United States for the Use & Benefit of Davison v. York Electric Construction Co.

184 F. Supp. 520, 1960 U.S. Dist. LEXIS 4035
CourtDistrict Court, D. North Dakota
DecidedJune 15, 1960
DocketCiv. 249
StatusPublished
Cited by13 cases

This text of 184 F. Supp. 520 (United States for the Use & Benefit of Davison v. York Electric Construction Co.) is published on Counsel Stack Legal Research, covering District Court, D. North Dakota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States for the Use & Benefit of Davison v. York Electric Construction Co., 184 F. Supp. 520, 1960 U.S. Dist. LEXIS 4035 (D.N.D. 1960).

Opinion

REGISTER, Chief Judge.

This action was submitted for determination upon written statements of facts filed by the plaintiff and each of the answering defendants, Mountain States Construction Company and the American Surety Company of New York, together with the briefs of those parties. The defendant York Electric Construction Company, Inc., is in default.

This action is brought pursuant to the provisions of Section 270b, 40 U.S.C.A., *521 hereinafter referred to as the Miller Act, for balance on account of goods, wares and merchandise furnished and labor performed by the use plaintiff on the Minot, North Dakota, Air Force Base. The defendant Mountain States was a general contractor for electrical work under construction contract No. DA-25-066-Eng.-4942; defendant York Electric was a subcontractor to Mountain States; and defendant American Surety was surety on a standard government form of payment bond to the United States of America. The use plaintiff, a wholesale electrical supply dealer at Minot, North Dakota, furnished such property items and performed such labor, at the specific instance and request of the subcontractor, on open account. There is admittedly an unpaid balance therefore of $1,559.14, for which judgment is herein sought.

There is no written contract between the use plaintiff and either the prime contractor or subcontractor. The last of the materials furnished and labor performed by use plaintiff was on February 23, 1959; written notice thereof was sent by registered mail, as required by Section 270b of the Miller Act, to the prime contractor on June 15, 1959. Admittedly no written notice was served or mailed within the ninety-day period, as required by the Miller Act.

On June 7, 1958, the contractor (Mountain States) wrote a letter (Plaintiff’s Exhibit A) to the subcontractor, stating therein the procedure to be followed as between them. Under this procedure, copies of all purchase orders issued by York Electric were to be mailed to Mountain States; invoices approved by York Electric were to be sent to Mountain States; checks were to be made out to the vendor and to York Electric for dual signature; and Mountain States was to receive a copy of labor expenditures for the month and such expenditures were to be paid to York Electric upon receipt of partial payment estimates. A payment by Mountain States to payees York Electric and use plaintiff was made on March 26, 1959. The last billing for material to York Electric by use plaintiff was sent on February 23, 1959.

The answering defendants contend that they are entitled to a judgment of dismissal herein for the reason that use plaintiff failed to give written notice to the prime contractor within the ninety-day period prescribed by the Miller Act and that compliance with such statutory requirement is a condition precedent to use plaintiff’s right to recover against the answering defendants. |

The use plaintiff contends that; (1) it had a direct contractual relationship with the defendant Mountain States, and hence the provisions of the Miller Act with reference to the written notice are not applicable, and (2) that, as Mountain States at all times had full knowledge of the account, no notice was necessary, but if such notice were necessary the requirement has been fulfilled and complied with by the sending of invoices pursuant to the procedure established between the contractor and York Electric; that such invoices constituted sufficient and adequate notice; and that by having made a payment within the ninety-day period Mountain States admitted notice and knowledge of the facts, including amount of the account due.

As to use plaintiff’s first contention, great reliance is placed upon the fact that under the procedure established between the prime contractor and York Electric, the former received all invoices and payments were to be made by it to the vendor and to York Electric for dual signatures. In the Court’s opinion use plaintiff did not have a contractual relationship, express or implied with Mountain States.

It is interesting to note the relative similarity of this action and United States for Use of Bruce Co., Inc. v. Fraser Construction Co., Inc. et al., D.C., 87 F.Supp. 1, as to facts, issues and contentions of the parties. In the Bruce case, supra, the court discusses “implied contracts” at pages 5 and 6.

*522 “When the words ‘implied contract’ occur in a statute, the reference is to an actual contract inferred from the circumstances, conduct, acts or relations of the parties, showing a tacit understanding.” United States for Use of Bruce Co. v. Fraser Construction Co., supra.

A very thorough and interesting discussion concerning implied contracts appears in United States ex rel. Hargis v. Maryland Casualty Co. et al., D.C., 64 F.Supp. 522.

With reference to this contention, use plaintiff in his brief makes the assertion that under the agreement entered into between Mountain States and York Electric it (use plaintiff) became a third-party beneficiary. No argument is made in support of such assertion, nor is any authority cited. Section 9-0204, NDRC 1943, provides that “A contract made expressly for the benefit of a third person may be enforced by him at any time before the parties thereto rescind it”. In this Court’s opinion the agreement here involved is not such as is referred to in the quoted North Dakota statute.

In dealing with use plaintiff’s second contention, it should be noted that the Courts have uniformly held that the Miller Act is remedial in nature and is entitled to a liberal construction in order to effectuate the legislative intent. One very apparent purpose and intent was to protect those whose labor and materials go into public projects. An equally apparent purpose and intent of Congress was to fix a time limit after which the prime contractor could make payment to its subcontractors with certainty that he would not thereafter be faced with claims of those who had performed labor for and supplied materials to those subcontractors.

However, the statute itself makes the requirement of written notice from the supplier a condition precedent to a right of action on the bond; Congress specifically inserted this provision as a prerequisite to the cause of action.

“The requirement in the Miller Act for written notice to general contractor on a public work or building of any unpaid claim for materials or labor furnished to a subcontractor, as the foundation for a suit upon general contractor’s bond, was ‘mandatory’ and a strict ‘condition precedent’ to existence of any right of action upon contractor’s bond.” United States for Use and Benefit of American Radiator & Standard Sanitary Corp. v. Northwestern Engineering Co. et al., 8 Cir., 122 F.2d 600, 601, Headnote 2.

In the American Radiator case, supra, the court analyzed the decision in United States for Use and Benefit of Hallenbeck v. Fleisher Engineering & Construction Co., 2 Cir., 107 F.2d 925

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Chicago Rigging Co. v. Uniroyal Chemical Co., Inc.
718 F. Supp. 696 (N.D. Illinois, 1989)
Noland Co. v. Armco, Inc.
445 A.2d 1079 (Court of Special Appeals of Maryland, 1982)
UNITED STATES, ETC. v. PW Parker, Inc.
504 F. Supp. 1066 (D. Maryland, 1980)
Garff v. JR Bradley Company
436 P.2d 428 (Nevada Supreme Court, 1968)
State Ex Rel. Komac Paint & Wallpaper Store v. McBride
392 P.2d 577 (New Mexico Supreme Court, 1964)
California Electric Supply Co. v. United Pacific Life Insurance
227 Cal. App. 2d 138 (California Court of Appeal, 1964)
United States v. Van Riet
316 F.2d 912 (Fourth Circuit, 1963)
United States v. Van de Riet
316 F.2d 912 (Fourth Circuit, 1963)
Hydrotherm, Inc. v. Insurance Co. of North America
31 Misc. 2d 534 (New York Supreme Court, 1961)

Cite This Page — Counsel Stack

Bluebook (online)
184 F. Supp. 520, 1960 U.S. Dist. LEXIS 4035, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-for-the-use-benefit-of-davison-v-york-electric-ndd-1960.