DYSER PLUMBING v. Ross Plumbing & Heating
This text of 515 So. 2d 250 (DYSER PLUMBING v. Ross Plumbing & Heating) is published on Counsel Stack Legal Research, covering District Court of Appeal of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
DYSER PLUMBING Company and Insurance Company of North America, Appellants,
v.
ROSS PLUMBING AND HEATING, INC., Appellee.
District Court of Appeal of Florida, Second District.
*251 Stevan T. Northcutt, of Levine, Hirsch, Segall, Northcutt & Hanlon, P.A., Tampa, for appellants.
Raymond C. Conklin, of Stolba, Englander, Conklin, Brainard, DiSano & Verona, P.A., St. Petersburg, for appellee.
RYDER, Judge.
This dispute arose from the parties' involvement in constructing an addition to St. Anthony's Hospital in Pinellas County. Appellant Dyser Plumbing was engaged by the owner to install the plumbing, medical gas and fire protection systems in the addition. Dyser subcontracted with three companies: appellee Ross Plumbing, Hobgood Air Conditioning and Brown Automatic Sprinklers. Appellant INA was the surety on Dyser's performance and payment bonds.
The project experienced substantial delays. When the project was five months behind, Dyser requested delay damage estimates from its subcontractors. When the project became eleven months behind, Dyser mathematically projected everyone's five-month delay estimates to eleven months and submitted the total to the owner. The $1,136,799.00 claim included estimated eleven-month delay damages for Dyser and all three subcontractors. The amount submitted as Ross' delay damages estimate was $108,130.00. After some negotiations with the owner, Dyser and the owner agreed to a settlement of the delay damages claim of $175,000.00. The amount was not allocated by the owner.
Dyser and the other two subcontractors agreed on an amount to settle their delay damages, Dyser paid them the agreed-upon sum, and those subcontractors signed a release. Ross and Dyser attempted to negotiate a settlement, but could not come to an agreement.
Ross then sued Dyser and INA for breach of contract and requested delay damages, the balance of the payments held as retainage and attorney's fees and costs. Dyser's answer included affirmative defenses which admitted a retainage was owed to Ross, but that the retainage was not, in fact, due and payable because the retainage had not been received by Dyser from the owner. The answer also included a counterclaim for defective and/or improperly performed work.
A bench trial was held in which the trial court limited the evidence of the settlement negotiations between Dyser and Ross. The trial court limited the evidence relating to negotiations because it decided no settlement had been reached. Dyser argued unsuccessfully that a settlement between Dyser and Ross had been reached, so evidence of it was admissible. In its final judgment, the trial court found that the delays were not caused by either party and that both parties had suffered delay damages. It also found that some of Ross' work was performed incorrectly and the cost of conforming the work $17,600.00 would be a set-off against Ross' recovery. The trial court found "the delay damages submitted by Ross were accurate and that the delay claim itself was legitimate," and that Dyser had negotiated a settlement of the delay damages claim with the owner "without first having negotiated a settlement agreement with Ross and without first being authorized to settle for Ross." It then found that "the retainage monies of $49,197.00 have been, and are due." The *252 trial court's order awarded Ross its total delay damage claim of $108,130.00 minus the $17,600.00 set-off, plus the retainage of $49,197.00, for a total of $139,727.00. It ordered prejudgment interest from March 25, 1985. A subsequent order awarded to Ross costs and attorney's fees. This appeal is from those orders.
Dyser raises three points on appeal. The first point contains three subparts. We address the points seriatim. The first point argues that the evidence is insufficient to support a judgment in Ross' favor as to (a) a breach of contract, (b) the amount of delay damages, and (c) prejudgment interest. Ross claimed at trial that Dyser breached the contract in not paying to Ross its retainage when a reasonable time had passed after completion of the project. Ross argued that the owner's payment is not a condition precedent to the contractor's obligation to pay a subcontractor, citing Peacock Construction Co., Inc. v. Modern Air Conditioning, Inc., 339 So.2d 294, 295 (Fla. 2d DCA 1976) [Peacock I]. Dyser argued that payment of the retainage by the owner was an express contractual condition precedent to Dyser's obligation to pay Ross' retainage. Paragraph 5.(e) of the contract between Dyser and Ross provides:
Final payment, inclusive of retention, shall be made within thirty days of completion of the construction project, acceptance of the same by the Owner, and as a condition precedent, receipt of final payment of Dyser Plumbing and Mechanical from the Owner or Prime Contractor, as the case may be.
The supreme court, in affirming Peacock I, stated:
Our decision to require judicial interpretation of ambiguous provisions for final payment in subcontracts in favor of subcontractors should not be regarded as anti-general contractor. It is simply a recognition that this is the fairest way to deal with the problem. There is nothing in this opinion, however, to prevent parties to these contracts from shifting the risk of payment failure by the owner to the subcontractor. But in order to make such a shift the contract must unambiguously express that intention. And the burden of clear expression is on the general contractor.
Peacock Construction Co., Inc. v. Modern Air Conditioning, Inc., 353 So.2d 840, 842-43 (Fla. 1977). In reading the contract clause above, it is hard to imagine a more clear expression of an intent to shift the risk of payment failure by the owner to the subcontractor.
The owner's final payment to Dyser was a condition precedent to Dyser's obligation to pay Ross' retainage. The evidence at trial was insufficient to prove the condition precedent had been met. Dyser claims that at the time of trial, Dyser had yet to be paid by the owner. The record does not indicate whether Dyser has, in fact, been paid by the owner. We reverse and remand the case with the following instructions. If the trial court determines that Dyser has been paid the final payment by the owner, the trial court can leave the retainage award undisturbed. If the trial court determines that Dyser has yet to be paid the final payment by the owner, the retainage award must be vacated and set aside.
The second subpart of Dyser's first point on appeal challenges the sufficiency of the evidence in support of the delay damages award. Paragraph 4.(b) of the contract provides, in pertinent part:
Should the Subcontractor's performance of this subcontract be delayed by any acts of Dyser Plumbing and Mechanical, its subcontractors or suppliers, or delayed by any acts or causes which entitle Dyser Plumbing and Mechanical to an extension of time under the Agreement, the Subcontractor shall receive an equitable extension of time for the performance of this subcontract (not to exceed that received by Dyser Plumbing and Mechanical from the Owner or Prime Contractor, as the case may be), but shall not be entitled to any increase in the subcontract price or to damages or additional compensation as a consequence of such delays, unless the Owner is liable and pays for such delays. Dyser *253
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
515 So. 2d 250, 12 Fla. L. Weekly 2153, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dyser-plumbing-v-ross-plumbing-heating-fladistctapp-1987.