Trinity Universal Insurance Company v. Clyde H. Smithwick

222 F.2d 16
CourtCourt of Appeals for the Eighth Circuit
DecidedMay 26, 1955
Docket15199
StatusPublished
Cited by25 cases

This text of 222 F.2d 16 (Trinity Universal Insurance Company v. Clyde H. Smithwick) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Trinity Universal Insurance Company v. Clyde H. Smithwick, 222 F.2d 16 (8th Cir. 1955).

Opinion

COLLET, Circuit Judge.

Clyde H. Smithwick a sub-contractor of Lancaster and Love, Inc., recovered a judgment for the balance due on his contract with Lancaster and Love against the defendant Trinity Universal Insurance Co., a Texas corporation, which had executed a bond insuring subcontractors the amount due them from Lancaster and Love. - Trinity appeals. The assignments of error require a rather detailed statement of the facts.

On April 16, 1951 the City of Pine Bluff, Arkansas and Lancaster and Love executed a general contract by which the latter as the prime contractor agreed for the price of $1,527,071.81 to construct certain sewer improvements in the City of Pine Bluff. The prime contractor had the right under the contract to sublet the work. It did sublet to plaintiff the construction of six pump stations for the aggregate sum of $174,729.00 by six separate subcontracts. The subcontracts provided that the stations should be completed within 180 days from the time work was begun. Work was to begin within 10 days from the date the prime contractor issued a work order to plaintiff. The work order was issued June'l, 1951.

The subcontracts further provided that in the event the work was not completed within 180 days the plaintiff was-to pay the prime contractor the sum of $50.00 for each day required in excess of 180, “provided however, (if) materials (were) not available, the liquidated sum enumerated herein shall be waived.”

It was further provided that the plaintiff should not be liable for any liquidated damages caused by reason of the delay of the prime contractor.

The defendant executed its bond April 16, 1951 insuring the performance of the general contract by the prime contractor. Defendant’s bond inured to the benefit of plaintiff as a subcontractor insuring to plaintiff the payment of all sums due him from Lancaster and Love, the prime contractors.

When Lancaster and Love proffered the completed job to the City a controversy arose between them concerning the work and it was not accepted by the City. Lancaster and Love brought suit in the United States District Court for the Eastern District of Arkansas against the City for the contract price. The City brought Trinity into the case. Both Lancaster and Love and Trinity by their pleadings in that case asserted comple *19 tion of the entire contract, including plaintiff’s subcontracted portion of the work in accordance with the terms of the general contract. That suit was filed November 7, 1952, and according to the briefs was referred to a special master before whom it is still pending.

Plaintiff filed the present action on August 4, 1953 against Trinity and the City in the Arkansas State Court. The complaint alleged the execution of the general contract between the City and Lancaster and Love, the execution of the bond by Trinity, and _the execution and performance of the six subcontracts by plaintiff. It was alleged in paragraph 8 that—

“8. The work which plaintiff agreed to construct under the terms of said contracts dated April 30, 1951, has been fully completed and has been accepted by the City of Pine Bluff and is now being used by said City of Pine Bluff.”

The complaint further alleged that the original contract price had been increased $599.51 to a total of $175,328.51, that $154,427.33 had been paid and certain work of the value of $367.50 omitted, leaving a balance due plaintiff of $20,-533.61 for which it prayed judgment against Trinity and the City. Trinity’s “Contractor’s Surety Bond” and plaintiff’s six subcontracts were attached to the complaint as exhibits and made a part of the complaint. The cause was removed to the United States District Court for the Eastern District of Arkansas. The defendant Trinity answered asserting in general terms that the complaint failed to state “a claim against this defendant upon which relief can be granted,” alleged that Lancaster and Love was a necessary and indispensable party, admitted the execution of the general contract, the execution of Trinity’s bond, and the execution of plaintiff’s six subcontracts. Referring to paragraph 8 of the complaint (quoted above) Trinity’s answer stated:

“This defendant admits the allegations of paragraph 8 of said petition except the allegation that the work ‘has been accepted by the City of Pine Bluff,’ and in this (fol. 13) connection says that while it believes as a matter of law that such work has been accepted by the City of Pine Bluff, there is presently pending litigation in cause No. 2481, hereinafter more fully set out, wherein the City of Pine Bluff denies that it has accepted the work of the plaintiff herein.”

Paragraph 9 of the Complaint contained the allegations above referred to of the amount of plaintiff’s contract price, the payments and credit and the amount due plaintiff. Answering that paragraph Trinity stated that it admitted those allegations except the allegation that “the sum claimed is now due.” In that connection Trinity alleged:

“that under the plaintiff’s contracts the balance owing is not due until such time as the entire sewer system of the City of Pine Bluff has been accepted by the owner (the City) and the owner (City) has paid the retained percentages to the prime contractor, Lancaster and Love, Inc., at which time the sum owing by Lancaster & Love, Inc., to plaintiff will become due.”

Trinity further admitted that the City had received the benefit of the work performed by plaintiff, admitted that the reasonable value to the City of plaintiff’s work was as plaintiff alleged, and admitted a balance owing to plaintiff of $20,533.68. The answer then asserted that the action was prematurely brought in that Lancaster and Love were not obligated to pay plaintiff until it had been paid by the City, that since the City and Lancaster and Love were involved in litigation there was no obligation on the part of Lancaster and Love or Trinity to pay plaintiff until such time as plaintiff’s work had been “accepted and paid for by the City.”

Trinity then alleged that the City was in the other case claiming liquidated damages from Lancaster and Love under *20 the general contract — “and in the event they (the City) are successful in that cause, the claim of plaintiff herein will be entitled to be off-set for liquidated damages in an amount then to be determined.” The prayer of the answer was that the cause be abated “until all necessary parties are before the court” and until the determination of the litigation between the City and Lancaster and Love, or that this cause be consolidated with the other action.

After Trinity’s answer was filed the cause was remanded to the State Court upon the motion of the City. Upon becoming reinvested with jurisdiction of the cause the State Court on motion of the plaintiff, Smithwick, struck from Trinity’s answer the allegation that Lancaster and Love was an indispensable and necessary party to the action; the allegation that under plaintiff’s subcontracts the balance of $20,533.68 owing to him was not due until such time as the entire sewer system had been accepted by the City and the City had paid Lancaster and Love; and the denial by Trinity of any contractual obligation to plaintiff under Trinity’s bond.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Capitol Steel Fabricators, Inc. v. Mega Constr. Co.
58 Cal. App. 4th 1049 (California Court of Appeal, 1997)
Koch v. Construction Technology, Inc.
924 S.W.2d 68 (Tennessee Supreme Court, 1996)
JONES EXCAVAT. CONTRACTOR v. Firemen's Ins.
920 S.W.2d 483 (Supreme Court of Arkansas, 1996)
Colonial Mechanical Corp. v. Jesson & Frantz Contractors & Developers, Inc.
22 Va. Cir. 304 (Richmond County Circuit Court, 1990)
Mrozik Construction, Inc. v. Lovering Associates, Inc.
461 N.W.2d 49 (Court of Appeals of Minnesota, 1990)
A. A. Conte, Inc. v. Campbell-Lowrie-Lautermilch Corp.
477 N.E.2d 30 (Appellate Court of Illinois, 1985)
Ray Ross Construction Co. v. Raney
587 S.W.2d 46 (Supreme Court of Arkansas, 1979)
Dairy Farm Leasing Co., Inc. v. Hartley
395 A.2d 1135 (Supreme Judicial Court of Maine, 1978)
Peacock Const. Co., Inc. v. Modern Air Conditioning, Inc.
353 So. 2d 840 (Supreme Court of Florida, 1977)
Vern Barnett Construction Co. v. J. A. Hadley Construction Co.
496 S.W.2d 446 (Supreme Court of Arkansas, 1973)
National Surety Corp. v. Ideal Lumber Co.
460 S.W.2d 55 (Supreme Court of Arkansas, 1970)
A. J. Wolfe Co. v. Baltimore Contractors, Inc.
244 N.E.2d 717 (Massachusetts Supreme Judicial Court, 1969)
United States ex rel. Peevy v. Pensacola Construction Co.
257 F. Supp. 131 (W.D. Arkansas, 1966)
Universal Security Ins. v. Zambie
396 S.W.2d 842 (Supreme Court of Arkansas, 1965)
Fort Smith Structural Steel Co. v. Western Surety Co.
247 F. Supp. 674 (W.D. Arkansas, 1965)
Reid v. Miles Construction Corporation
307 F.2d 214 (Eighth Circuit, 1962)
Reid v. Miles Construction Corp.
307 F.2d 214 (Eighth Circuit, 1962)

Cite This Page — Counsel Stack

Bluebook (online)
222 F.2d 16, Counsel Stack Legal Research, https://law.counselstack.com/opinion/trinity-universal-insurance-company-v-clyde-h-smithwick-ca8-1955.