Mullan Contracting Co. v. International Business MacHines Corp.

151 A.2d 906, 220 Md. 248, 1959 Md. LEXIS 502
CourtCourt of Appeals of Maryland
DecidedJune 10, 1959
Docket[No. 247, September Term, 1958.]
StatusPublished
Cited by38 cases

This text of 151 A.2d 906 (Mullan Contracting Co. v. International Business MacHines Corp.) is published on Counsel Stack Legal Research, covering Court of Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mullan Contracting Co. v. International Business MacHines Corp., 151 A.2d 906, 220 Md. 248, 1959 Md. LEXIS 502 (Md. 1959).

Opinion

Horney, J.,

delivered the opinion of the Court.

International Business Machines Corporation (I.B.M. or the supplier) and the Board of Education of Baltimore County (Board of Education) for the use of I.B.M., the plaintiffs below, filed a suit in the Superior Court of Baltimore City against Charles A. Russell, a partnership (Russell or sub-contractor), The Mullan Contracting Company (Mullan or general contractor) and National Surety Company and Maryland Casualty Company (National and Maryland or sureties), the defendants below, for the balance due on the electrical time and fire alarm equipment (usually hereinafter referred to as “equipment”) supplied by I.B.M. and installed in the Kenwood Senior High School (Kenwood project or project). When I.B.M. moved for summary judgment, the lower court granted the motion against all of the defendants (except James A. Russell who was not a copartner). From the judgment for $2420.50 ($1937.50 plus interest), Mullan and the sureties appealed.

Mullan, who had sub-contracted with Russell to furnish and install all of the electrical facilities in the project, paid the subcontractor from time to time while the work was in progress *252 and eventually paid them in full. However, the sub-contractor, who purchased the time and fire alarm equipment from I.B.M., made several payments on account thereof, but failed or refused to pay the balance due of $1937.50. 1

I.B.M., joining five causes of action in one amended declaration, sued Russell on the simple contract and Mullan, as principal, and National and Maryland, as sureties, on payment and performance bonds. Among other things, it was alleged that the sub-contractor ordered the equipment from I.B.M., promised to pay therefor, received delivery thereof and installed it in the Kenwood project, but failed or refused to fully pay therefor. It was further alleged that the principal as well as the sureties on the bonds, although notified of non-payment, also refused to pay the balance due of $1937.50.

In his deposition, L. Thomas Russell (one of the copartners) testified that the partnership had purchased the equipment from I.B.M. at a total cost of $4367, that the prices charged were fair and reasonable and reflected the then current market prices, and that all of the equipment purchased for the project had been installed therein. He further testified that the “summary invoice” attached to the amended declaration was, to the *253 best of his knowledge, correct, and, although he was not absolutely sure that the “payment schedule,” showing total credits of $2429.50, was correct, he thought it was because he recognized the check numbers. He was also of the opinion that at that time [May 31-October 31, 1955] his firm did not have any other accounts with I.B.M. He also recalled that I.B.M. had made a mistake by crediting $500 on May 31, 1955, when the credit should have been only $419, and that the last statement received showed a balance due of $1948, which, when credited with $10.50 for a returned outlet box, would reduce the unpaid balance to $1937.50. On cross-examination, the deponent reiterated that while his firm had purchased other materials from I.B.M. for other projects from time to time, the firm, as of May 31, 1955, was not indebted to I.B.M. for anything other than equipment purchased for use in the Ken-wood project.

In connection with a request for admission of facts and genuineness of documents pursuant to Rule 421, other pertinent facts were established by attaching a true and correct copy of the contract between Mullan and the Board of Education. The basic contract incorporated by reference true and correct extracts of several documents contained in two bound volumes. These, together with forms of the payment and performance bonds, were also attached to the request for admission. The truth and correctness of an omitted rider to one of the bonds was subsequently supplied by stipulation. The request for admission further established that the general contractor and the sureties had been notified of the failure and refusal of the subcontractor to pay I.B.M.

After the amended declaration had been filed on February 4, 1957, many other pleadings were filed during the ensuing period of nineteen months. But when I.B.M., on September 24, 1958, moved for summary judgment as a matter of law pursuant to Rule 610, the case moved more rapidly to a conclusion. Claiming there was no genuine dispute as to any material facts, the motion was based on the pertinent pleadings, the admissions and the only deposition then on file. Two days later, Mullan and the sureties filed what they termed was an *254 “answer”—for which the rule does not provide 2 —stating that there was a genuine dispute between the parties as to “many” material facts and that the “defendants” — but meaning the plaintiffs—were not entitled to judgment as a matter of law, but such facts as were claimed to be in dispute were not specified.

On October 20, 1958, an affidavit made by Charles H. Feihe (secretary-treasurer of Mullan) was filed in opposition to the motion. Therein the affiant made oath that he had personal knowledge that I.B.M. generally charged all purchases made by the sub-contractor to a running account without designating in which of several projects a particular purchase was to be used, that other projects were in progress subsequent to October 1, 1954, and that the sub-contractor had paid I.B.M. $8360 between October 1, 1954, when the Kenwood materials were shipped, and October 31, 1955, when the last payment was made on account of them, although during that time I.B.M. had charged the sub-contractor with purchases aggregating only $4367. At the summary judgment hearing on October 23, 1958, I.B.M. called the affiant, who was allowed to testify without objection. 3 He admitted that he had never been employed by I.B.M. nor the sub-contractor, and that the only knowledge he had had been gathered from an analysis of a ledger card furnished him by the attorneys and other evidence in the case. His testimony on the point was stricken as speculative. 4

On October 22, 1958—one day before the summary judgment hearing had been set and more than twenty months after *255 the amended declaration had been filed—Mullan and the sureties moved for discovery of I.B.M.’s billings to and receipts from the sub-contractor, its accounting card system and all writings between the supplier and the sub-contractor. On the same day notice was served of the desire to take the depositions of two I.B.M. managers on October 30, 1958. At the conclusion of the summary judgment hearing the court made an order postponing the taking of the depositions and staying the production of the records pending further order of the court.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Nationwide Prop. & Cas. v. Selective Way
248 A.3d 1044 (Court of Appeals of Maryland, 2021)
George v. Baltimore Co.
205 A.3d 950 (Court of Appeals of Maryland, 2019)
Scapa Dryer Fabrics, Inc. v. Saville
16 A.3d 159 (Court of Appeals of Maryland, 2011)
Gonzales v. Boas
874 A.2d 491 (Court of Special Appeals of Maryland, 2005)
Wilson v. John Crane, Inc.
867 A.2d 1077 (Court of Appeals of Maryland, 2005)
Maryland State Highway Administration v. Kim
726 A.2d 238 (Court of Appeals of Maryland, 1999)
Reisterstown Plaza Associates v. General Nutrition Center, Inc.
597 A.2d 1049 (Court of Special Appeals of Maryland, 1991)
First Virginia Bank v. Settles
588 A.2d 803 (Court of Appeals of Maryland, 1991)
Washington Federal Savings & Loan Ass'n v. Prince George's County
560 A.2d 582 (Court of Special Appeals of Maryland, 1989)
Atlantic Sea-Con. Ltd. v. Robert Dann Co.
560 A.2d 592 (Court of Special Appeals of Maryland, 1989)
Greer Limestone Co. v. Nestor
332 S.E.2d 589 (West Virginia Supreme Court, 1985)
Insurance Co. of North America v. Aufenkamp
435 A.2d 774 (Court of Appeals of Maryland, 1981)
I. W. Berman Properties v. Porter Bros.
344 A.2d 65 (Court of Appeals of Maryland, 1975)
Trupp v. Wolff
335 A.2d 171 (Court of Special Appeals of Maryland, 1975)
James v. Tyler
304 A.2d 256 (Court of Appeals of Maryland, 1973)
Davis v. Montgomery County
298 A.2d 178 (Court of Appeals of Maryland, 1972)
Shaffer v. Lohr
287 A.2d 42 (Court of Appeals of Maryland, 1972)
L. M. White Contracting Co. v. St. Joseph Structural Steel Co.
488 P.2d 196 (Court of Appeals of Arizona, 1971)
Isle of Thye Land Co. v. Whisman
279 A.2d 484 (Court of Appeals of Maryland, 1971)

Cite This Page — Counsel Stack

Bluebook (online)
151 A.2d 906, 220 Md. 248, 1959 Md. LEXIS 502, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mullan-contracting-co-v-international-business-machines-corp-md-1959.