United States Ex Rel. Bruce Co. v. Fraser Const. Co.

87 F. Supp. 1, 1949 U.S. Dist. LEXIS 1945
CourtDistrict Court, W.D. Arkansas
DecidedDecember 5, 1949
DocketCiv. 878
StatusPublished
Cited by32 cases

This text of 87 F. Supp. 1 (United States Ex Rel. Bruce Co. v. Fraser Const. Co.) is published on Counsel Stack Legal Research, covering District Court, W.D. Arkansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States Ex Rel. Bruce Co. v. Fraser Const. Co., 87 F. Supp. 1, 1949 U.S. Dist. LEXIS 1945 (W.D. Ark. 1949).

Opinion

JOHN E. MILLER, District Judge.

This cause of action is brought under the Miller Act, Title 40 U.S.C.A. § 270b, to recover from the defendant Construction Company and the defendant Bonding Company, on the payment bond given pursuant to the Act, the value of certain materials furnished to a sub-contractor of the Construction Company, which held a contract for the construction work on a government project at Shumaker, Arkansas.

Defendants have filed a motion to dismiss for failure to state a claim upon which relief can be granted, which motion is now before the court, alleging that as a condition precedent to the creation of a right of action on said bond the statute (Miller Act) requires the giving to the defendant Construction Company of notice in writing within 90 days from the furnishing of the material stating with substantial accuracy the amount claimed and the name of the party to whom the material was furnished, and that the complaint fails to allege the *3 giving of said notice within the time prescribed.

The Federal Rules of Civil Procedure, 28 U.S.C.A., contemplate a very liberal view of the complaint when it is challenged for insufficiency of statement. As stated by the Court of Appeals for this, the 8th, Circuit in Dennis et al. v. Village of Tonka Bay et al., 151 F.2d 411, 412; “Under the present practice in the District Courts of the United States, a motion to dismiss a complaint for failure to state a claim upon which relief can be granted, admits the existence and validity of the claim as stated, but challenges the plaintiff’s right to relief. Leimer v. State Mut. Life Assur. Co., 8 Cir., 108 F.2d 302, 305. This Court has said that there is no justification for dismissing a complaint for insufficiency of statement unless it appears to a certainty that the plaintiff would be entitled to no relief under any state of facts which could be proved in support of the claim. (Citing cases.)”

Proceeding then to an examination of the allegations of the complaint the court finds, and accepts as true for purposes of this motion, the following facts.

On or about February 2, 1948, the defendant, Fraser Construction Company, entered into a building contract (No. Y-14378) with the United States Government to construct certain barracks and other buildings at the Naval Ammunition Depot at Shumaker, Arkansas. The defendant Construction Company, as well as the defendant Bonding Company, executed a bond dated March 16, 1948, to guarantee the payment to all persons supplying labor and materials in the prosecution of the work. In reliance upon this bond and the oral assurance of the defendant Construction Company that the plaintiff would get its money for materials, the latter furnished certain materials to W. B. Crosland, d/b/a Crosland Electric Company of Fort Smith, Arkansas, a sub-contractor doing the electrical work on said project. Materials were furnished between February 7, 1948, and October 2, 1948, of the total value of $14,852.58. Crosland, the sub-contractor, paid $6,759.79 on the total, leaving unpaid $8,092.79. Defendant Construction Company authorized and approved the furnishing of the materials, and was notified that Crosland was not paying for the same. After being so notified, defendant Construction Company requested plaintiff to continue furnishing materials and represented to plaintiff that they would be paid for, advising that the bond sued upon herein was executed for the protection of plaintiff. Crosland had approximately $4,000.00 worth of materials on hand on or about September 20, 1948, and on that date defendant Construction Company took ovei the electrical work and used said materials in finishing the work. Thereafter, defendant Construction Company received other materials from the plaintiff and used the same on the job. For the purpose of doing the work Crosland was the agent of the defendant Construction Company, and the defendant Construction Company received all materials by reason of delivery to Crosland or directly to the job. Demand has been made upon -Crosland for the balance due, the accuracy of which is admitted by the latter, and demand has been made upon the defendant Construction Company, but both have refused payment.

As appears from the above, the complaint does not allege that written notice was given to the defendant Construction Company within 90 days from the -date of the last furnishing of materials stating with substantial accuracy the amount claimed and to whom furnished.

The applicable provision of the Miller Act, Title 40 U.S.C.A. § 270b, grants a cause of action upon the payment bond required thereby to every person who has furnished material in the prosecution of work provided for in a contract such as the one here. This provision contemplates a contractual relationship express or implied with the contractor furnishing the payment bond, but in a proviso, a cause of action is granted on the payment bond to any person furnishing materials who has a direct contractual relationship with a subcontractor but no contractual relationship express or implied with the contractor furnishing the bond, provided such person gives written notice to said contractor (who furnished the bond) within 90 days from the *4 last furnishing of materials stating with substantial accuracy the amount claimed and the person to whom furnished. It is further provided that the notice shall be served by registered mail or in any manner in which the United States Marshal of the district in which the improvement is situated is authorized by law to serve summons.

The plaintiff, in opposition to the motion to dismiss, contends as follows:

(1) The use plaintiff was not required to give the 90 day notice referred to in the statute for the reason that a contractual relationship, either express or implied, existed between the plaintiff and the defendant Fraser Construction Company, Inc.

(2) The defendants are precluded from setting up the lack of the 90 day notice because of waiver and estoppel.

(3) The defendant Fraser Construction Company, Inc., having had actual notice, the statutory notice was unnecessary.

The last two contentions of the plaintiff will be considered first and together.

Although the Miller Act is highly remedial in nature and is entitled to a liberal construction in order properly to effectuate the Congressional intent to protect those whose labor and materials go into public projects, Fleisher Engineering and Construction Co. v. United States, 311 U.S. 15, 17, 61 S.Ct. 81, 85 L.Ed. 12; Clifford F. MacEvoy Co. et al. v. United States, 322 U.S. 102, 107, 64 S.Ct. 890, 88 L.Ed. 1163, the courts have not proceeded with such liberality as to extend the scope of the Act 'beyond the plain words of limitation contained therein.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Southern Electrical Health Fund v. Kelley
308 F. Supp. 2d 847 (M.D. Tennessee, 2003)
Chicago Rigging Co. v. Uniroyal Chemical Co., Inc.
718 F. Supp. 696 (N.D. Illinois, 1989)
United States v. Limbs
356 F. Supp. 1004 (D. Arizona, 1973)
Fuller Industries, Inc. v. R. Terry Blazier & Son, Inc.
188 So. 2d 2 (District Court of Appeal of Florida, 1966)
Fidelity & Deposit Co. v. Harris
360 F.2d 402 (Ninth Circuit, 1966)
Woods Construction Co. v. Pool Construction Co.
348 F.2d 687 (Tenth Circuit, 1965)
California Electric Supply Co. v. United Pacific Life Insurance
227 Cal. App. 2d 138 (California Court of Appeal, 1964)
United States v. Baehner, Inc.
326 F.2d 556 (Second Circuit, 1964)
United States v. F. A. Baehner, Inc.
326 F.2d 556 (Second Circuit, 1964)
Triangle Erectors, Inc. v. James King & Son., Inc.
41 Misc. 2d 12 (New York Supreme Court, 1963)
Extruded Louver Corp. v. McNulty
18 A.D.2d 661 (Appellate Division of the Supreme Court of New York, 1962)
Hydrotherm, Inc. v. Insurance Co. of North America
31 Misc. 2d 534 (New York Supreme Court, 1961)
United States v. Thompson Construction Corp.
273 F.2d 873 (Second Circuit, 1959)
Dover Electric Supply Co. v. Leonard Pevar Co.
178 F. Supp. 834 (D. Delaware, 1959)
United States v. Thompson Construction Corp.
172 F. Supp. 161 (S.D. New York, 1959)

Cite This Page — Counsel Stack

Bluebook (online)
87 F. Supp. 1, 1949 U.S. Dist. LEXIS 1945, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-ex-rel-bruce-co-v-fraser-const-co-arwd-1949.