Gilbane Building Co. v. Brisk Waterproofing Co.

585 A.2d 248, 86 Md. App. 21, 1991 Md. App. LEXIS 36
CourtCourt of Special Appeals of Maryland
DecidedFebruary 4, 1991
Docket552, September Term, 1990
StatusPublished
Cited by27 cases

This text of 585 A.2d 248 (Gilbane Building Co. v. Brisk Waterproofing Co.) is published on Counsel Stack Legal Research, covering Court of Special Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gilbane Building Co. v. Brisk Waterproofing Co., 585 A.2d 248, 86 Md. App. 21, 1991 Md. App. LEXIS 36 (Md. Ct. App. 1991).

Opinion

BLOOM, Judge.

In an action by Brisk Waterproofing Company, Inc. (Brisk) against Gilbane Building Company (Gilbane) for work done by Brisk as a subcontractor of Gilbane, the general contractor, the Circuit Court for Prince George’s County entered summary judgment in favor of Brisk, from which Gilbane has taken this appeal. Brisk cross-appealed from the denial of pre-judgment interest.

We agree with Gilbane’s contention that the court erred as a matter of law in granting Brisk’s motion for summary *23 judgment; accordingly, we shall reverse the judgment, thus rendering the cross-appeal moot.

Facts

The facts of this case, as set forth in the parties’ agreed statement of the case, submitted in lieu of the record pursuant to Md.Rule 8-413(b), may be summarized as follows.

Carley Capital Group was the owner of a project in Baltimore City known as “Henderson’s Wharf.” The project was designed to convert warehouses in the Fells Point area of the city into residential condominiums. On 4 September 1987, Carley and Gilbane executed a construction contract wherein Gilbane agreed to act as Carley’s construction manager and general contractor for the project. Shortly thereafter, Gilbane and Brisk executed two subcontracts wherein Brisk agreed to perform certain masonry work on the project for a total price of $1,989,058.

Brisk received periodic payments from Gilbane as the work progressed. By August, 1988, Brisk had satisfactorily performed all of its obligations under both subcontracts and requested final payment of the outstanding balance of $283,079. Gilbane refused to tender the final payment on the ground that it had not received payment from Carley Capital Group. Brisk subsequently established a mechanic’s lien against the property; however, in December 1988 the holder of a third deed of trust on the property foreclosed. Since the resulting foreclosure sale failed to yield any surplus to satisfy the mechanic’s lien, the lien was extinguished.

On 10 March 1989, Carley Capital Group was forced into a Chapter 7 bankruptcy, which was subsequently converted to a Chapter 11 proceeding on 9 April 1989. Thereafter, Brisk filed this action against Gilbane in the Circuit Court for Prince George’s County, seeking payment of the $283,-079 due on the subcontracts plus prejudgment interest of 10% per annum from the date of the Carley bankruptcy. *24 The case was submitted on an agreed statement of facts. After considering the cross-motions for summary judgment filed by the parties, the court granted Brisk’s motion for summary judgment in the amount of $283,079 but denied its request for prejudgment interest.

Discussion

When ruling on a motion for summary judgment, the trial court must consider whether the pleadings, depositions, answers to interrogatories, admissions, and affidavits show that there is no genuine dispute as to any material fact and whether the moving party is entitled to judgment as a matter of law. Md.Rule 2-501(e). See also, Syme v. Marks Rentals, Inc., 70 Md.App. 235, 238, 520 A.2d 1110 (1987). Since submission of the case on an agreed statement of facts precludes any dispute between the parties as to any material fact, our scope of review is limited to whether the trial court was correct in awarding judgment to Brisk as a matter of law. Department of Environment v. Showell, 316 Md. 259, 267-68, 558 A.2d 391 (1989); City of Baltimore v. Fid. & Dep. Co., 282 Md. 431, 446, 386 A.2d 749 (1978); Brewer v. Mele, 267 Md. 437, 441, 298 A.2d 156 (1972).

Gilbane contends that both subcontracts clearly establish that its receipt of payment from the owner, Carley Capital Group, is a condition precedent to its obligation to pay Brisk. The subcontracts provide, in pertinent part, as follows:

3.2 On the established day of each month, the trade contractor [Brisk] shall deliver to the construction manager [Gilbane], a detailed, quadruplicate statement acceptable to the construction manager, and if required, supported by receipts, vouchers, etc. showing values of all materials delivered and work completed up to the established billing date for which payment is requested. Monthly and final payments will be made to the trade contractor within five (5) days after receipt of payment by the construction manager from the owner. The retained *25 percentage will be forwarded as soon as received by the construction manager from the owner. It is specifically understood and agreed that the payment to the trade contractor is dependent, as a condition precedent, upon the construction manager receiving contract payments, including retainer from the owner. (Emphasis added.)

Brisk, on the other hand, contends, and the trial court agreed, that the above language constitutes merely a “pay when paid” clause, which postpones the time for payment until the happening of a certain event or for a reasonable period of time if such event does not occur, rather than a condition precedent to the obligation to pay. In holding that the subcontracts do not address the prospect of owner insolvency, the trial court stated,

I conclude the clause does not exempt insolvency, that that is such an extraordinary condition that has a direct bearing on payment, that in order for it to act as a bar to recovery by the subcontractor it has to be specifically mentioned by the parties. It is not in this case.

In support of the trial court’s ruling that the subcontracts did not shift the risk of owner insolvency from Gilbane, Brisk relies on Atlantic States Constr. Co. v. Drummond & Company, Inc., 251 Md. 77, 246 A.2d 251 (1968). In Atlantic, the Court of Appeals observed that

“Normally and legally, the insolvency of the owner will not defeat the claim of the subcontractor against the general contractor. Accordingly, in order to transfer this normal credit risk incurred by the general contractor to the subcontractor, the contract between the general contractor and subcontractor should contain an express condition clearly showing that to be the intention of the parties.”

251 Md. at 82, 246 A.2d 251, quoting Thos. J. Dyer Co. v. Bishop Int’l Eng. Co., 303 F.2d 655, 661 (6th Cir.1962). The Court stated that the above passage “is an acceptable amplification of what we have thus far indicated the law of this State is or ought to be.” 251 Md. at 83, 246 A.2d 251. *26 The contract at issue in Atlantic,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

HC&D, LLC v. DCK Pacific Construction, LLC.
529 P.3d 691 (Hawaii Intermediate Court of Appeals, 2023)
Allegis Group, Inc. v. Justin Jordan
951 F.3d 203 (Fourth Circuit, 2020)
Young Elec. Contractors, Inc. v. Dustin Constr., Inc.
185 A.3d 170 (Court of Appeals of Maryland, 2018)
Young Electrical Contractors, Inc. v. Dustin Construction, Inc.
151 A.3d 32 (Court of Special Appeals of Maryland, 2016)
BMD CONTRACTORS v. Fidelity and Deposit Co. of Md.
679 F.3d 643 (Seventh Circuit, 2012)
BMD Contractors, Inc. v. Fidelity & Deposit Co.
828 F. Supp. 2d 978 (S.D. Indiana, 2011)
Fedder Development Corp. v. FB Hagerstown, LLC
181 F. App'x 384 (Fourth Circuit, 2006)
Richard F. Kline, Inc. v. Shook Excavating & Hauling, Inc.
885 A.2d 381 (Court of Special Appeals of Maryland, 2005)
Froelich v. Erickson
96 F. Supp. 2d 507 (D. Maryland, 2000)
Lane Construction Corp. v. Brown & Root, Inc.
29 F. Supp. 2d 707 (E.D. Virginia, 1998)
Urban Masonry Corp. v. N&N Contractors, Inc.
676 A.2d 26 (District of Columbia Court of Appeals, 1996)
West-Fair Electric Contractors v. Aetna Casualty & Surety Co.
661 N.E.2d 967 (New York Court of Appeals, 1995)
W.-FAIR ELEC. v. Aetna Cas.
661 N.E.2d 967 (New York Court of Appeals, 1995)
Galloway Corp. v. S.B. Ballard Construction Co.
464 S.E.2d 349 (Supreme Court of Virginia, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
585 A.2d 248, 86 Md. App. 21, 1991 Md. App. LEXIS 36, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gilbane-building-co-v-brisk-waterproofing-co-mdctspecapp-1991.