T. Dan Kolker, Inc. v. Shure

121 A.2d 223, 209 Md. 290, 1956 Md. LEXIS 302
CourtCourt of Appeals of Maryland
DecidedMarch 12, 1956
Docket[No. 105, October Term, 1955.]
StatusPublished
Cited by33 cases

This text of 121 A.2d 223 (T. Dan Kolker, Inc. v. Shure) is published on Counsel Stack Legal Research, covering Court of Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
T. Dan Kolker, Inc. v. Shure, 121 A.2d 223, 209 Md. 290, 1956 Md. LEXIS 302 (Md. 1956).

Opinion

Collins, J.,

delivered the opinion of the Court.

This is an appeal from a decree granting the enforcement of part of a mechanic’s lien, and denying enforcement of the remainder of said lien.

In the latter part of 1953 Arthur A. Shure and Fay Shure, his wife, appellees, entered into a contract with Mr. Albert Miller, President of Georgetown Construction Company, (Miller), a body corporate, for the construction of a home on their lot for $32,500.00. As a result of that contract Mr. Miller approached the appellant, T. Dan Kolker, Inc., (Kolker), which operated a lumber yard in Baltimore City. On October 30, 1953, Mr. Kolker, President of Kolker, and Mr. Miller entered into a written contract for mill work in the amount of $2,587.51 to be furnished for the Shure dwelling.

About the time this written contract was made, Mr. Kolker and Mr. Miller discussed the rough lumber to be furnished on this job. Mr. Kolker testified that he told Mr. Miller that he would sell him the rough lumber at the “going price” at the time and that Mr. Miller agreed to buy from him whatever rough lumber he needed for the Shure house at the “going price”. Mr. Miller testified that he told Mr. Kolker that he would buy all his rough lumber from him provided his deliveries and *294 price “were right” at the time the material was desired. He further said that he only agreed to buy the rough lumber from Mr. Kolker if the price was satisfactory, and that if the price was not low enough Mr. Kolker could not compel him to buy it.

When asked by the Court why a definite contract was entered into for the mill work and not for the rough lumber, Mr. Miller replied: “You see, lumber, there aren’t too many millwork shops, and a residence of this type was special millwork involved, and you have got to have time to make it up. While, if you need rough lumber, you can call up any yard and say, ‘Have you got this and this size in stock,’ and, ‘When can you deliver it?’ ” He further said that the order for the rough lumber was more or less a “bait” for the millwork. He also said: “* * * my procedure was, and the instruction to the superintendent was on the job when he needed material, he would see me in the morning, and tell me. I would go to the phone, and I called up T. Dan Kolker, and say, ‘Have you got this and this in this size ?’ If they didn’t have it, I would say, ‘Forget about it.’ If they had it, ‘What is the price.’ I might call up one or two other companies, particularly Pulaski who were working on a very narrow margin, and so on. I mean — but Kolker always got first preference, because I felt I had an obligation to him because we made a deal on the millwork. He had first choice.” The invoices were made out by Kolker to “Georgetown Construction Co. & A. Miller, (Shure Residence, Stevenson Lane and Anton Farms Road).” The items of millwork and lumber were carried as a single account on the invoices and on Kolker’s books. It was admitted that all the materials listed in the liens claimed on these invoices were delivered to the Shure property.

Kolker extended credit to Miller and began supplying materials on the Shure job on December 10, 1953, and charged the millwork and rough lumber in one and the same account. On the invoices sent to Miller these items were not differentiated. Kolker continued to de *295 liver material to Miller without any payment until June 25, 1954, at which time Kolker claimed a balance owing of $4,730.30. Miller had sent several checks to Kolker which were returned by the bank for lack of funds. On July 14, 1954, Miller sent Kolker a check on a Towson bank for $401.37 which was paid, and when credited to the Miller account, left a balance of $4,328.93.

In June, 1954, Miller, on account of financial difficulties, abandoned the contract with Shure. After that time the construction of the house was done under the personal supervision of Mr. Shure. On July 14, 1954, and again on July 16, 1954, Kolker gave proper notice by registered mail of its intention to file a mechanic’s lien in the amount of $4,329.33 against the Shure dwelling. Attached was an itemized invoice. The Shures, appellees, admit that they received this notice of intention to file on July 17, 1954. Kolker, pursuant to said letters, on September 17, 1954, filed the mechanic’s lien for $4,329.33. Deducting the payment of $401.37 from $4,730.30 leaves a balance of $4,328.93 and not $4,329.33. The appellees, Shures, having failed to pay that lien, Kolker, the appellant, brought this suit in equity for its enforcement. During the trial of the case it was found that an item charged in the amount of $19.38 had been returned. The amount therefore claimed by the appellant is $4,309.55.

The chancellor was of the opinion that there was a contract for the millwork but no contract for the rough lumber. Accordingly a decree was signed ordering the balance of the payment for the millwork in the amount of $2,078.41, without interest, in full payment and discharge of the mechanic’s lien. From that decree appellant appeals.

Code, 1951, Article 63, Section 11, provides: “If the contract for furnishing such work or materials, or both, shall have been made with any architect or builder or any other person except the owner of the lot on which the building may be erected, or his agent, the person so doing work or furnishing materials, or both, shall *296 not be entitled' to a lien unless, within sixty days after furnishing the same, he or his agent shall give notice in writing to such owner or agent, if resident within the city or county, of his intention to claim such lien.”

From the account filed it appears that rough lumber was delivered to this project from January 5, 1954, up to and including May 25, 1954. The last two items of rough lumber delivered were on March 18, 1954, charged at $10.48, and on May 24, 1954, charged at $19.80. This last delivery of $19.80 was within the sixty day period required for notice of intention to file the lien.

Of course, the mechanic’s lien law was passed to protect material men. This Court has laid down the rule that it is to be construed in the most liberal and comprehensive manner in favor of mechanics and material men. Blake v. Pitcher, 46 Md. 453, 464; Real Estate Co. v. Phillips, 90 Md. 515, 527, 45 A. 174; Fulton v. Parlett, 104 Md. 62, 64 A. 58; Caltrider v. Isberg, 148 Md. 657, 668, 130 A. 53. In the late case of Bounds v. Nuttle, 181 Md. 400, 406, 30 A. 2d 263, it was said: “The mechanic’s lien law was passed to cover just such a situation and to protect material men. The theory of it is that the owner gets the benefit of the material, and he has control of the money. If he negligently and carelessly pays the money out to the contractor without taking precautions to see that it is applied to the payment of the materials which go in the building, then he must stand the loss rather than the material man, who has no opportunity to protect himself once he has delivered the materials.”

All parties agree that there was a contract for the millwork. The first question to be decided is whether there was a contract for the rough lumber delivered.

Mr. Miller said he agreed to buy all the rough lumber from the appellant provided its deliveries and prices were right at the time the material was desired.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Arfaa v. Martino
946 A.2d 995 (Court of Appeals of Maryland, 2008)
A.J. Rinella & Co. v. Bartlett (In Re Bartlett)
367 B.R. 21 (D. Massachusetts, 2007)
Martino v. Arfaa
906 A.2d 945 (Court of Special Appeals of Maryland, 2006)
Cottage City Mennonite Church, Inc. v. Jas Trucking, Inc.
894 A.2d 609 (Court of Special Appeals of Maryland, 2006)
Ridge Heating, Air Conditioning and Plumbing, Inc. v. Brennen
783 A.2d 691 (Court of Appeals of Maryland, 2001)
WINKLER CONSTRUCTION CO. INC. v. Jerome
734 A.2d 212 (Court of Appeals of Maryland, 1999)
Insurance Co. of North America v. Genstar Stone Products Co.
656 A.2d 1232 (Court of Appeals of Maryland, 1995)
Celta Corp. v. A.G. Parrott Co.
617 A.2d 632 (Court of Special Appeals of Maryland, 1993)
Greens at Hilton Run I Ltd. Partnership v. Rollin Building Supply Co.
589 A.2d 536 (Court of Special Appeals of Maryland, 1991)
Reisterstown Lumber Co. v. Tsao
574 A.2d 307 (Court of Appeals of Maryland, 1990)
Ami Operating Partners Ltd. Partnership v. Jad Enterprises, Inc.
551 A.2d 888 (Court of Special Appeals of Maryland, 1989)
Ridge Sheet Metal Co. v. Morrell
517 A.2d 1133 (Court of Special Appeals of Maryland, 1986)
Cabana, Inc. v. Eastern Air Control, Inc.
487 A.2d 1209 (Court of Special Appeals of Maryland, 1985)
Hurst v. v & M of Virginia, Inc.
446 A.2d 55 (Court of Appeals of Maryland, 1982)
Back v. Reisterstown Lumber Co.
332 A.2d 30 (Court of Special Appeals of Maryland, 1975)
Clark-King Constr. v. SALTER AND TAYLOR, TRUSTEES
307 A.2d 485 (Court of Appeals of Maryland, 1973)
Diener v. Cubbage
270 A.2d 471 (Court of Appeals of Maryland, 1970)
Palmer Park Ltd. Partnership v. Marvelite, Inc.
257 A.2d 169 (Court of Appeals of Maryland, 1969)

Cite This Page — Counsel Stack

Bluebook (online)
121 A.2d 223, 209 Md. 290, 1956 Md. LEXIS 302, Counsel Stack Legal Research, https://law.counselstack.com/opinion/t-dan-kolker-inc-v-shure-md-1956.