Fishman Construction Co. v. Hansen

209 A.2d 605, 238 Md. 418, 1965 Md. LEXIS 670
CourtCourt of Appeals of Maryland
DecidedApril 28, 1965
Docket[No. 252, September Term, 1964.]
StatusPublished
Cited by24 cases

This text of 209 A.2d 605 (Fishman Construction Co. v. Hansen) is published on Counsel Stack Legal Research, covering Court of Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fishman Construction Co. v. Hansen, 209 A.2d 605, 238 Md. 418, 1965 Md. LEXIS 670 (Md. 1965).

Opinion

Horney, J.,

delivered the opinion of the Court.

In this suit for the balance due a subcontractor by a general contractor and its surety for work done and materials furnished on a school construction project, the principal question on appeal is whether the lower court erred in granting the motion of the subcontractor (Wilbur R. Hansen, t/a Hansen Plumbing and Heating Company) for summary judgment against the general contractor and its surety (Fishman Construction Company, Inc., and Security Insurance Company of New Haven, Connecticut). Secondary questions concern the failure of the subcontractor to comply with the subcontract with respect to claims for extras and as to the form of the affidavit prescribed by Maryland Rule 610 b.

Under an agreement made in March 1962, the subcontractor agreed to furnish all materials and perform all work in connection with the plumbing, heating and ventilation of a school building to be constructed in Montgomery County by the general contractor. The standard form of building subcontract, together with such additional insertions a's were pertinent to the project, provided, in part, that the work was to be performed “in accordance with the general conditions of the contract between the owner [Montgomery County Board of Education] and the contractor” so as to reach final completion by February 1, 1963. Payments for materials and work were to be made as the proj ect progressed in the amount of “ninety percent of the value of the work completed up to the first day of the month, as approved by the architect and the owner’s representative.” Other standard provisions stated that the subcontractor agreed to be bound by the terms and general conditions of the agreement between the general contractor and owner and *421 that the general contractor agreed to pay the subcontractor on demand for his work and materials less the retained percentage as the work progressed even though the architect failed to issue a certificate for any cause not the fault of the subcontractor.

While the record does not show when the subcontractor completed his work, the school has been in use since the fall of 1963, and suit for the balance due him was brought in February 1964. The declaration, alleging that the subcontractor had “fully performed the work under the contract in good and workmanlike manner” and that the general contractor “failed and refused to pay the balance due,” was accompanied by the motion for summary judgment. The motion and supporting affidavit, to which were attached a copy of the subcontract and a summarized statement of the balance due the plaintiff thereunder, stated that the defendants had no defense to the claim, that no genuine dispute as to a material fact existed between the parties, and that the defendants were “justly and bona fide” indebted to the plaintiff in the “full and true sum” of S8947.23, which is slightly less than ten per cent of the original contract price. The defendants, in addition to filing the general issue pleas, filed an affidavit in opposition to the motion for summary judgment asserting in effect that the claim of the plaintiff was premature because the ten per cent due him under the subcontract was not payable until the owner, which had not approved and accepted the school building, had paid the general contractor the balance due it for constructing the school. The defendants, however, did not attach to or file with the opposing affidavit a copy of the contract between the owner and the general contractor, as the rule requires, and there was no explanation for the absence thereof. Furthermore, no claim was made that the subcontractor had not satisfactorily performed and completed his wmrk or that the delay in finally approving and accepting the school building was caused by defects in the work done or materials furnished by the plaintiff.

The lower court, on the authority of Eastern Constructors v. Fox, 231 Md. 15, 188 A. 2d 286 (1963), granted the motion and entered a judgment in favor of the plaintiff against the defendants. Since the propriety of granting a motion for *422 summary judgment under Rule 610 d 1 depends on whether or not the pleadings, exhibits and affidavits show the existence of a genuine dispute as to a material fact, we think the plaintiff was entitled to a judgment as a matter of law on the facts of this case.

The appellants (defendants below) assign two reasons for the contention that granting the motion for summary judgment was improper. For one, they assert that the appellee (plaintiff below) should have filed a copy of the general contract or, in lieu thereof, should have given an explanation of its terms as it applied to him. For the other, they claim that the subcontractor was not entitled to be paid the balance due him until after the owner had approved and accepted the school building and paid the general contractor the balance due it. While the subcontractor agreed to perform the subcontract in accordance with the terms and conditions of the general contract, which was conceded to have contained a condition requiring the retention of a percentage of the monies due the general contractor until the owner had approved and accepted the school building, the contentions of the appellants overlook at least two important facts. First, although the subcontractor agreed that the general contractor should retain ten per cent of the value of work completed up to the first of a month, there is nothing in the subcontract to indicate that the general contractor had a right to continue holding the retained percentage, after the subcontract had been fully and satisfactorily performed. Secondly, there is nothing in any of the pleadings, exhibits and affidavits to indicate or even suggest that the work done and materials furnished by the subcontractor had caused the owner to refuse approval and acceptance of the school building.

As we see it, the burden of explaining the conditions of the general contract and showing compliance therewith was not on the appellee. Where, as here, the pleadings, exhibits and affidavits of the moving party set forth sufficient competent evidence to entitle him to summary judgment, it is incumbent upon the opposing party to present such evidence as will give rise to a triable issue of a material fact. Guerassio v. American Bankers, 236 Md. 500, 204 A. 2d 568 (1964). For in order to raise a triable issue, it must be shown by precise facts admis *423 sible as evidence that there is a genuine dispute as to a material fact. Mullan Co. v. I. B. M. Corporation, 200 Md. 248, 151 A. 2d 906 (1959); Frush v. Brooks, 204 Md. 315, 104 A. 2d 624 (1954). That was not done in this case. On the contrary, it may be that the failure of the appellants to file a copy of the general contract prevented the lower court from construing those parts of the contract on which it intended to rely to show the existence of a genuine dispute. Cf. Strickler Eng. Corp. v. Seminar, 210 Md. 93, 122 A. 2d 563 (1956).

Although not involving a motion for summary judgment, it is apparent that the decision of this Court in Eastern Constructors v. Fox, supra, is dispositive of the question as to whether the subcontractor was entitled to be paid the balance due him before the owner had paid the general contractor.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Young Elec. Contractors, Inc. v. Dustin Constr., Inc.
185 A.3d 170 (Court of Appeals of Maryland, 2018)
Sodergren v. Johns Hopkins University Applied Physics Laboratory
773 A.2d 592 (Court of Special Appeals of Maryland, 2001)
Okwa v. Harper
757 A.2d 118 (Court of Appeals of Maryland, 2000)
Faith v. Keefer
736 A.2d 422 (Court of Special Appeals of Maryland, 1999)
Colonial Mechanical Corp. v. Jesson & Frantz Contractors & Developers, Inc.
22 Va. Cir. 304 (Richmond County Circuit Court, 1990)
Riverside Iron Works, Inc. v. Insurance of North America
156 A.D.2d 919 (Appellate Division of the Supreme Court of New York, 1989)
Castiglione v. Johns Hopkins Hospital
517 A.2d 786 (Court of Special Appeals of Maryland, 1986)
Verona Housing, Inc. v. St. Mary's County Metropolitan Commission
413 A.2d 270 (Court of Special Appeals of Maryland, 1980)
Singer v. Steven Kokes, Inc.
384 A.2d 463 (Court of Special Appeals of Maryland, 1978)
Peacock Const. Co., Inc. v. Modern Air Conditioning, Inc.
353 So. 2d 840 (Supreme Court of Florida, 1977)
Placido v. Citizens Bank & Trust Co.
379 A.2d 773 (Court of Special Appeals of Maryland, 1977)
Dietz v. Moore
351 A.2d 428 (Court of Appeals of Maryland, 1976)
Wyand v. Patterson Agency, Inc.
295 A.2d 773 (Court of Appeals of Maryland, 1972)
Melbourne v. Griffith
283 A.2d 363 (Court of Appeals of Maryland, 1971)
Trustees of Broadfording Church v. Western Maryland Railway Co.
277 A.2d 276 (Court of Appeals of Maryland, 1971)
Shatzer v. Kenilworth Warehouses, Inc.
274 A.2d 95 (Court of Appeals of Maryland, 1971)
Brown v. Suburban Cadillac, Inc.
272 A.2d 42 (Court of Appeals of Maryland, 1971)
Marshall v. Woods
271 A.2d 357 (Court of Appeals of Maryland, 1970)
Foreman v. Melrod Ex Rel. Krick of Maryland, Inc.
263 A.2d 559 (Court of Appeals of Maryland, 1970)

Cite This Page — Counsel Stack

Bluebook (online)
209 A.2d 605, 238 Md. 418, 1965 Md. LEXIS 670, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fishman-construction-co-v-hansen-md-1965.