United States ex rel. Noland Co. v. Allied Contractors, Inc.

171 F. Supp. 569, 1959 U.S. Dist. LEXIS 3623
CourtDistrict Court, D. Maryland
DecidedMarch 13, 1959
DocketCiv. A. No. 9369
StatusPublished
Cited by4 cases

This text of 171 F. Supp. 569 (United States ex rel. Noland Co. v. Allied Contractors, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States ex rel. Noland Co. v. Allied Contractors, Inc., 171 F. Supp. 569, 1959 U.S. Dist. LEXIS 3623 (D. Md. 1959).

Opinion

R. DORSEY WATKINS, District Judge.

This is a suit under the Miller Act, 40 U.S.C.A. § 270a et seq., brought by the United States to the use of Noland Company, Incorporated (Noland) against Allied Contractors, Incorporated (Allied), prime contractor, and Maryland Casualty Company, surety for said prime contractor, to recover One Thousand Thirty-Three Dollars and Thirty-Six Cents ($1,033.36) together with interest and costs on a statutory payment bond or bonds for materials furnished and delivered by Noland to Thomas Electric Company (Thomas), a subcontractor of Allied, in the prosecution of work under two government contracts in connection with the building of a Nike I project control area and a Nike I project launching area within the state of Maryland.

Allied and its surety in their answer to the complaint asserted as defenses to this action that statutory limitations under the Miller Act had run; that there was no evidence of the use on the job site of the materials furnished by plaintiff; and the general issue plea that the defendants never promised and were not indebted as alleged.1

Parties stipulated as to the facts which they felt were controlling, as follows:2

“3. Allied Contractors, Incorporated subcontracted a portion of the work called for under bond of said Government contracts to Thomas Electric Company.
“4. Noland Company, Incorporated, the use Plaintiff who was a distributor of electrical supplies, supplied and furnished to Thomas Electric Company for use on the projects covered by said Government contracts, by separate and distinct, orders and not under a general or continuing contract to supply material, various materials at different times for the projects covered by bond of said Government contracts. Under Contract No. DA-18-020 Eng. 714, the use Plaintiff supplied material on the dates and at the prices indicated below:

Amount Invoice No. Date of Delivery

$ 26.72 8270 12-22-54

74.42 1748 1- 10-55

17.29 3431 2- 10-55

19.03 1283 2- 25-55

3.32 7799 3- 24-55

260.98 8320 3-25-55

Total $401.76

[571]*571Under Contract No. DA-18-020 Eng. 697, the use Plaintiff supplied material on the dates and at the prices indicated below:

Invoice No. Date of Delivery Amount

8796 12-28-54 $211.61

520 1-24-55 25.68

4793 2-11-55 224.52

4792 2-15-55 49.94

6088 2-21-55 86.82

1859 4- 6-55 33.03

Total $631.60

“5. Noland Company, Incorporated has never received payment for the material referred to above.

“6. On May 5, 1955, Noland Company, Incorporated notified Allied Contractors, Incorporated of its claim for such material by registered mail.

“7. Noland Company, Incorporated entered the present suit within one year from the date of final settlement by the United States and Allied Contractors, Incorporated of the two above mentioned Government contracts.”

The case was then submitted on the stipulated facts for a ruling by the court on the merits. The applicable statutory provision is 40 U.S.C.A. § 270b, which provides as follows:

“(a) Every person who has furnished labor or material in the prosecution of the work3 provided for in such contract, in respect of which a payment bond is furnished under section 270a of this title and who has not been paid in full therefor before the expiration of a period of ninety days after the day on which the last of the labor was done or performed by him or material was furnished or supplied by him for which such claim is made, shall have the right to sue on such payment bond for the amount, or the balance thereof, unpaid at the time of institution of such suit and to prosecute said action to final execution and judgment for the sum or sums justly due him: Provided, however, That any person having direct contracual relationship with a subcontractor but no contractual relationship express or implied with the contractor furnishing said payment bond shall have a right of action upon the said payment bond upon giving written notice to said contractor within ninety days from the date on which such person did or performed the last of the labor or furnished or supplied the last of the material for which such claim is made, stating with substantial accuracy the amount claimed and the name of the party to whom the material was furnished or supplied or for whom the labor was done or performed. Such notice shall be served by mailing the same by registered mail, postage prepaid, in an envelop addressed to the contractor at any place he maintains an office or conducts his business, or his residence, or in any manner in which the United States marshal of the district in which the public improvement is situated is authorized by law to serve summons.
“(b) * * * but no such suit shall be commenced after the expira[572]*572tion of one year after the date of final settlement of such contract.”

Upon oral argument the defendants abandoned the defense of failure to prove use on the job site of the materials furnished, and correctly so in view of such authorities as Fourt v. United States for use of Westinghouse Electric Supply Co., 10 Cir., 1956, 235 F.2d 433, 435; Glassell-Taylor Co. v. Magnolia Petroleum Co., 5 Cir., 1946, 153 F.2d 527, 529-530; Montgomery v. Unity Electric Co., Inc., D.C. Puerto Rico 1957, 155 F.Supp. 179, 180; United States for Use and Benefit of J. A. Edwards & Co., Inc. v. Bregman Construction Corp., D.C.N.Y.1957, 156 F.Supp. 784, 787;—each holding that to permit recovery under the Miller Act all that the materialman need show is that, in the words of the statute itself (see pertinent underlined portion above), the materials were furnished in the prosecution of the work4 and that there is no requirement of proof that the materials were actually used or incorporated into the contract project. (Contra: United States for Benefit and Use of Westinghouse Electric Supply Co. v. Robbins, D.C.Mass.1954, 125 F.Supp. 25, 27).

By the time of submission of briefs the defendant had apparently abandoned the defense of “statutory limitations”, that is, that no claim could be made, under the facts in this particular case, for material delivered more than ninety days prior to May 5, 1955, the date the Notice of Claim by the plaintiff was received by Allied. The defendants’ brief stated, in part:

“Specifically the issue is whether under the Miller Act a person supplying materials to a sub-contractor, a government contractor, and to whom an unpaid balance is due, without a contractual basis either express or implied with sadd subcontractor (and as is stipulated) and who made only over-the-counter sales and which sales were a series of independent transactions, without the slightest knowledge of how much material will be needed or how long the sub-contractor’s contract will run, can recover on the payment bond executed by the Allied Contractors. -x-

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Back v. Reisterstown Lumber Co.
332 A.2d 30 (Court of Special Appeals of Maryland, 1975)
United States v. Peter Reiss Construction Co.
273 F.2d 880 (Second Circuit, 1959)

Cite This Page — Counsel Stack

Bluebook (online)
171 F. Supp. 569, 1959 U.S. Dist. LEXIS 3623, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-ex-rel-noland-co-v-allied-contractors-inc-mdd-1959.