United States v. George Schaeffer, Jr., and Elsie Schaeffer, His Wife

319 F.2d 907
CourtCourt of Appeals for the Ninth Circuit
DecidedOctober 17, 1963
Docket18291_1
StatusPublished
Cited by42 cases

This text of 319 F.2d 907 (United States v. George Schaeffer, Jr., and Elsie Schaeffer, His Wife) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. George Schaeffer, Jr., and Elsie Schaeffer, His Wife, 319 F.2d 907 (9th Cir. 1963).

Opinion

JAMESON, District Judge.

Appellant brought this action to recover construction and maintenance costs, enforce covenants running with the land, and foreclose liens, pursuant to repayment contracts executed by the appellees or their predecessors in title, in connection with the Lummi Diking Project constructed by the Government pursuant to the Act of March 18, 1926, 44 Stat. 211. 1 The district court entered summary judgment for the appellees, based upon facts admitted in a pretrial order, holding that there was a “fatal want of equity as to the case of the plaintiff, and in particular that any and all rights it may have had * * * were subject to a certain condition precedent and that the same was not fulfilled, and that in no other respects has it any lawful grounds of recovery * * * or does it have or possess any lawful lien * * * ”. The United States has appealed from the summary judgment.

The purpose of the Lummi Diking Project was to construct dikes for the protection of lands within the Lummi Indian Reservation and those in private ownership adjoining the reservation on the east, including the lands here involved, from the overflow of fresh water at flood stages from the Nooksack River, the eastern boundary of the project lands, and the overflow by salt water tides from the Lummi River on the southwest side of the reservation.

All of the appellees executed repayment contracts in which they agree “to and with the Secretary of the Interior and with all other landowners whose lands may be included within the project, in consideration of the premises, the promises of said other landowners, and the work to be done by the United States in connection with the project, that if the Secretary * * * shall construct dikes ■ for the purpose contemplated in the Act”, their lands “shall at once be and become burdened with and subject to a first lien” to secure “the full payment of a pro rata share of the entire cost of said project and all of the betterment, operation and maintenance charges, and penalties in connection therewith; * * * ”. 2

*910 Prior to the execution of the contracts, the appellees or their predecessors in title were notified that the Secretary of the Interior had determined the identity and area of the lands to be benefited. He had divided the lands into four classes, according to the relative benefits. Appellees’ lands were in Class I, were not affected by the salt water tides, and the construction charge was fixed at $8.00 per acre.

Before commencing construction, the Secretary’s agents obtained repayment contracts from all except one of the owners of private lands outside the reservation in the same area with appellees. The owners of the other lands outside the reservation executed a supplemental agreement under which they agreed to assume their respective shares of the cost assessable against the nonsigning owner.

The Secretary proceeded to construct the dikes and expend the funds appropriated by Congress without procuring the execution of repayment contracts from the owners of seven tracts of land in private ownership located inside the reservation. This court held in Hood v. United States, 9 Cir., 1958, 256 F.2d 522, that there was no lien upon those tracts, that they were improperly included by the Secretary in the schedule of charges allocating pro rata costs of construction, and that there was no basis for the imposition of any charge for operation and maintenance. The title of the landowners was quieted against the claims of the Government.

On August 9, 1930, after construction was completed, the Secretary issued the “public notice” required by the Act, fixing the construction costs assessed against each acre in the project, and payment terms. 25 CFR (1949 ed) § 144. This notice included the names and lands of the seven nonsigning owners within the reservation. Prior to the final determination of Hood v. United States, supra, the Secretary claimed and asserted that the Government had valid liens against those lands.

There has been no change in the allocation of construction costs among appellees by reason of the determination that the Government has no lien or claim against the lands of the seven nonsigning owners. Appellees do not dispute the distribution of the construction costs, but do dispute their validity.

Since the completion of the construction, assessments have been made against the owners of all lands for the cost of operation and maintenance on a pro rata basis. 3 Prior to the decision in the Hood case, the Government claimed a lien for maintenance and operation charges against all lands in private ownership, including the lands of nonsigners.

Appellees and their predecessors in title have made some payments on both construction charges and operation and maintenance charges, but have refused and neglected to make others.

Three questions are presented:

1. Whether the rights of the United States were subject to a condition precedent which had not been fulfilled, because the seven landowners did not execute similar contracts.

2. Whether the United States has a lien on the properties of appellees in view of the contract provision that if the Secretary of the Interior shall construct the dikes for the purpose contemplated in the Act, the lands shall at once become burdened with and subject to a first lien.

*911 3. Whether under the admitted facts there is a fatal want of equity to justify the position of the claimed liens because of lack by appellant of fair dealing with appellees, and impossibility of enforcing the alleged contracts without, in effect, writing new contracts and imposing inequitable burdens.

Appellees contend that the execution of the repayment contracts by all private landowners within the project was a condition precedent, that the dikes accordingly were constructed in violation of law, and that appellees are not obligated under their contracts to pay the delinquent assessments for either construction or maintenance. Appellant contends that obtaining repayment contracts from all of the private landowners was not a condition precedent to the validity of the contracts with appellees, and the fact that a few landowners did not execute contracts was at most a partial failure of consideration which would not terminate the contracts.

A condition precedent is “a fact (other than mere lapse of time) which * * * must exist or occur before a duty of immediate performance of a promise arises, * * * Restatement of the Law, Contracts § 250. Williston defines a condition precedent as “a fact or event which the parties intend must exist or take place before there is a right to performance”. 5 Williston on Contracts 3d ed., 126-127, § 663, quoting from Lach v. Cahill, 138 Conn. 418, 85 A.2d 481.

“No particular form of words is necessary in order to create an express condition. Whether a promise.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

German v. Ford
300 S.W.3d 692 (Court of Appeals of Tennessee, 2009)
Consumers Energy Co. v. United States
65 Fed. Cl. 364 (Federal Claims, 2005)
Richard Charron v. United States
200 F.3d 785 (Federal Circuit, 1999)
Charron v. United States
200 F.3d 785 (Federal Circuit, 1999)
D'Addario v. D'Addario
603 A.2d 1199 (Connecticut Appellate Court, 1992)
D'Addario v. D'addario, No. 256879 (Apr. 24, 1991)
1991 Conn. Super. Ct. 3615 (Connecticut Superior Court, 1991)
Gilbane Building Co. v. Brisk Waterproofing Co.
585 A.2d 248 (Court of Special Appeals of Maryland, 1991)
Favell v. United States
22 Cl. Ct. 132 (Court of Claims, 1990)
Riggs National Bank of Washington, D.C. v. District of Columbia
581 A.2d 1229 (District of Columbia Court of Appeals, 1990)
Barrett v. Weyerhaeuser Co. Severance Pay Plan
700 P.2d 338 (Court of Appeals of Washington, 1985)
A. A. Conte, Inc. v. Campbell-Lowrie-Lautermilch Corp.
477 N.E.2d 30 (Appellate Court of Illinois, 1985)
Carr v. Benike, Inc.
365 N.W.2d 4 (South Dakota Supreme Court, 1985)
Norton v. Herron
677 P.2d 877 (Alaska Supreme Court, 1984)
Maruyama & Associates, Ltd. v. Mariana Islands Housing Authority
1 N. Mar. I. Commw. 798 (Northern Mariana Islands, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
319 F.2d 907, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-george-schaeffer-jr-and-elsie-schaeffer-his-wife-ca9-1963.