Paul Morrell, Incorporated v. Kellogg Brown & Root Services

453 F. App'x 322
CourtCourt of Appeals for the Fourth Circuit
DecidedNovember 10, 2011
Docket10-1253
StatusUnpublished

This text of 453 F. App'x 322 (Paul Morrell, Incorporated v. Kellogg Brown & Root Services) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Paul Morrell, Incorporated v. Kellogg Brown & Root Services, 453 F. App'x 322 (4th Cir. 2011).

Opinion

Affirmed by unpublished PER CURIAM opinion.

Unpublished opinions are not binding precedent in this circuit.

PER CURIAM:

Plaintiff/Appellee Paul Morrell, Incorporated, d/b/a The Event Source (“TES”) brought suit in the United States District Court for the Eastern District of Virginia against Defendants/Appellants Kellogg Brown & Root Services, Incorporated and several related entities (“KBR”), alleging various common law claims. Prior to trial, a number of the claims were either dismissed or resolved between the parties. After a multi-week bench trial on the remaining claims, the district court ruled against TES on its claims for breach of contract and tortious interference, 1 but in favor of TES on its claim for fraudulent inducement, setting forth detailed findings of fact and conclusions of law in a 47-page written opinion. The court awarded approximately $12.4 million in fraud damages, slightly more than $2.5 million in prejudgment interest, and $4 million in punitive damages.

On appeal, KBR challenges the district court’s judgment on the fraud claim, as well as the award of both compensatory and punitive damages. For the reasons set forth herein, we affirm the judgment of the district court.

I.

This case arises out of a contract and subsequent settlement agreement between KBR and TES. The district court determined that KBR made material false statements in order to induce TES to accept a settlement payment that was approximately $12.4 million less than what KBR had previously acknowledged it owed TES.

*324 The initial contract between KBR and TES was part of the effort to provide dining facilities and food services (“DFAC services”) to American troops in Iraq. That effort began in December 2001, when KBR contracted with the federal government to provide logistical support, including DFAC services, to our armed forces in Iraq. On June 13, 2003, actual work authorization was awarded to KBR through Task Order 59, and KBR selected TES as a sub-contractor to provide certain of those services. TES and KBR entered into a Master Agreement on June 15, 2003, which contained a number of incorporated contractual documents. TES, in turn, hired a number of sub-contractors to perform various aspects of the required work, setting up separate payment arrangements with each of them. The time of performance under Task Order 59 was modified periodically and additional funding was provided as the need for DFAC services in Iraq continued.

Toward the end of 2003, KBR came under scrutiny from the Defense Contract Audit Agency (“DCAA”), which was investigating the DFAC invoices KBR submitted for payment from its subcontractors. One of DCAA’s primary concerns was that some DFAC invoices, including those from TES, billed for more meals than were actually served to the troops. In early 2004, DCAA began reviewing its payment of invoices to KBR, and informed KBR that, pending further discussions, DCAA would withhold payment on a portion of the invoices. 2 DCAA also instructed KBR to review all of its DFAC subcontracts.

KBR conducted the review of its subcontracts, and informed DCAA that its review confirmed that its subcontracts were reasonably priced and structured, and that outstanding invoices should be paid in full. KBR thus told DCAA that it intended to pay outstanding invoices to its subcontractors in full and bill those amounts to the government.

In response to KBR’s stated intention, DCAA announced in May 2004 that it would begin to withhold and/or recoup 19.35% of the total payments made by the government to KBR for DFAC invoices because of the discrepancy between the actual number of meals served and the invoiced meal amounts. This “decrement” caused KBR, in turn, to withhold money from its subcontractors. Additionally, in response to the imposition of the decrement, KBR and TES executed Amendment No. 1 to the Master Agreement, which reflected their agreement as to the proper method to calculate the amount due and payable to TES, later agreed by them to be $36,464,644.65. Amendment No. 1 also extended the time for TES to file contract dispute claims with KBR.

In early 2005, KBR met with the Army Sustainment Command (“ASC”), to discuss the government’s continued concerns regarding the alleged overbilling, and they engaged in extensive renegotiations over the DFAC billing and invoices. ASC and KBR finally reached a negotiated settlement (“the KBR-ASC Settlement”), in *325 which KBR agreed to a $55 million decrement from the invoice amounts it had submitted from its DFAC subcontractors and released the government from all claims relating to the DFAC invoices. As a result, KBR no longer had the ability to assert claims on behalf of its subcontractors for any additional payment for DFAC services, and the sole remedy for TES and other subcontractors was against KBR. KBR did not consult with TES or its other sub-contractors regarding the KBRASC Settlement, nor did it disclose any of the settlement details to TES. In any event, TES never authorized KBR to waive any of TES’ rights vis a vis the government under its subcontract with KBR.

Following the KBR-ASC Settlement, KBR scheduled meetings in Dubai with TES and other subcontractors in order to resolve their outstanding invoices which had been subject to the decrement. During the Dubai meetings, KBR convinced TES to accept a reduced payment from KBR on its invoiced amounts (approximately $24 million, instead of the $36.4 million agreed to in Amendment No. 1) and to release KBR from any additional claim for payment.

TES’ fraud claim was based on the representations made by KBR before and during the Dubai meetings. The dispute over the fraud claim at trial focused primarily on whether the Dubai representations by KBR were knowingly false, and whether TES justifiably relied on those representations when it accepted the reduced payment from KBR and released it from further claims.

The district court found that KBR officials made numerous fraudulent statements to TES in order to induce TES to agree to the reduced payment and the release. These misrepresentations by KBR included: (1) the characterization of the amount KBR was going to pay TES as a “Government decision,” that was “calculated by the Government based on a number of factors, primarily including actual headcount and the period of performance”; (2) “that KBR has no ability to increase or decrease the KBR Holdback,” defined as “that portion of the amount billed for the Invoiced Work that will not be paid to TES as determined by the Government”; (3) that KBR had no discretion to raise or lower the amount offered, which was therefore “nonnegotiable”; and (4) if TES rejected the KBR offer, “TES’ only legal remedy was to contest the government’s decision by filing a claim, through KBR, against the government.” (See J.A. 2379-82.)

Many of KBR’s fraudulent statements were made orally, but some were incorporated into a written document, Amendment No. 2 to the Master Agreement. Significantly, the district court expressly found that TES asked KBR to sign Amendment No. 2 in order to verify that KBR was being truthful about its representations.

The district court further found that, had KBR not executed Amendment No.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re: The Wallace & Gale Company, Debtor. Roy E. Jones Andrew R. Youngbar Louise Holcomb, Personal Representative of the Estate of Cossie Holcomb Robert M. Barber, Personal Representative of the Estate of Milton Barber, Intervenors-Plaintiffs-Appellants v. Liberty Mutual Insurance Company Hartford Insurance Company Continental Casualty Company Adriatic Insurance Company St. Paul Fire & Marine Insurance Company Granite State Insurance Company New Hampshire Insurance Company Travelers Casualty and Surety Company, and the Wallace & Gale Company Mayor of Baltimore City Council of Baltimore City American Employers Insurance Company International Insurance Company, the Aetna Casualty and Surety Company, Intervenor-Defendant. Porter Hayden Company Official Committee of Unsecured Creditors of Porter Hayden Official Committee of Unsecured Creditors of Acands, Incorporated Acands, Incorporated Jt Thorpe Company Celotex Asbestos Settlement Trust, Amici Supporting Complex Insurance Claims Litigation Association the American Insurance Association Certain Underwriters at Lloyd's, London, Amici Supporting in Re: The Wallace & Gale Company, Debtor. Roy E. Jones Andrew R. Youngbar Louise Holcomb, Personal Representative of the Estate of Cossie Holcomb Robert M. Barber, Personal Representative of the Estate of Milton Barber, Intervenors-Plaintiffs v. Travelers Casualty and Surety Company v. Liberty Mutual Insurance Company, and the Wallace & Gale Company Mayor of Baltimore City Council of Baltimore City Hartford Insurance Company Cna-Continental Casualty Company Adriatic Insurance Company St. Paul Fire & Marine Insurance Company American Employers Insurance Company International Insurance Company Granite State Insurance Company New Hampshire Insurance Company, the Aetna Casualty and Surety Company, Intervenor-Defendant
385 F.3d 820 (Fourth Circuit, 2004)
Grant Thornton LLP v. Prospect High Income Fund
314 S.W.3d 913 (Texas Supreme Court, 2010)
1001 McKinney Ltd. v. Credit Suisse First Boston Mortgage Capital
192 S.W.3d 20 (Court of Appeals of Texas, 2006)
Gulf Const. Co., Inc. v. Self
676 S.W.2d 624 (Court of Appeals of Texas, 1984)
Heritage Life Insurance Co. v. Heritage Group Holding Corp.
751 S.W.2d 229 (Court of Appeals of Texas, 1988)
Ernst & Young, L.L.P. v. Pacific Mutual Life Insurance Co.
51 S.W.3d 573 (Texas Supreme Court, 2001)
Prospect High Income Fund v. Grant Thornton, LLP
203 S.W.3d 602 (Court of Appeals of Texas, 2006)
Urban Masonry Corp. v. N&N Contractors, Inc.
676 A.2d 26 (District of Columbia Court of Appeals, 1996)
Foley v. Parlier
68 S.W.3d 870 (Court of Appeals of Texas, 2002)
Clear Lake City Water Authority v. Friendswood Development Co.
344 S.W.3d 514 (Court of Appeals of Texas, 2011)
Sanderson v. Sanderson
109 S.W.2d 744 (Texas Supreme Court, 1937)

Cite This Page — Counsel Stack

Bluebook (online)
453 F. App'x 322, Counsel Stack Legal Research, https://law.counselstack.com/opinion/paul-morrell-incorporated-v-kellogg-brown-root-services-ca4-2011.