United States Ex Rel. Excavation Construction, Inc. v. Glenn-Stewart-Pinckney Builders & Developers, Inc.

388 F. Supp. 289
CourtDistrict Court, D. Delaware
DecidedJanuary 20, 1975
DocketCiv. A. 4656
StatusPublished
Cited by15 cases

This text of 388 F. Supp. 289 (United States Ex Rel. Excavation Construction, Inc. v. Glenn-Stewart-Pinckney Builders & Developers, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Delaware primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States Ex Rel. Excavation Construction, Inc. v. Glenn-Stewart-Pinckney Builders & Developers, Inc., 388 F. Supp. 289 (D. Del. 1975).

Opinion

FINDINGS OF FACT, CONCLUSIONS OF LAW AND JUDGMENT

LATCHUM, Chief Judge.

This case was tried by the Court without a jury on December 16, 1974. After carefully considering and weighing the testimony of the witnesses 1 and the documentary evidence adduced at trial, the Court enters the following findings of fact, conclusions of law and judgment:

FINDINGS OF FACT

1. This action was brought under the Miller Act, 40 U.S.C. §§ 270a-270d, by the use plaintiff, Excavation Construction, Inc. (“Excavation”), seeking to recover $16,112 from the defendants Glenn-Stewart-Pinckney Builders and Developers, (“Glenn-Stewart”), Wisconsin Surety Corporation (“Wisconsin”), and Rural Mutual Insurance Company (“Rural”) on a payment bond furnished to the United States government by Glenn-Stewart and secured by Wisconsin and Rural for labor and materials allegedly furnished by Excavation to a subcontractor of Glenn-Stewart in the prosecution of work performed under a federal contract awarded to Glenn-Stewart by the Army Corps of Engineers.

2. The defendant Glenn-Stewart was general contractor for a federal project located near Reedy Point Bridge in this District. 2 (“Reedy Point project”).

3. As a condition precedent to the award of the federal contract for the Reedy Point project, 3 Glenn-Stewart furnished to the United States a payment bond secured by defendants Wisconsin and Rural “guaranteeing the payment of all persons supplying labor and materials in the prosecution of the work provided for in said [Reedy Point] project.” 4

4. Alex Feinman, Inc. (“Feinman”) was a subcontractor of defendant Glenn-Stewart for the Reedy Point project. 5

5. On June 1, 1972, Excavation orally contracted with subcontractor Feinman to rent Feinman two payhaulers with operators at a cost for each of $53.00 per hour and with a guaranteed minimum one month rental. This contract was confirmed in a letter from Excavation to Feinman dated June 2, 1972. 6

6. The payhaulers and operators were provided by Excavation to Feinman and were used by Feinman on the Reedy Point project for a total of approximately 16 hours for each payhauler and operator. 7

7. The payhaulers were found to be unsuited for the work required by the Reedy Point project and thus Feinman was ordered by Glenn-Stewart to remove *291 them from the project upon orders of the Corps of Engineers. 8

8. The last day that Excavation’s pay-haulers or operators performed work and labor at the Reedy Point project was June 29, 1972. 9

9. The payhaulers were returned to Excavation by July 28, 1972 and the bill for their return was paid by Glenn-Stewart. 10

10. Excavation billed Feinman on June 30, 1972 a total of $16,112 for the rental of the payhaulers and the use of the operators during the month of June, 1972. 11 The amount of the bill was based- on the guaranteed one month minimum rental and not on any actual use of the payhaulers and operators at the Reedy Point project. No additional bill for the payhaulers and operators was submitted by Excavation to Feinman.

11. The $16,112 June 30 bill to Feinman was never paid. 12

12. Patricia Mallory (“Mallory”) was general agent for the defendant Glenn-Stewart handling all contractual matters pertaining to the Reedy Point project. As such, she had the responsibility of handling all of Glenn-Stewart’s office and paper work involving the Reedy Point project including pricing and estimating the job and paying subcontractors. She worked out of Glenn-Stewart’s offices.

13. Homer N. Garner (“Garner”) was purchasing agent for Excavation during the summer of 1972.

14. Several telephone conversations took place between Mallory and Garner during late June and July 1972 concerning the payhaulers. In one such conversation Garner indicated that Feinman had. the responsibility for returning the payhaulers to Excavation and Mallory assured Garner that Glenn-Stewart would pick up the bill for the return of the pay-haulers to Excavation. 13

15. In a later July 1972 telephone conversation between Mallory and Garner the topic of the $16,112 bill for the rental of the payhaulers and operators was discussed. With regard to this conversation, Garner testified that:

a) he told Mallory that the $16,112 bill had not been paid by Feinman;
*292 b) the $16,112 was owed and due to Excavation;
c) Excavation expected to be paid;
d) Mallory told him that Glenn-Stewart would assume responsibility for the bill;
e) Mallory requested a copy of the bill be sent to her; and
f) she requested that a copy or written explanation of Excavation’s contract with Feinman be sent to her.

16. With regard to this same conversation, Mallory testified that:

a) Garner probably told her that $16,122 was due to Excavation from Feinman;
b) Garner told her Excavation was having difficulty contacting Feinman;
c) she told Garner that she wanted information concerning the ExcavationFeinman contract including a copy of the purchase order, a copy of the bill and all the particulars relating to the bill;
d) Garner told her he would send the above requested information to her;
e) Garner never indicated that Excavation was looking to Glenn-Stewart for payment of the bill; and
f) she never indicated that Glenn-Stewart would be responsible for the bill because she had no specific knowledge of Excavation’s and Feinman’s arrangement with respect to the payhaulers.

17. Garner further testified that after this conversation with Mallory he asked Edward W. Storke (“Storke”), Excavation’s Comptroller, to send a copy of the Feinman bill to Glenn-Stewart since he had no secretary at that time to do it himself. Garner thereafter suffered a disabling heart attack and did not resume his duties at Excavation until the following year.

18. Storke testified that Garner requested him in late July 1972 to send a copy of the Feinman bill to Glenn-Stewart. Storke put the request on his “to do” list.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pepper Burns Insulation, Inc. v. Artco Corp.
970 F.2d 1340 (Fourth Circuit, 1992)
Pi-Con, Inc. v. a J Anderson Construction Co.
458 N.W.2d 639 (Michigan Supreme Court, 1990)
United States v. Mortenson Company
894 F.2d 311 (Eighth Circuit, 1990)
Lezzer Cash & Carry, Inc. v. Aetna Insurance
537 A.2d 857 (Supreme Court of Pennsylvania, 1988)
UNITED STATES, ETC. v. PW Parker, Inc.
504 F. Supp. 1066 (D. Maryland, 1980)
Eastern Insulating Glass Co. v. Raymon R. Heddon & Co.
21 Pa. D. & C.3d 611 (Lackawanna County Court of Common Pleas, 1980)
United States v. E.J.T. Construction Co.
453 F. Supp. 435 (D. Delaware, 1978)
UNITED STATES, ETC. v. EJT Const. Co., Inc.
453 F. Supp. 435 (D. Delaware, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
388 F. Supp. 289, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-ex-rel-excavation-construction-inc-v-ded-1975.