Architechural Systems, Incorporated, a Maryland Corporation v. Gilbane Building Company, a Rhode Island Corporation

974 F.2d 1330, 1992 U.S. App. LEXIS 29695, 1992 WL 214446
CourtCourt of Appeals for the Fourth Circuit
DecidedSeptember 8, 1992
Docket92-1107
StatusUnpublished

This text of 974 F.2d 1330 (Architechural Systems, Incorporated, a Maryland Corporation v. Gilbane Building Company, a Rhode Island Corporation) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Architechural Systems, Incorporated, a Maryland Corporation v. Gilbane Building Company, a Rhode Island Corporation, 974 F.2d 1330, 1992 U.S. App. LEXIS 29695, 1992 WL 214446 (4th Cir. 1992).

Opinion

974 F.2d 1330

NOTICE: Fourth Circuit I.O.P. 36.6 states that citation of unpublished dispositions is disfavored except for establishing res judicata, estoppel, or the law of the case and requires service of copies of cited unpublished dispositions of the Fourth Circuit.
ARCHITECHURAL SYSTEMS, INCORPORATED, a Maryland corporation,
Plaintiff-Appellant
v.
GILBANE BUILDING COMPANY, a Rhode Island corporation,
Defendant-Appellee.

No. 92-1107.

United States Court of Appeals,
Fourth Circuit.

Argued: June 3, 1992
Decided: September 8, 1992

Peter Wilson Taliaferro, THOMAS & LIBOWITZ, Baltimore, Maryland, for Appellant.

John Francis Morkan, III, OBER, KALER, GRIMES & SHRIVER, Baltimore, Maryland for Appellee.

Michael S. Libowitz, THOMAS & LIBOWITZ, Baltimore, Maryland, for Appellant.

John Anthony Wolfe, OBER, KALER, GRIMES & SHRIVER, Baltimore, Maryland, for Appellee.

Before WIDENER and HAMILTON, Circuit Judges, and STAMP, United States District Judge for the Northern District of West Virginia, sitting by designation.

PER CURIAM:

OPINION

Architectural Systems, Inc. ("ASI") contracted with Gilbane Building Company ("Gilbane") on March 25, 1987, to perform drywall and acoustical tile work on a Baltimore development project for which Gilbane served as the general contractor. During the course of construction, Carley Capital Group ("Carley"), the project owner, experienced financial difficulties, which resulted in delays in payments to Gilbane and its subcontractors, including ASI. In late 1988, Carley became insolvent and ceased payments to Gilbane. Gilbane then halted payments to ASI, relying on a condition precedent in its contract with ASI. Following Gilbane's failure in its efforts to recover the monies owed by Carley, ASI filed suit against Gilbane in the United States District Court for the District of Maryland on September 12, 1990, alleging breach of contract, negligence, negligent misrepresentation, and intentional misrepresentation. The district court granted Gilbane's motion for partial summary judgment as to ASI's breach of contract claim on March 21, 1991, which ruling ASI has not challenged in this appeal. Following discovery, the district court entered summary judgment in favor of Gilbane on ASI's negligence, negligent misrepresentation, and intentional misrepresentation allegations on December 16, 1991. Architectural Sys., Inc. v. Gilbane Bldg. Co., 779 F. Supp. 820 (D. Md. 1991). ASI timely noted this appeal from the district court's December 16, 1991, memorandum opinion. Following a de novo review of the materials before the court, see Felty v. Graves-Humphreys Co., 818 F.2d 1126, 1127 (4th Cir. 1987), viewing all inferences from the underlying facts in the light most favorable to ASI, Celotex Corp. v. Catrett, 477 U.S. 317, 323-24 (1986), we affirm.

I.

In early 1985, Gilbane entered into a cost-reimbursable general contract with Carley to serve as the construction manager and general contractor for the Henderson's Wharf project located in Baltimore City, Maryland. On March 25, 1987, ASI contracted with Gilbane to perform drywall and acoustical work on the project for a total cost of $2,624,000. ASI's payments were subject to a ten percent retainage from the amounts of its monthly requisitions to Gilbane. The trade contract into which Gilbane and ASI entered provided that Gilbane's receipt of payments from Carley was a condition precedent to Gilbane's obligation to pay ASI. ASI commenced work on the project in April 1987.

On September 4, 1987, several months after entering into the trade contract with ASI, Gilbane entered into a lump-sum general contract with Carley that replaced the cost-reimbursable contract. Under the lump-sum contract, valued at $19,188,414, Gilbane was not required to incur any cost prior to being paid by Carley but rather was to be paid in installments consistent with the percentage completion of the project. Gilbane and ASI executed an amendment to the trade contract on November 18, 1987, incorporating the September 4, 1987, agreement between Carley and Gilbane as a contract document to which the trade agreement applied. The contract between ASI and Gilbane remained a retainage contract.

Under the conduit clause of the trade contract, ASI was entitled to the benefit of all rights against Gilbane that Gilbane had against Carley. Gilbane had the right to obtain financial assurances of Carley's ability to fund the project at the time of the execution of the general contracts, and under the conduit clause, ASI was entitled to request assurances from Gilbane at the time of the execution of the trade contract. Prior to entering the lump-sum general contract, Gilbane sought financial assurances from Carley as to its ability to complete the project. Carley provided Gilbane with a letter from its lender on October 14, 1987, stating that the lender's "total commitment is now in excess of Twenty-Nine Million, One Hundred Fifty Thousand Dollars ($29,150,000)"; that "[f]unds will be available based upon approved requisitions to pay contractors and agents in a timely manner"; and that "the additional funds will assure the entire program's completion". Following receipt of the letter, Gilbane executed the lump-sum contract and proceeded with its work.

By the autumn of 1987, ASI had experienced slow payment of several of its monthly requisitions. ASI's president contacted Gilbane's project engineer, asking whether Carley's money problems might prevent ASI from being paid. The project engineer responded that the job was going to finish, that it was not in trouble, and that there was no chance of ASI not being paid. In October 1987, Gilbane's project manager concluded that Carley's financial arrangements were not sufficient to cover the full range of costs on the Henderson's Wharf project, which costs included expenses outside the Gilbane contract. The project manager's conclusions were not communicated to ASI. In February 1988, ASI was again concerned with Carley's ability to finance the project, and ASI's owner asked Gilbane's project executive about Carley's financial condition. Gilbane's project executive informed ASI's president that, in Gilbane's opinion, Carley would be able to complete the project as anticipated.

Completion of the Henderson's Wharf project was scheduled for early June 1988, but as work progressed through the spring of 1988, several of Carley's payments were late. As Gilbane received the payments due it from Carley, Gilbane paid its subcontractors, including ASI. When Carley's payment of Gilbane's May 1988 requisition was delayed beyond the mid-June payment date, Gilbane contacted Carley to inquire of the status of the payment and contacted Carley's lender in an attempt to ascertain whether a problem existed. Still not having received the required payment, Gilbane exercised its rights under the lump-sum contract and notified Carley that it would suspend its work as well as that of its subcontractors unless payment was forthcoming. Gilbane also advised its subcontractors of its action.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ernst & Ernst v. Hochfelder
425 U.S. 185 (Supreme Court, 1976)
Architectural Systems, Inc. v. Gilbane Building Co.
760 F. Supp. 79 (D. Maryland, 1991)
Fegeas v. Sherrill
147 A.2d 223 (Court of Appeals of Maryland, 1978)
Gilbane Building Co. v. Brisk Waterproofing Co.
585 A.2d 248 (Court of Special Appeals of Maryland, 1991)
Jones v. J.H. Hiser Construction Co.
484 A.2d 302 (Court of Special Appeals of Maryland, 1984)
Boatel Industries, Inc. v. Hester
550 A.2d 389 (Court of Special Appeals of Maryland, 1988)
Read Drug & Chemical Co. v. Colwill Construction Co.
243 A.2d 548 (Court of Appeals of Maryland, 1968)
Martens Chevrolet, Inc. v. Seney
439 A.2d 534 (Court of Appeals of Maryland, 1982)
Appel v. Hupfield
84 A.2d 94 (Court of Appeals of Maryland, 2001)
Impala Platinum Ltd. v. Impala Sales (U.S.A.), Inc.
389 A.2d 887 (Court of Appeals of Maryland, 1978)
Patuxent Development Co. v. Ades of Lexington, Inc.
263 A.2d 584 (Court of Appeals of Maryland, 1970)
University Nursing Home, Inc. v. R.B. Brown & Associates, Inc.
506 A.2d 268 (Court of Special Appeals of Maryland, 1986)
Owens-Illinois, Inc. v. Zenobia
601 A.2d 633 (Court of Appeals of Maryland, 1992)
Flow Industries, Inc. v. Fields Construction Co.
683 F. Supp. 527 (D. Maryland, 1988)
Architectural Systems, Inc. v. Gilbane Building Co.
779 F. Supp. 820 (D. Maryland, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
974 F.2d 1330, 1992 U.S. App. LEXIS 29695, 1992 WL 214446, Counsel Stack Legal Research, https://law.counselstack.com/opinion/architechural-systems-incorporated-a-maryland-corp-ca4-1992.