Humphrey v. Harrison Bros., Inc

196 F.2d 630, 1952 U.S. App. LEXIS 2508
CourtCourt of Appeals for the Fourth Circuit
DecidedMay 2, 1952
Docket6402
StatusPublished
Cited by7 cases

This text of 196 F.2d 630 (Humphrey v. Harrison Bros., Inc) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Humphrey v. Harrison Bros., Inc, 196 F.2d 630, 1952 U.S. App. LEXIS 2508 (4th Cir. 1952).

Opinion

*631 SOPER, Circuit Judge.

This case calls for a construction of the Mechanics’ Lien Law of Maryland, Article 63, §§ 1 to 33 of the Maryland Code, and particularly Section 1, 1947 Supplement to Maryland Code which provides that in the counties of Maryland, as distinguished from Baltimore City, every building erected shall be subject to a lien for the payment of all debts contracted for materials furnished for or about the same. Section 3 of the statute further provides that no person having such a lien shall be considered as waiving it by granting credit or receiving notes or other securities, unless the same shall be received as payment, or the lien is expressly waived; and Section 11 provides that if the contract for furnishing the materials is made with any person except the Owner of the lot on which the building may be erected, the furnisher of the materials shall not be entitled to a lien unless within sixty days after furnishing the same, he shall give notice in writing to the owner of his intention to claim a lien. Sections 17 and 18 provide for the filing of the lien in the office of the clerk of the Circuit Court for the county, and the maintenance by the clerk of a mechanics’ lien docket in which he shall record a description of the property affected and the name. Section 19 specifically provides that every claim shall set forth the name of the claimant, the owner of the building, and the contractor, when the contract was made by the claimant with the contractor; also the amount claimed and the kind of materials furnished, the time when they were furnished and the locality and size of the building. Section 21 provides that if the claim shall be filed against two or more buildings owned by the same person, the claim s.hall designate the amount claimed to be due on each of the buildings, otherwise the claim shall be postponed to other lien creditors and the lien shall not extend beyond the amount designated as against other lien creditors. Section 32 provides that Article 63 shall be construed and have the sanie effect as laws which are remedial in their nature.

The controversy relates to a lien claim of Harrison Brothers, Inc., a wholesale plumbing and supply house located in Washington in the District of Columbia, for plumbing and heating supplies sold on open account to Alexander Green for installation in 135 houses erected on a tract of land in University Hills, Chillum District, Prince George’s County, Maryland. The material was supplied and installed by Green at the rate of $1250 per house under a single contract of March 21, 1950 between Green and James Humphrey, the owner of the land and the builder of the houses.

Prior to the execution of the contract, Green arranged with Harrison to purchase the necessary material to enable him to perform his contract with Humphrey and 90 per cent, of the supplies needed for the job were actually purchased from Harrison. Prices were named by Harrison at the beginning of the operation but there was no written or oral contract between Harrison and Green fixing the prices or binding the parties to a sales agreement for the entire project; and the goods were bought on open account as needed during the ensuing months, and payments on account were made from time to time. In August, 1950 the prices for plumbing and heating supplies had risen 40 to 50 per cent, over those prevailing in March, and the goods subsequently supplied by Harrison to Green were billed at the new prices. Although Green was under a firm contract at the time to supply each house with the needed material for $1250, Humphrey, the owner and builder of the houses, advanced the contract price by $150 per house to help meet the emergency. In every instance the invoices of Harrison showed that the goods were sold to Green for use on the University Hills project.

During the progress of the work Green got behind in his payments so that on January 25, 1951 he was indebted to Harrison in the sum of $8396.76 for goods installed in the houses on the University Hills project. On that date Harrison served a notice of a claim for a lien on 29 houses erected *632 by Humphrey in blocks K and J in the development. The lien was recorded in the clerk’s office of the county on January 29, 1951. The claim as filed was somewhat in excess of the sum of $8396.76, which is now accepted by the parties as the correct amount. All of the goods listed in the claim were furnished to the project between November 27, 1950 and January-11, 1951, and it is conceded that the claim was filed in due time.

When the notice of the claim was served and recorded. Green was still engaged in the performance of his contract for the 135 houses and the work on the 29 houses in blocks K and J was still incomplete; and some of the materials purchased from Harrison by Green for the contract was on the site of the work awaiting installation. Green was engaged on the job until May, 1951.

Additional facts to which the appellant attributes special significance are that although all the materials for which the claim was filed were installed in the houses in the University Hills project, none of the materials (except a very small amount) was installed in the 29 houses in blocks K and J; and that when the claim was made Humphrey had paid Green for all the material furnished and work done in those houses. It 'was explained -by claimant’s attorney in the course of the trial that the notice of lien was confined to the houses in blocks K and J because at the time the lien was filed claimant’s attorneys were not informed as to the ownership by Humphrey of the remaining portions of the tract.

In order to test the validity of the lien, Humphrey filed suit against Harrison in the Circuit Court of Prince George’s County. The suit was removed to the District Court below on the ground of diversity of citizenship and a counterclaim for the enforcement of the lien was filed, upon which trial ■ was had resulting in a judgment establishing the validity of the lien for the sum of $8396.76. The property owner appealed to this court.

While it is now admitted that Green is indebted to Harrison in the sum of $8396.-76 and that the lien was claimed in due time, it is contended that the claim is invalid because (1) Harrison failed to furnish the supplies at the prices named at the beginning of the transactipn; (2) Harrison supplied the material on open account <?n the personal credit of Green and did not rely on the credit of the buildings or the right to assert a lien against them; and (3) the materials specified in the claim were not installed in the houses in blocks K and J against which the lien is asserted, but in other houses in the project against which no claim has been filed, and therefore the lien as to the latter houses has been waived and, under the Maryland decisions, may not now be allowed against the houses in blocks K and J.

There is no shadow of substance in the first two contentions. The evidence clearly shows and the judge found that Green had no binding contract with Harrison for the purchase at fixed prices of all materials needed for the job. Although all the material was purchased for the University Hills project, each purchase was a separate transaction, and Harrison was within its right in raising the prices in August 1950 -in accordance with the rising market.

It is equally clear that the extension of credit by the supply house to the contractor for materials to be used in the houses in the project did not prohibit the creation of a lien.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

District Heights Apartments v. Noland Co.
95 A.2d 90 (Court of Appeals of Maryland, 1998)
Back v. Reisterstown Lumber Co.
332 A.2d 30 (Court of Special Appeals of Maryland, 1975)
Clark Certified Concrete Co. v. Lindberg
141 A.2d 685 (Court of Appeals of Maryland, 1958)
T. Dan Kolker, Inc. v. Shure
121 A.2d 223 (Court of Appeals of Maryland, 1956)
Warner Co. v. Leedom Construction Co.
97 A.2d 884 (Supreme Court of Delaware, 1953)

Cite This Page — Counsel Stack

Bluebook (online)
196 F.2d 630, 1952 U.S. App. LEXIS 2508, Counsel Stack Legal Research, https://law.counselstack.com/opinion/humphrey-v-harrison-bros-inc-ca4-1952.