W.-FAIR ELEC. v. Aetna Cas.

661 N.E.2d 967, 87 N.Y.2d 148, 638 N.Y.S.2d 394
CourtNew York Court of Appeals
DecidedDecember 7, 1995
StatusPublished

This text of 661 N.E.2d 967 (W.-FAIR ELEC. v. Aetna Cas.) is published on Counsel Stack Legal Research, covering New York Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
W.-FAIR ELEC. v. Aetna Cas., 661 N.E.2d 967, 87 N.Y.2d 148, 638 N.Y.S.2d 394 (N.Y. 1995).

Opinion

87 N.Y.2d 148 (1995)
661 N.E.2d 967
638 N.Y.S.2d 394

West-Fair Electric Contractors et al., Plaintiffs,
v.
Aetna Casualty & Surety Company et al., Defendants.

Court of Appeals of the State of New York.

Argued October 24, 1995
Decided December 7, 1995.

Ernstrom & Dreste, Rochester (J. William Ernstrom and Martha A. Connolly of counsel), for Aetna Casualty and Surety Company, defendant.

Max E. Greenberg, Trager, Toplitz & Herbst, New York City (George N. Toplitz, Kalvin Kamien and Regina C. Saat of counsel), for Gilbane Building Company, defendant.

Welby & Welby, White Plains (Thomas H. Welby and Michael E. Greenblatt of counsel), for L.J. Coppola, Inc., plaintiff.

Bryant, O'Dell & Basso, LLP, Syracuse (Linda E. Alario of counsel), for General Building Contractors of New York State, Inc., and another, amici curiae.

Hendrick, Phillips, Schemm & Salzman, of the Georgia Bar, admitted pro hac vice, and Altieri, Kushner, Miuccio & Frind, P. C., New York City (Denis B. Frind of counsel), for American Subcontractors Association and another, amici curiae.

Chief Judge KAYE and Judges SIMONS, TITONE, BELLACOSA, LEVINE and CIPARICK concur.

*153SMITH, J.

Two questions of law have been certified to us from the Second Circuit Court of Appeals (West-Fair Elec. Contrs. v Aetna Cas. & Sur. Co., 49 F.3d 48):

1. Whether a pay-when-paid provision in a subcontract, which transfers the risk of an owner's default from a general contractor to a subcontractor, violates New York public policy as set forth in the Lien Law; and
2. Whether a surety's liability is contingent on the duty of a contractor to make payment to a subcontractor when the surety bond created an independent obligation to that subcontractor.

We answer the first question in the affirmative and do not reach the second question.

This dispute among the parties arose in connection with a construction project in White Plains, New York. The owner of the construction project entered into a contract with defendant Gilbane Building Company, the general contractor, to build a development known as the Westchester Pavilion. The general contractor entered into various subcontract agreements with subcontractors, including West-Fair Electric Contractors and L.J. Coppola, Inc., to perform specified tasks on the construction project.

The general contractor also obtained a payment bond from defendant Aetna Casualty & Surety Company (Aetna) which named the general contractor as the principal, and the owner of the construction project as the obligee. The payment bond provided that upon the satisfaction of certain conditions (not applicable to the circumstances of this case):

"The above named Principal and Surety [Aetna] hereby jointly and severally agree with the Owner that every [subcontractor] claimant as herein defined who has not been paid in full before the expiration of a period of ninety (90) days after the date on which the last of such claimant's work or *154 labor was done or performed * * * may sue on this bond for the use of such claimant, prosecute the suit to final judgment for such sum or sums as may be justly due claimant, and have execution thereon."

Plaintiff L.J. Coppola, Inc. substantially completed the mechanical and plumbing work specified in its subcontract with the general contractor by October 1993. Although the general contractor paid plaintiff with funds received from the owner through the end of October, the owner subsequently became insolvent and the general contractor did not make any further payments to plaintiff. Plaintiff commenced an action in Federal District Court against Aetna and against the general contractor, seeking the rest of the sums due under the subcontract.[1] Plaintiff's complaint alleged that the general contractor owed a duty to pay under the subcontract and that the general contractor would be unjustly enriched unless plaintiff received the full subcontract price. Plaintiff sued Aetna pursuant to the payment bond.

Defendants moved for summary judgment, arguing that section 3.2 of the subcontract contained a pay-when-paid provision which limited the general contractor's liability to the sums the general contractor received from the owner. Section 3.2 of the subcontract agreement provides in relevant part:

"IT IS SPECIFICALLY UNDERSTOOD AND AGREED THAT THE PAYMENT TO THE TRADE CONTRACTOR [plaintiff] IS DEPENDENT, AS A CONDITION PRECEDENT, UPON THE CONSTRUCTION MANAGER [the general contractor] RECEIVING CONTRACT PAYMENTS, INCLUDING RETAINER FROM THE OWNER".

Defendants claimed that because the owner had not made any further payments to the general contractor, the general contractor had no obligation to pay the subcontractor. Aetna argued that as a surety, its payment obligation under the bond was contingent on the general contractor's liability. Since the general contractor had no obligation to pay plaintiff, Aetna maintained it also owed no obligation to plaintiff under the payment bond.

Plaintiff cross-moved for summary judgment and argued that the pay-when-paid provision merely fixed a time for payment, *155 rather than placing the risk of nonpayment by the owner on the subcontractor. Plaintiff further argued that the payment bond issued by Aetna unconditionally provided for payment to plaintiff after 90 days if the general contractor failed to pay plaintiff within that time.

The District Court granted plaintiff's summary judgment motion and awarded plaintiff the sums due under the subcontract; defendants' summary judgment motions were denied. The District Court reasoned that pay-when-paid provisions indefinitely suspended subcontractors' enforcement rights under the Lien Law because the subcontractor could obtain payment only after the owner paid the general contractor. If the owner failed to pay the general contractor, payment to the subcontractor would never be due and the subcontractor would never be able to enforce its mechanics' lien. The District Court voided the pay-when-paid provision as against the public policy of New York State and held that the provision operated as an improper waiver of plaintiff's right to enforce its mechanics' liens. The court also held Aetna liable under the payment bond because Aetna had assumed a direct obligation to plaintiff by the plain language of the bond.

Defendants appealed to the Second Circuit Court of Appeals which certified the questions before us. We accepted the certified questions for review (85 N.Y.2d 890).

We reject plaintiff's argument that the pay-when-paid provision in section 3.2 of the subcontract merely fixed a time for payment. A contract provision stating that payment will occur upon a stipulated event will be construed as a time for payment provision unless there is express language to the contrary in the contract (Schuler-Haas Elec. Co. v Aetna Cas. & Sur. Co., 40 N.Y.2d 883, 885). In Schuler-Haas, we held that the pay-when-paid provision fixed a time for payment because the document containing the provision lacked express language imposing a condition on the general contractor's legal responsibility to pay.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Architectural Systems, Inc. v. Gilbane Building Co.
760 F. Supp. 79 (D. Maryland, 1991)
Gilbane Building Co. v. Brisk Waterproofing Co.
585 A.2d 248 (Court of Special Appeals of Maryland, 1991)
Schuler-Haas Electric Co. v. Aetna Casualty & Surety Co.
357 N.E.2d 1003 (New York Court of Appeals, 1976)
West-Fair Electric Contractors v. Aetna Casualty & Surety Co.
661 N.E.2d 967 (New York Court of Appeals, 1995)
Schuler-Haas Electric Corp. v. Aetna Casualty & Surety Co.
49 A.D.2d 60 (Appellate Division of the Supreme Court of New York, 1975)
In re Schiavone Construction Co.
181 A.D.2d 580 (Appellate Division of the Supreme Court of New York, 1992)
David Fanarof, Inc. v. Dember Construction Corp.
195 A.D.2d 346 (Appellate Division of the Supreme Court of New York, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
661 N.E.2d 967, 87 N.Y.2d 148, 638 N.Y.S.2d 394, Counsel Stack Legal Research, https://law.counselstack.com/opinion/w-fair-elec-v-aetna-cas-ny-1995.