Urban Masonry Corp. v. N&N Contractors, Inc.

676 A.2d 26, 1996 D.C. App. LEXIS 85, 1996 WL 264689
CourtDistrict of Columbia Court of Appeals
DecidedMay 16, 1996
Docket94-CV-283
StatusPublished
Cited by21 cases

This text of 676 A.2d 26 (Urban Masonry Corp. v. N&N Contractors, Inc.) is published on Counsel Stack Legal Research, covering District of Columbia Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Urban Masonry Corp. v. N&N Contractors, Inc., 676 A.2d 26, 1996 D.C. App. LEXIS 85, 1996 WL 264689 (D.C. 1996).

Opinions

KING, Associate Judge:

This appeal stems from a breach of contract claim brought by N & N Contractors, Inc., (“N & N”) against Urban Masonry Corporation (“Urban”). Urban was a subcontractor on a major construction project in the District of Columbia (the “District”) and N & N was a subcontractor of Urban. In its complaint, N&N alleged that it had performed all “conditions precedent for payment” under the contract and that, despite repeated requests for payment, Urban breached the contract by refusing to pay N & N. N & N sought compensation for: (1) installing sixty-eight precast concrete panels which N&N contended were in excess of the number of panels called for by the subcontract; (2) experiencing delays and disruptions completing the project that were caused by the material supplier’s failure to timely supply the panels; and (3) attorneys’ fees and interest pursuant to the subcontract. The trial court granted N & N’s motion for partial summary judgment on the compensation issue relating to the sixty-eight panels, and, following an evidentiary hearing, awarded N&N damages and attorneys’ fees associated with that issue. The breach of [28]*28contract claim relating to the delays and disruptions issue, and attorneys’ fees associated with that issue, were tried to a jury which returned a verdict awarding N & N damages, attorneys’ fees, and interest. In this appeal, Urban challenges the partial summary judgment ruling, the jury verdict, and the damage awards. We affirm in all respects but remand the award of attorneys’ fees made by the jury for further proceedings.

I.

A. Background

The Blake Construction Company (“Blake”), the general contractor for construction of the Portals Office Building in the District (the “project”), subcontracted with Bogert Precast, Inc. (“Bogert”) for the manufacture and delivery to the project of the precast concrete panels, and with Urban, for the construction of all masonry, including installation of the precast concrete panels. On November 27, 1990, Urban subcontracted with N & N to install 297 pieces of welded precast concrete for the project. The Urban/N & N subcontract provided that in the event of a dispute arising out of the subcontract, the prevailing party was entitled to an award of attorneys’ fees;1 however, Article 1(f)2 of the same subcontract attached and incorporated the Blake/Urban contract, including specifically Articles 283 and 29.4 Those articles provide that each party should bear its own attorneys’ fees and costs incurred in the resolution of any dispute between the parties.

B. N & N’s Breach of Contract Claim

After N & N began installing the panels it became obvious, apparently because the pan[29]*29els were smaller than the size specified in the plans, that additional precast concrete panels would be required to complete the project. Concluding that installation of the additional pieces was beyond the scope of the Urban/N & N subcontract, N&N requested, and received, both Urban’s permission to proceed with the project, and Urban’s promise of additional compensation for installing the sixty-eight additional pieces.5 N&N ultimately installed the sixty-eight precast pieces, but Urban declined to pay N & N for the additional work. N&N brought this action to recover, inter alia, the cost of installation of the additional pieces. The trial court granted N & N’s motion for partial summary judgment on the issue of Urban’s liability for payment for installation of the extra sixty-eight concrete panels. At a subsequent evi-dentiary hearing, the trial court awarded damages in the amount of $17,000 and attorneys’ fees in the amount of $4,550 on this aspect of the claim.

N&N also sued to recover damages incurred by it due to delays and disruption caused by Bogert’s failure to supply the material to be installed. Specifically the complaint alleges N&N experienced a loss in productivity and accumulated additional costs associated with Bogert’s failure to: (1) supply the precast panels or steel connections for installing those panels in the predetermined sequence; and (2) install the “control lines” which had to be in place before N&N could erect the panels. N&N documented its resulting loss of productivity on a “Lost Time Log” and submitted its costs to Urban, consistent with paragraph 1(f) of the subcontract. The jury awarded N&N $36,500 in [30]*30damages and $25,000 in attorneys’ fees on this claim.6

II.

Scope of Review

Summary judgment is proper if, accepting the allegations of the complaint as true, and construing all the facts and inferences in favor of the nonmoving party, the record shows there is no genuine issue of material fact, and the movant is entitled to judgment as a matter of law. Nader v. de Toledano, 408 A.2d 31, 41 (D.C.1979), cert. denied, 444 U.S. 1078, 100 S.Ct. 1028, 62 L.Ed.2d 761 (1980); Super. Ct. Civ. R. 56(c) (1995). On appeal, we review de novo, determining whether the trial court properly concluded there was no genuine issue of material fact and that the movant is entitled to judgment as a matter of law. Northbrook Ins. Co. v. United Servs. Auto. Ass’n, 626 A.2d 915, 917 (D.C.1993). We will affirm the trial court if we find that the “pleadings, depositions, answers to interrogatories, and admissions on file together with the affidavits,” if any ... support that conclusion. Byrd v. Allstate Ins. Co., 622 A.2d 691, 693 (D.C.1993) (quoting Super. Ct. Civ. R. 56(e)).

III.

DISCUSSION

A. The Grant of Partial Summary Judgment

Urban contends that summary judgment on the claim seeking compensation to install the sixty-eight additional panels was improper because the parties had differing interpretations of the clause defining the scope of N & N’s work, and there are genuine issues of material fact with regard to N & N’s entitlement to compensation for installing the sixty-eight additional precast pieces. The subcontract term at issue provides:

Subcontractor agrees to supply all necessary equipment (except site tower crane), tools and labor required to install the precast concrete (297 pieces) * for this project in accordance with Contract Documents between Owner and General Contractor (“Blake”) including but not limited to Specification Sections 3450 and 3405 (the “Contract Documents”) and approved shop drawings and the terms and conditions set forth below:
* All pieces requiring welded connections Approx. 297(+/ — ).
ALL FOR THE SUM OF $84,600.00 (EIGHTY-FOUR THOUSAND SIX HUNDRED DOLLARS)7

Urban, maintaining that the term “Approx. 297(+/-)” means N & N would install all of the precast pieces requiring welded connections, without regard to the actual number of pieces required, contends that N & N’s contrary interpretation demonstrates that the provision is ambiguous, requiring extrinsic [31]*31evidence to resolve, and therefore, summary judgment does not lie.8

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re Estate of Drake
4 A.3d 450 (District of Columbia Court of Appeals, 2010)
Quinn Construction, Inc. v. Skanska USA Building, Inc.
730 F. Supp. 2d 401 (E.D. Pennsylvania, 2010)
Mixon v. Washington Metropolitan Area Transit Authority
959 A.2d 55 (District of Columbia Court of Appeals, 2008)
Estate of Raleigh v. Mitchell
947 A.2d 464 (District of Columbia Court of Appeals, 2008)
Wallasey Tenants Ass'n, Inc. v. Varner
892 A.2d 1135 (District of Columbia Court of Appeals, 2006)
Hill v. G.E. Capital Mortgage Services, Inc.
859 A.2d 1055 (District of Columbia Court of Appeals, 2004)
Futrell v. Department of Labor Federal Credit Union
816 A.2d 793 (District of Columbia Court of Appeals, 2003)
Angulo v. Gochnauer
772 A.2d 830 (District of Columbia Court of Appeals, 2001)
In Re Estate of King
769 A.2d 771 (District of Columbia Court of Appeals, 2001)
Connelly v. Swick & Shapiro, P.C.
749 A.2d 1264 (District of Columbia Court of Appeals, 2000)
Manuel v. District of Columbia
726 A.2d 687 (District of Columbia Court of Appeals, 1999)
Concord Enterprises, Inc. v. Binder
710 A.2d 219 (District of Columbia Court of Appeals, 1998)
Derzavis v. Security Storage Co. of Wash.
703 A.2d 839 (District of Columbia Court of Appeals, 1997)
Federal Deposit Insurance v. Bender
127 F.3d 58 (D.C. Circuit, 1997)
Rockler v. Sevareid
691 A.2d 97 (District of Columbia Court of Appeals, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
676 A.2d 26, 1996 D.C. App. LEXIS 85, 1996 WL 264689, Counsel Stack Legal Research, https://law.counselstack.com/opinion/urban-masonry-corp-v-nn-contractors-inc-dc-1996.