Colonial Mechanical Corp. v. Jesson & Frantz Contractors & Developers, Inc.

22 Va. Cir. 304, 1990 Va. Cir. LEXIS 371
CourtRichmond County Circuit Court
DecidedDecember 14, 1990
DocketCase No. LS-2979-2
StatusPublished

This text of 22 Va. Cir. 304 (Colonial Mechanical Corp. v. Jesson & Frantz Contractors & Developers, Inc.) is published on Counsel Stack Legal Research, covering Richmond County Circuit Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Colonial Mechanical Corp. v. Jesson & Frantz Contractors & Developers, Inc., 22 Va. Cir. 304, 1990 Va. Cir. LEXIS 371 (Va. Super. Ct. 1990).

Opinion

By JUDGE RANDALL G. JOHNSON

At issue in this case, which is before the court on plaintiff’s motion for summary judgment, is the proper interpretation of a payment provision in a contract between a general contractor and subcontractor. The provision, which is contained in Article VI of the contract, provides:

The Contractor shall make final payment to the Subcontractor within ten days of receipt of final payment from the owner.

The question now before the court is whether that provision creates a condition precedent for payment to the subcontractor or simply establishes a reasonable time for such payment. Stated differently, the question is whether the general contractor is excused from paying the subcontractor if payment is never received from the owner.

The parties agree that the subcontractor has performed all of its duties under the contract and that the value of those services for which he has not been paid is as set out in the motion for judgment. They also agree that the precise issue before the court is one which has never [305]*305been addressed by our Supreme Court and that the majority view of other states is that such a provision does not create a condition precedent to payment but merely establishes a reasonable time for payment. Naturally, plaintiff, the subcontractor, urges the court to follow the majority view. Just as naturally, defendant, the general contractor, urges the opposite. Defendant offers two arguments in support of its position.

First, defendant argues that the minority view is simply the better view and that this court, in the absence of guidance from our own Supreme Court, should adopt it. Second, defendant argues that even if the majority view prevails in Virginia, the parties to this particular contract have expressed their intent not to be bound by the majority view here. For the reasons which follow, the court rejects both of defendant’s arguments and will enter summary judgment for the plaintiff.

With respect to whether the court should adopt the majority or minority view, the court has located only four cases which even remotely suggest adherence to the minority view, and three of those cases are highly questionable. In Massoni v. I. B. Miller, Inc., 261 N.Y. 1, 184 N.E. 473 (1933), a case generally cited as indicating that New York has adopted the minority view, the trial judge, after allowing parole evidence to help show the parties’ intent, held that a contract provision similar to the one at issue here created a condition precedent to payment to the subcontractor. The court of appeals affirmed the trial court, stating "[t]he trial judge, after receiving parol evidence of the actual intention of the parties, gave it this construction, and that construction was not erroneous as [a] matter of law." 184 N.E. at 474 (emphasis added).

By contrast, the parties in the case at bar have stipulated that parol evidence would not be helpful to the court here and that the parties’ intent must be gleaned solely from the written contract. In fact, even though defendant has not formally moved for summary judgment, counsel for both parties agreed at oral argument that the court must enter summary judgment for one of the parties now since there are no factual issues in dispute. Thus, unlike the situation in Massoni, the issue here is strictly a question of law.

[306]*306Moreover, a later New York appellate division case cites with approval two of the leading cases expressing the majority view. In Schuler-Haas Electric Corp. v. Aetna Casualty and Surety Co., 371 N.Y.S. 2d 207, 49 A.D. 2d 60 (1975), the court stated:

No New York appellate case has been brought to our attention bearing directly on this issue, but a number of courts in other jurisdictions have dealt with this question. These courts have recognized that as a practical matter, the suppliers and small contractors on large construction projects need reasonably prompt payment for their work and materials in order for them to remain solvent and stay in business. In the absence of a clear expression in the contract papers that the credit risk of the general contractor and the delay in payment frequently attending on constructions projects are meant to be shifted to such suppliers and subcontractors, the contract instruments should not be construed as intending such assumption (Thos. J. Dyer Co. v. Bishop Intern. Engineering Co., 303 F.2d 655 [6th Cir. 1962]). Indeed, it is presumed that the parties did not intend that payment of the small subcontractors should await the determination of an extended legal dispute between the owner and general contractor over an issue not concerning him or his work (Eastern Heavy Constructors v. Fox, 231 Md. 15, 19-20, 188 A.2d 286 [1963]). 371 N.Y.S. 2d at 210.

The court in Schuler-Haas went on to hold that similar language in a payment bond also merely established a time for payment and did not constitute a condition precedent. Id. at 211-12.

Similarly, Zulla Steel, Inc. v. A & M Gregos, Inc., 174 N.J. Super. 124, 415 A.2d 1183 (App. Div. 1980), cited as showing that New Jersey is a minority view state, does not so hold. In Zulla, the contract provided that the subcontractor would be paid 90% of the value of the work completed and approved by the owner and/or the general [307]*307contractor and that such payments would be made on or about the fifteenth day of each succeeding month. The contract further provided that the retainage (10%) would be paid thirty days after completion and acceptance of the captioned job and receipt of final payment therefor by the general contractor.

The subcontractor commenced performance but discontinued its work when it was not paid the progress payments called for in its contract with the general contractor. It then sued the general contractor for the progress payments. The general contractor defended on the ground, inter alia, that it was not obligated to pay the subcontractor until it, the general contractor, was paid by the owner. The trial judge rejected that argument. In affirming, the appellate court noted that there was no provision in the contract between the general contractor and the subcontractor allowing the general contractor to defer progress payments to the subcontractor until payments were received from the owner:

Defendant’s argument that the trial judge improperly rejected evidence of a trade custom that permitted it to defer paying plaintiff until the [owner] paid defendant lacks merit. Whatever may have been the trade custom, the contract between the plaintiff and defendant was clear and unambiguous .... If we read into the contract a provision that defendant could defer payment until it was paid, we would improperly be writing a new contract for the parties. 415 A.2d at 1187 (citations omitted).

The court then added:

Further, since the payment provision did defer payment of the retained percentage to plaintiff until defendant received final payment from the [owner], an intent that such deferment apply to the installments is plainly negated. Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cliff Byler v. Great American Insurance Company
395 F.2d 273 (Tenth Circuit, 1968)
Peacock Const. Co., Inc. v. Modern Air Conditioning, Inc.
353 So. 2d 840 (Supreme Court of Florida, 1977)
Mignot v. Parkhill
391 P.2d 755 (Oregon Supreme Court, 1964)
Peacock Construction Co. v. West
142 S.E.2d 332 (Court of Appeals of Georgia, 1965)
Fishman Construction Co. v. Hansen
209 A.2d 605 (Court of Appeals of Maryland, 1965)
Seal Tite Corp. v. Ehret, Inc.
589 F. Supp. 701 (D. New Jersey, 1984)
Statesville Roofing & Heating Co., Inc. v. Duncan
702 F. Supp. 118 (W.D. North Carolina, 1988)
Eastern Heavy Constructors, Inc. v. Fox
188 A.2d 286 (Court of Appeals of Maryland, 1963)
Zulla Steel, Inc. v. a & M GREGOS, INC.
415 A.2d 1183 (New Jersey Superior Court App Division, 1980)
Mascioni v. I. B. Miller, Inc.
184 N.E. 473 (New York Court of Appeals, 1933)
Peacock Construction Co. v. West
111 Ga. App. 604 (Court of Appeals of Georgia, 1965)
Schuler-Haas Electric Corp. v. Aetna Casualty & Surety Co.
49 A.D.2d 60 (Appellate Division of the Supreme Court of New York, 1975)
A. J. Wolfe Co. v. Baltimore Contractors, Inc.
244 N.E.2d 717 (Massachusetts Supreme Judicial Court, 1969)
Standard Asbestos Manufacturing Co. v. Kaiser
45 N.E.2d 75 (Appellate Court of Illinois, 1942)

Cite This Page — Counsel Stack

Bluebook (online)
22 Va. Cir. 304, 1990 Va. Cir. LEXIS 371, Counsel Stack Legal Research, https://law.counselstack.com/opinion/colonial-mechanical-corp-v-jesson-frantz-contractors-developers-inc-vaccrichmondcty-1990.