermilch Corporation under its general contract, the subcontractor will be paid 85% of invoice as approved, less any payments previously made on account for previous periods. No payments made shall be considered as evidence of acceptance of the work either in whole or in part until the work is completed and accepted, whereupon final payment will be made within thirty (30) days of such acceptance upon receipt of all or any bonds, guarantees, etc. required.” (Emphasis added.)

Campbell-Lowrie asserted that its payment to Conte was contingent upon its receiving payment from the owners of the project. Based on the contractual language (articles 5 and 18), Campbell-Lowrie had no obligation to pay Conte since it had not been paid by the owners. The parties filed several memoranda of law in support of their respective positions.

On October 17, 1983, the trial court denied Conte’s motion for summary judgment and granted that of Campbell-Lowrie.

On appeal, Conte argues that the contractual provisions cited by Campbell-Lowrie in its affirmative defense was a limitation only as to the time of payment. The provisions gave Campbell-Lowrie a reasonable time in which to pay Conte without respect to whether Campbell-Lowrie had been paid by the owners. Conte urges this court to look at other factors outside the contract to determine the understanding and intent of the parties. Conte points out that the trial court’s denial of its (Conte’s) motion for summary judgment leads to the conclusion that the language of the contract was ambiguous; therefore, interpretation of the contractual provisions was a question of fact to be determined by the trier of fact. Accordingly, Conte concludes that it was error for the trial court to have granted CampbellLowrie’s motion for summary judgment.

Campbell-Lowrie points out that the plain meaning of the language in articles 5 and 18 of the contract creates a condition precedent to payment and that there is no ambiguity in the language. Campbell-Lowrie correctly states that whether a contract is ambiguous is a question of law and ambiguity can be found only if the language is reasonably or fairly susceptible of more than one construction. Additionally, failure of the parties to agree on proper construction does not render a contract ambiguous.

In determining the meaning of the contract, especially with regard to paragraphs 5 and 18, every effort must be made to effectuate the intentions of the parties. (National Aircraft Leasing, Ltd. v. American Airlines, Inc. (1979), 74 Ill. App. 3d 1014, 1020, 394 N.E.2d 470, 475.) A court must arrive at meaning from language used in the contract (Vigilante v. National Bank (1982), 106 Ill. App. 3d 820, 823, 436 N.E.2d 652, 655), and if the language in the contract is clear and unambiguous then no evidence outside the contract itself may be considered in determining the contract’s meaning. National Aircraft Leasing, Ltd. v. American Airlines, Inc. (1979), 74 Ill. App.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cooper v. Cooper
N.D. Illinois, 2023
Pepper Construction Co. v. Palmolive Tower Condominiums, LLC
2021 IL App (1st) 200753 (Appellate Court of Illinois, 2021)
People v. Eubanks
2020 IL App (3d) 180117 (Appellate Court of Illinois, 2020)
Beal Bank Nevada v. NorthShore Center THC, LLC
2016 IL App (1st) 151697 (Appellate Court of Illinois, 2016)
Jeffrey Wissot v. Great-West Life & Annuity Ins.
619 F. App'x 603 (Ninth Circuit, 2015)
Riley J. Wilson v. Career Education Corporation
729 F.3d 665 (Seventh Circuit, 2013)
MHM Services v. Assurance Company of America
2012 IL App (1st) 112171 (Appellate Court of Illinois, 2012)
Brown & Kerr Inc. v. St. Paul Fire and Marine Ins. Co.
940 F. Supp. 1245 (N.D. Illinois, 1996)
J & K PAINTING CO. v. Bradshaw
45 Cal. App. 4th 1394 (California Court of Appeal, 1996)
Premier Electrical Construction Co. v. American National Bank
658 N.E.2d 877 (Appellate Court of Illinois, 1995)
George S. May International Co. v. King
629 N.E.2d 257 (Indiana Court of Appeals, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
477 N.E.2d 30, 132 Ill. App. 3d 325, 87 Ill. Dec. 429, 1985 Ill. App. LEXIS 1812, Counsel Stack Legal Research, https://law.counselstack.com/opinion/a-a-conte-inc-v-campbell-lowrie-lautermilch-corp-illappct-1985.