Clark Certified Concrete Co. v. Lindberg

141 A.2d 685, 216 Md. 576
CourtCourt of Appeals of Maryland
DecidedMay 19, 1958
Docket[No. 211, September Term, 1957.]
StatusPublished
Cited by8 cases

This text of 141 A.2d 685 (Clark Certified Concrete Co. v. Lindberg) is published on Counsel Stack Legal Research, covering Court of Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Clark Certified Concrete Co. v. Lindberg, 141 A.2d 685, 216 Md. 576 (Md. 1958).

Opinions

Henderson, J.,

delivered the opinion of the Court.

This appeal is from decrees of an equity court dismissing bills of complaint filed by the appellants for the sale of houses owned by Walter W. Lindberg and wife, and Rosalie Hokemeyer, respectively known as 1243 and 1245 Neighbors Avenue, to enforce mechanics’ liens against each property in the total amount of $5,798.93. The two cases were heard together and present the same questions for decision.

It was stipulated that Brook Homes, Inc., acquired a tract of land for development purposes by various conveyances between January 26 and August 13, 1951, consisting of 92 lots out of a total of 119 shown on a recorded plat. It proceeded to erect houses on these lots in groups of six or seven. Construction began in January, 1951, and continued until a re[578]*578ceiver was appointed for Brook Homes, Inc., on August 28, 1953, at which time some of the houses were still uncompleted. The houses with which we are now concerned were substantially completed by June 16, 1952, and were used as sample houses by the developer. They were sold by the developer on June 16, 1953. The lien claims were filed on August 5, 1953, and were for ready mixed concrete supplied to the developer between August 1, 1952 and April 8, 1953. None of this concrete went into the houses in question.

Mr. William M. Duncan, Jr., a salesman for Clark Certified Concrete Company, Inc. (Clark), testified that he discussed with Mr. Schoppert, who was in charge of buying materials for Brook Homes, Inc. (Brook), the matter of supplying concrete for the new development. This conversation took place before any of the work began. Schoppert asked if Clark would be able to supply concrete for the job and Duncan said it would. There was no signed contract to supply all of the concrete necessary for the development, but it was understood that Schoppert would “give us at least a day’s notice, and he would tell us how many yards for that particular day, and we would deliver it.” The price was to be “the prevailing price at the time of delivery * * * on that particular day he would pay what the yardage price would be.” Pursuant to the understanding, concrete was regularly delivered as ordered, in each month and on 134 different days between February 28, 1951, and April 8, 1953, a total of 1883 cubic yards of concrete at a total price of $20,720.38, as shown by invoices produced. The account was paid up to and including the concrete delivered on July 29, 1952, the total amount paid being $14,921.95.

The appellees contend that the liens were not filed in time. The Mechanics’ Lien Law, Code (1957), Art. 63, sec. 1, pn> vides that “Every building erected * * * shall be subject to a lien for the payment of all debts contracted * * * for materials furnished for or about the same * * Sec. 23 provides that “Every such debt shall be a lien until after the expiration of six months after the work has been finished or the materials furnished, although no claim has been filed therefor, but no longer, unless a claim shall be filed at or [579]*579before the expiration of that period.” We have held that the clause as to “work” refers to a labor claim. A material claim must be filed within six months from- the time the materials are furnished. Harrison v. Stouffer, 193 Md. 46, 50; Heath v. Tyler, 44 Md. 312, 318; Trustees of German Lutheran Church v. Heise, 44 Md. 453, 475. In the instant case the claims were filed within six months from the date of the last delivery, April 8, 1953. It seems clear that an express antecedent contract is not a prerequisite. Where there are continuous deliveries at a “going price”, pursuant to an undertaking to supply materials as needed, a lien may be filed within six months from the delivery of the last item, provided sxtch delivery is made in good faith and not as a subterfuge to toll the statute. T. Dan Kolker, Inc. v. Shure, 209 Md. 290; District Hgts. Apts. v. Noland Co., 202 Md. 43; Humphrey v. Harrison Bros. (4th Cir.), 196 F. 2d 630.

The appellees contend that because it was shown that none of the materials for which the liens are claimed went into the houses against which the liens were filed, the liens were unenforceable. It is generally held that delivery of material to the site of building operations is enough to establish a lien, even though none of the materials are actually incorporated into the building, but the cases are not in accord as to whether such proof is conclusive, or merely establishes a rebuttable presumption. See note in 39 A. L. R. 2d 394. That the fact of incorporation is immaterial was flatly stated in Greenway v. Turner, 4 Md. 296 and Watts v. Whittington, 48 Md. 353, although probably the statement was unnecessary for the decisions in those cases. In Wilson v. Wilson, 51 Md. 159, while the Court found there was a failure to prove the use. of materials in one of the four houses sought to be charged, the holding was that the lien failed because of a release by the claimant, which had the effect of releasing all of the houses from the lien. To the same effect, see Nickel v. Blanch, 67 Md. 456, and Brick Co. v. Dimkerly, 85 Md. 199. In Maryland Brick Co. v. Spilman, 76 Md. 337, it was held that where there was an entire contract to deliver bricks for the construction of 47 houses, it was not incumbent upon the claimant to show that the bricks were actually used in the [580]*580construction of the particular buildings against which the lien was filed. The statement in the Greenway and Watts cases, supra, was quoted with approval. The Wilson and Nickel cases were distinguished as dealing with the effect of a release. But it is not entirely clear from this decision whether the Court meant that the owner would be precluded from showing that none of the materials went into the particular buildings. The Court observed that it would be “unreasonable to require the person who furnishes materials * * * to ascertain how much of the material is placed in each house * * *”. This same statement was repeated in Fulton v. Parlett, 104 Md. 62, 64, where it was also said that there was no duty to apportion the claim where more than one structure is built. In Caltrider v. Isberg, 148 Md. 657, it was held by a divided court that where the owner paid the builder for all the materials going into one of the two houses under construction, this did not amount to an apportionment ■or prevent the enforcement of the lien against both houses.

In Humphrey v. Harrison Bros., supra (p. 633), the facts were that a lien claim was based upon an agreement to furnish plumbing and heating supplies for 135 houses, at a flat rate per house. It was shown that payment had been made for substantially all of the materials installed in the 29 houses against which the lien was filed. Judge Soper, for the Court, applying the Maryland law, sustained the lien, and said that it was “not essential to the validity of the lien claim that the furnisher show in what houses specific materials were used, ■or indeed that the materials were actually used upon the •project if they were purchased for and delivered to the site ■ of the work.” .The statement was quoted with approval in District Hgts. Apts v. Noland Co., supra (p. 48). We also stated (p.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Insurance Co. of North America v. Genstar Stone Products Co.
656 A.2d 1232 (Court of Appeals of Maryland, 1995)
Reisterstown Lumber Co. v. Tsao
574 A.2d 307 (Court of Appeals of Maryland, 1990)
Talbott Lumber Co. v. Tymann
428 A.2d 1229 (Court of Special Appeals of Maryland, 1981)
Landover Associates Ltd. Partnership v. Fabricated Steel Products, Inc.
371 A.2d 1140 (Court of Special Appeals of Maryland, 1977)
Brosenne v. Warthen
172 A.2d 485 (Court of Appeals of Maryland, 1961)
G. Edgar Harr Sons v. Newton
155 A.2d 480 (Court of Appeals of Maryland, 1959)
Clark Certified Concrete Co. v. Lindberg
141 A.2d 685 (Court of Appeals of Maryland, 1958)