Baltimore County v. Archway Motors, Inc.

370 A.2d 113, 35 Md. App. 158, 1977 Md. App. LEXIS 464
CourtCourt of Special Appeals of Maryland
DecidedMarch 9, 1977
Docket73, September Term, 1976
StatusPublished
Cited by13 cases

This text of 370 A.2d 113 (Baltimore County v. Archway Motors, Inc.) is published on Counsel Stack Legal Research, covering Court of Special Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Baltimore County v. Archway Motors, Inc., 370 A.2d 113, 35 Md. App. 158, 1977 Md. App. LEXIS 464 (Md. Ct. App. 1977).

Opinion

Davidson, J.,

delivered the opinion of the Court.

On 12 May 1975, in the Circuit Court for Baltimore County, the appellant, Baltimore County, Maryland, sued the appellee, Archway Motors, Inc., for money allegedly due either “on accounts stated between them” (count one), or *160 under a contract allegedly breached by Archway (count two). Judge John Grason Turnbull denied Baltimore County’s motion for summary judgment and granted Archway’s motion for summary judgment.

Viewed in the light most favorable to the appellant, 1 the evidence shows that on 29 August 1972, the parties signed a Public Works Agreement in which Archway requested Baltimore County to construct a water main near its property. Section 25 of this agreement provided, in pertinent part:

“Financial Agreements: After bids for the utilities have been received and accepted as satisfactory by the County and the undersigned, the Developer [Archway] will deposit with the County, in cash or certified check, an amount equal to the aggregate cost of the proposed work plus overhead charges as established by the Office of Finance at the time of awarding of contract.” (Emphasis added.)

It also provided that the estimated cost of construction was $6,750.

In a letter dated 15 November 1973, Baltimore County notified Archway that bids had been received and asked Archway to contribute $17,044.72. The letter continued:

“Upon receipt of your certified check in the above amount, payable to Baltimore County, Maryland and receipt of the approved allotment, the subject contract will be awarded.
“You are reminded that contract proposals specify that the award of the contract will be within 60 days of the bid date and any delay in compliance with the requests of this letter could *161 result in the refusal by the low bidding contractor to accept the award.” (Emphasis added.)

In a letter dated 21 December 1973, Archway refused to pay the requested amount and stated:

“I shall do nothing until I hear from you in regard to the extent of any discrepancy in the water deficit computation. ...”

In a letter also dated 21 December 1973, Baltimore County notified Archway that the amount of its contribution had been reduced to $11,547.94. This letter additionally stated:

“Upon receipt of your certified check in the above amount, payable to Baltimore County, Maryland and receipt of the approved allotment, the subject contract will be awarded.” (Emphasis added.)

Moreover, like its predecessor, it stated that the award of the contract would be within 60 days of the bid date and that any delay in compliance could result in the low bidding contractor refusing to accept the bid.

In letters dated 23 September 1974 and 31 October 1974, Baltimore County requested payment of $11,547.94. In a letter dated 18 December 1974, Archway offered to pay $6,750. Notwithstanding the fact that at some unidentified point in time the contract was awarded and the work completed, Archway never paid any amount to Baltimore County.

I

Breach of Contract

In granting Archway’s motion for summary judgment, the trial court determined that § 25 of the parties’ agreement contained a condition precedent which established that Archway would not become obligated to pay until it had accepted the bid. Baltimore County initially contends that § 25 did not create this condition precedent. It maintains that the language of § 25 is ambiguous. Pointing to § 4 of *162 the agreement, in which the words “condition precedent” were expressly stated, it argues that had the parties intended to create a condition precedent in § 25, they would have done so expressly. It maintains that the absence of these words in § 25 indicates that here the parties did not intend to create a condition precedent. 2

The Court of Appeals has established the standard by which to determine whether a provision in a contract constitutes a condition precedent. In Chirichella v. Erwin, 3 that Court said:

“A condition precedent has been defined as ‘a fact, other than mere lapse of time, which, unless excused, must exist or occur before a duty of immediate performance of a promise arises.’ . . . The question whether a stipulation in a contract constitutes a condition precedent is one of construction dependent on the intent of the parties to be gathered from the words they have employed and, in case of ambiguity, after resort to the other permissible aids to interpretation. . . . Although no particular form of words is necessary in order to create an express condition, such words and phrases as ‘if’ and ‘provided that,’ are commonly used to indicate that performance has expressly been made conditional, ... as have the words ‘when,’ ‘after, ’ ‘as soon as,’ or ‘subject to.’ ” (Citations omitted. Emphasis added.)

Here, § 25 expressly states that an amount equal to the construction cost would be deposited after bids were “accepted as satisfactory” by Archway. Notwithstanding the absence of the specific words “condition precedent” in § 25, there is no ambiguity here. The use of the word “after” *163 creates an express condition. Archway was not obligated to pay until it had accepted the bid.

Baltimore County next contends that even assuming the existence of a condition precedent, the trial court erred in granting the motion for summary judgment. It maintains that, despite Archway’s failure to transmit a certified check, it nonetheless accepted the bid. It argues that language in Archway’s letters dated 21 December 1973 and 18 December 1974, including an offer to pay $6,750 as its “fair share,” indicates that Archway knew that a bid had been received by Baltimore County and was concerned, not with the total amount of that bid, but rather with the amount of its contribution. It asserts that it is this evidence which raises an inference that Archway did in fact accept the bid so that the condition precedent was fulfilled. It concludes that, consequently, this evidence creates a genuine dispute as to a material fact.

While the question of whether Archway accepted the bid does involve a material fact, we are not persuaded that the evidence here created a genuine dispute as to that fact. In our view, the evidence does not support an inference that Archway accepted the bid.

Under general principles of contract law, when a method of performance necessary to constitute acceptance of an offer has been prescribed, performance in some other manner does not constitute acceptance. Thus, in Eshelman Co. v. Friedberg, 4 the Court of Appeals said:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
370 A.2d 113, 35 Md. App. 158, 1977 Md. App. LEXIS 464, Counsel Stack Legal Research, https://law.counselstack.com/opinion/baltimore-county-v-archway-motors-inc-mdctspecapp-1977.