Architectural Systems, Inc. v. Gilbane Building Co.

760 F. Supp. 79, 1991 U.S. Dist. LEXIS 4074, 1991 WL 43040
CourtDistrict Court, D. Maryland
DecidedMarch 27, 1991
DocketCiv. Y-90-2398
StatusPublished
Cited by11 cases

This text of 760 F. Supp. 79 (Architectural Systems, Inc. v. Gilbane Building Co.) is published on Counsel Stack Legal Research, covering District Court, D. Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Architectural Systems, Inc. v. Gilbane Building Co., 760 F. Supp. 79, 1991 U.S. Dist. LEXIS 4074, 1991 WL 43040 (D. Md. 1991).

Opinion

MEMORANDUM

JOSEPH H. YOUNG, Senior District Judge.

On September 12, 1990, Plaintiff, Architectural Systems, Inc. (“ASI”) filed suit seeking to recover the sum of $348,155.00 remaining unpaid under a subcontract entered into with the contractor, Gilbane Building Company (“Gilbane”), Defendant. On November 2, 1990, Gilbane filed this Motion for Partial Summary Judgment, stating that there were no disputed issues of material fact and that based upon the condition precedent provision in the Gil-bane — ASI Trade Contract, Gilbane is not required to compensate ASI for work accomplished.

Defendant’s motion was held in abeyance pending the Maryland Court of Special Appeals’ decision in Gilbane Building Co. v. Brisk Waterproofing Co., 86 Md.App. 21, 585 A.2d 248 (1991), which considered the condition precedent issue. 1 Resolution of the Defendant’s Motion for Partial Summary Judgment is therefore now appropriate.

In the Spring, 1985, Gilbane entered into an agreement with Carley Capital Group (“the Owner”), whereby Gilbane was to serve as a general contractor on a construction project (“the Project”). The first General Contract provided that Gilbane would receive a fee for its services and would be reimbursed for costs incurred in performing the work. This was later amended to include a provision for the timing of payments that the Owner would make to Gil-bane on a regular basis and to include a provision for the timing of payments that Gilbane would make to its Subcontractors. Furthermore, Gilbane and the Owner agreed that any payment by Gilbane to its Subcontractors would be dependent, as a condition precedent, upon Gilbane first receiving payment from the Owner:

It is specifically understood and agreed that the payment to the subcontractors is dependent, as a condition precedent, upon the contractor receiving contract payments, including retainer from the Owner.

(emphasis in original).

Gilbane subsequently entered into a subcontract with ASI, whereby ASI was to perform drywall and acoustical tile work on the Project. The Gilbane-ASI Trade Contract first provided for the timing of the payments:

MONTHLY AND FINAL PAYMENTS WILL BE MADE TO THE TRADE CONTRACTOR WITHIN FIVE (5) DAYS AFTER RECEIPT OF PAYMENT BY THE CONSTRUCTION MANAGER FROM THE OWNER. THE RETAINED PERCENTAGE WILL BE FORWARDED AS SOON AS RECEIVED BY THE CONSTRUCTION MANAGER FROM THE OWNER.

It then provided a provision similar to that expressed in the Owner-Gilbane contract:

IT IS SPECIFICALLY UNDERSTOOD AND AGREED THAT THE PAYMENT TO THE TRADE CONTRACTOR IS DEPENDENT, AS A CONDITION PRECEDENT, UPON THE CONSTRUCTION MANAGER RECEIVING CONTRACT PAYMENTS, INCLUDING RETAINER FROM THE OWNER. 2

*81 During the course of construction on the Project, the Owner became insolvent and ceased making payments to Gilbane. Gil-bane, in reliance on the condition precedent provision in the Gilbane-ASI Trade Contract, then ceased making payments to ASI. As a result of Gilbane’s failure to compensate ASI, ASI seeks to recover payments under the Trade Contract.

Gilbane concedes that the Trade Contract consists of a pay-when-paid provision and a condition precedent provision, and argues that its motion for partial summary judgment is based upon the latter provision. Although Gilbane acknowledges that in the construction business the general contractor incurs the owner’s credit risk, it maintains that the risk of insolvency was transferred explicitly by the condition precedent in the Trade Contract. See Atl. States Constr. Co. v. Drummond & Co., 251 Md. 77, 82, 246 A.2d 251 (1968), quoting Thos. J. Dyer Co. v. Bishop Int’l Eng’g Co., 303 F.2d 655, 660-61 (6th Cir.1962). ASI argues that it did not assume the credit risk simply by the inclusion of the statement “as a condition precedent” in the Trade Contract, and that the subcontract does not address owner insolvency specifically, as Atl. States compels.

Rule 56 of the Federal Rules of Civil Procedure provides that summary judgment shall be rendered if “the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any, show there is no genuine issue as to any material fact and that the moving party is entitled to judgment as a matter of law.” Fed.R.Civ.P. 56. The party moving for summary judgment has the initial burden of showing there is no genuine issue of fact. Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 256, 106 S.Ct. 2505, 2514, 91 L.Ed.2d 202 (1986). The moving party is entitled to summary judgment “as a matter of law” if the non-moving party fails to make such an affirmative showing. Celotex Corp. v. Catrett, 477 U.S. 317, 324, 106 S.Ct. 2548, 2553, 91 L.Ed.2d 265 (1986).

In Gilbane Building Co. v. Brisk Waterproofing Co., supra, the Court of Special Appeals of Maryland distinguished the provision at issue in Atl. States 3 and the condition precedent provision at issue before it, which is identical to the condition precedent provision before this Court. The Court of Special Appeals held that the language in the contract in Atl. States did not “clearly establish[] a condition precedent, such as the case sub judice.” Id., 86 Md.App. at 26, 585 A.2d 248. It concluded that the subcontract in Brisk contained both a pay-when-paid provision and an unambiguous condition precedent provision. Id. at 27, 585 A.2d 248. After a review of Maryland contract law, it held that since the objective meaning of the terms employed by the parties is pivotal, there can be no question that the payment by the Owner to the general contractor is a condition precedent to Gilbane’s obligation to pay Brisk, regardless of the fact that insolvency was not discussed during contract negotiations. Id. at 26-29, 585 A.2d 248.

ASI urges this Court to disregard the Brisk

Free access — add to your briefcase to read the full text and ask questions with AI

Related

J & K PAINTING CO. v. Bradshaw
45 Cal. App. 4th 1394 (California Court of Appeal, 1996)
Koch v. Construction Technology, Inc.
924 S.W.2d 68 (Tennessee Supreme Court, 1996)
Premier Electrical Construction Co. v. American National Bank
658 N.E.2d 877 (Appellate Court of Illinois, 1995)
West-Fair Electric Contractors v. Aetna Casualty & Surety Co.
661 N.E.2d 967 (New York Court of Appeals, 1995)
W.-FAIR ELEC. v. Aetna Cas.
661 N.E.2d 967 (New York Court of Appeals, 1995)
David Fanarof, Inc. v. Dember Construction Corp.
195 A.D.2d 346 (Appellate Division of the Supreme Court of New York, 1993)
Architectural Systems, Inc. v. Gilbane Building Co.
779 F. Supp. 820 (D. Maryland, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
760 F. Supp. 79, 1991 U.S. Dist. LEXIS 4074, 1991 WL 43040, Counsel Stack Legal Research, https://law.counselstack.com/opinion/architectural-systems-inc-v-gilbane-building-co-mdd-1991.