Bowden v. United States

239 F.2d 572
CourtCourt of Appeals for the Ninth Circuit
DecidedDecember 31, 1956
DocketNo. 14658
StatusPublished
Cited by29 cases

This text of 239 F.2d 572 (Bowden v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bowden v. United States, 239 F.2d 572 (9th Cir. 1956).

Opinion

WALSH, District Judge.

In September, 1951 the United States entered into a contract with appellant Twaits-Morrison-Knudsen-Macco, a joint venture,1 (hereinafter the “prime contractor”), whereby the latter was to furnish the materials and perform the work for constructing launching facilities, utilities, and roads at the Navy Air Missile Test Center, Point Mugu, California. The initial contract amount, before change orders, was $3,661,000.00 and the prime contractor furnished a payment bond, with appellant Fidelity & Deposit Company of Maryland as one of the sureties thereon, in the sum of $1,464,400.00.2 Under a subcontract, Frank T. Hickey, Inc., (hereinafter “Hickey”), performed a part of the work required of the prime' contractor under its contract with the United States, i. e., grading, excavation, and filling. In doing such work, Hickey used earth moving and excavating equipment which it rented from appellee Mal-loy. Hickey began work on the Point Mugu job in September, 1951, and used Malloy’s equipment from a date soon thereafter and until a very few days before the work under the subcontract was. completed on October 31, 1952.

Hickey’s arrangement with Malloy provided that payment of rental for the-equipment would be made to Malloy thirty days after receipt of monthly invoices therefor. However, such payment program was never actually complied with. By the spring of 1952, Hickey was substantially delinquent in its payments, and the situation worsened'. [574]*574during the summer months. Throughout the period, Malloy was making efforts to collect the payments which were delinquent and, in this connection, Malloy made numerous contacts with representatives of the prime contractor. These representatives assured Malloy that the prime contractor was interested in seeing that Hickey paid its bills incurred in the subcontract work and that they would do what they could to see that Hickey made payment to Malloy. On one occasion, in the summer of 1952, when it was threatened that Malloy’s equipment might be removed from the Point Mugu job because of Hickey’s delinquency, the prime contractor’s agents asked that this action be not taken, stating that Hickey had enough funds then due it under its subcontract to enable it to pay all the bills incurred by it on the Point Mugu job which the prime contractor’s agents then knew to be outstanding. The agents stated, also, that they did not propose to pay Hickey any money which they were not sure would be applied upon its indebtedness for work done under the subcontract.

In December, 1952, after the subcontract was completed, the prime contractor owed Hickey approximately $17,000.-00 3 in retentions under the subcontract, At a meeting then held between the prime contractor’s representatives and Hickey, the- latter requested that the prime contractor make the retained amount available to creditors of Hickey whose claims arose out of the Point Mugu work. An understanding was arrived at in the meeting whereby, out of the retained fund, all Hickey’s Point Mugu creditors whose claims were less than $1,000.00 would receive payment in full and those whose claims exceeded $1,000.00 would receive 50 per cent of their bills, checks for the payments to be drawn by the prime contractor payable to the joint order of Hickey and its respective Point Mugu creditors. As a result of the meeting, and on December 12, 1952, Hickey wrote the prime contractor a letter listing its Point Mugu creditors, including Malloy, and authorizing the prime contractor to issue checks payable to the joint payees and for the amounts agreed upon in the meeting.4

[575]*575On December 15, 1952, the prime contractor issued the cheeks as requested and delivered them to Hickey. On December 29, 1952, Hickey endorsed the prime contractor’s check in the amount of $5,895.55 to Malloy and mailed it to him with a letter concerning the balance which Hickey believed would remain due to Malloy after the cheek was credited and with a letter form receipt which Hickey requested Malloy to sign and return. After modifying the form of the receipt, Malloy executed it and returned it to Hickey.

Hickey’s financial condition continued to deteriorate until it filed a voluntary petition in bankruptcy and was adjudicated a bankrupt on July 30, 1953.

In the performance of the subcontract, Hickey had encountered an adverse soil condition at Point Mugu which caused it to do considerable extra work and to incur considerable extra expense. In view of this, the prime contractor on Hickey’s behalf made a “subsidence” claim against the United States, which claim was allowed in December, 1953, or in January, 1954, in the amount of $29,120.00. Payment of this sum was made by the United States to the prime contractor on March 25, 1954, and the prime contractor, after deducting certain overhead charges, credited Hickey’s account on its books with $27,260.00. At that time, the prime contractor owed Hickey additionally the sum of $2,298.95 for work performed at Point Mugu, so that the total credit balance in Hickey’s account on the books of the prime contractor stood at $29,-558.95.

To this fund of $29,558.95, claim was made by both appellant Leslie S. Bowden, the trustee in bankruptcy for Hickey’s estate, and Ford J. Twaits Co., a partnership, the claim of the latter being that Hickey was indebted to it in an amount probably exceeding $58,000.00 for costs incurred on behalf of Hickey in connection with public works contracts at Saugus, California, and Santa Ana County, California.5 On February 18, 1954, the trustee filed in the Hickey bankruptcy proceedings a petition for leave to settle his dispute with Ford J. Twaits Co. over the fund in the hands of the prime contractor on a basis whereby the trustee would accept and receive $19,705.97 of the fund in settlement of all his claims against the prime contractor and the balance of the fund would be paid to Ford J. Twaits Co. An order approving the proposed compromise was made by the referee in bankruptcy on March 30, 1954. The order directed that the $19,705.97 compromise sum would be subject in the hands of the trustee to any claims which might have been proved against it had it remained in the possession of the prime contractor and subject, also, to any claims which might be proved against the prime contractor under the Miller Act6 by suppliers to Hickey of labor and materials on the Point Mugu job.

On February 23, 1954, the present action was instituted by Malloy in the district court against all of the appellants other than Trustee Bowden. The complaint sought recovery on the payment bond under the Miller Act of $6,027.45, with interest, Malloy alleging that he had direct contractual relationship with both Hickey and the prime contractor. The complaint asked, also, that an equitable lien to secure payment of Malloy’s claim be impressed upon the proceeds of the “subsidence” claim then in the hands of the prime contractor. Malloy moved in the district court on April 9, 1954, for a preliminary injunction enjoining the prime contractor and its surety, pending final determination of Malloy’s action, from paying to the trustee in bankruptcy, or any other person, any funds in their possession belonging to Hickey for work done by it at Point Mugu, unless the parties enjoined should retain $6,-789.42 of the funds subject to the order of the district court. Immediately following presentation of Malloy’s motion, [576]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Maccaferri Gabions, Inc. v. Dynateria Inc.
91 F.3d 1431 (Third Circuit, 1996)
MacCaferri Gabions, Inc. v. Dynateria Inc.
91 F.3d 1431 (Eleventh Circuit, 1996)
United States v. Sun Engineering Enterprises, Inc.
817 F. Supp. 1009 (D. Puerto Rico, 1993)
Greaig v. Park West Construction Co.
637 P.2d 1079 (Court of Appeals of Arizona, 1981)
United States v. White Contracting Company
649 F.2d 29 (First Circuit, 1981)
Consolidated Concrete Co. v. Empire West Construction Co.
596 P.2d 106 (Idaho Supreme Court, 1979)
Western Asbestos Co. v. TGK Const. Co., Inc.
590 P.2d 927 (Arizona Supreme Court, 1979)
Westinghouse Electric Corp. v. Minnix
269 A.2d 580 (Court of Appeals of Maryland, 1970)
California Electric Supply Co. v. United Pacific Life Insurance
227 Cal. App. 2d 138 (California Court of Appeal, 1964)
United States v. Baehner, Inc.
326 F.2d 556 (Second Circuit, 1964)
United States v. F. A. Baehner, Inc.
326 F.2d 556 (Second Circuit, 1964)
Triangle Erectors, Inc. v. James King & Son., Inc.
41 Misc. 2d 12 (New York Supreme Court, 1963)
United States v. Van Riet
316 F.2d 912 (Fourth Circuit, 1963)
United States v. Van de Riet
316 F.2d 912 (Fourth Circuit, 1963)

Cite This Page — Counsel Stack

Bluebook (online)
239 F.2d 572, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bowden-v-united-states-ca9-1956.