Triangle Erectors, Inc. v. James King & Son., Inc.

41 Misc. 2d 12, 244 N.Y.S.2d 433, 1963 N.Y. Misc. LEXIS 1607
CourtNew York Supreme Court
DecidedSeptember 25, 1963
StatusPublished
Cited by3 cases

This text of 41 Misc. 2d 12 (Triangle Erectors, Inc. v. James King & Son., Inc.) is published on Counsel Stack Legal Research, covering New York Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Triangle Erectors, Inc. v. James King & Son., Inc., 41 Misc. 2d 12, 244 N.Y.S.2d 433, 1963 N.Y. Misc. LEXIS 1607 (N.Y. Super. Ct. 1963).

Opinion

John P. Cohalan, Jr., J.

This action was originally instituted by Triangle Erectors, Inc. to foreclose a mechanics’ lien and for payment of the amount of the lien. The claims of plaintiff Triangle and all of the materialmen and subcontractors were disposed of by settlement prior to or upon the trial, except for the claims of the defendants, Minneapolis-Honeywell Regulator Company, John J. Nesbitt, Inc. and I. Burack, Inc. Disposition of the claims of the said defendants are the subject of this determination.

The principal issue presented is whether written notice was given pursuant to the provision of the payment bond issued by the defendant, Continental Casualty Company, as a condition precedent to the institution of the action. The proof shows that defendant, James King & Son, Inc., hereinafter referred to as King, on February 26,1960 entered into a contract with defendant, Huntington Hospital Association for additions and alterations to the Huntington Hospital Project, N. Y. S. 190. The contract price was $1,782,331. Substantial funds for this improvement were provided by a Federal agency which required the hospital to obtain a surety company payment bond from the contractor for the payment of materials and labor supplied to the job. The bond in the full amount of the contract is dated July 16, 1960, Bond No. 2,203,458, and was issued by the Con[14]*14tinental Casualty Company to James King & Son, Inc. as principal and Huntington Hospital Association, Huntington, New York, as obligee. The bond provides in substance that if the principal King promptly makes payment to all claimants for labor and material used or reasonably required for use in the performance of the contract, then the obligation shall be void. Otherwise it is provided in the bond that the same shall remain in full force and effect, subject to specific conditions.

The bond does not include the payment of any costs or expenses of any suit, but does specify that claims for labor and material used in the performance of the contract and which have not been paid for a period of 90 days may be the subject of suit.

The bond then specifies: “no suit or action shall be commenced hereunder by any claimant:

(a) Unless claimant shall have given written notice to any two of the following: The Principal, the Owner, or the Surety above named, within ninety (90) days after such claimant did or performed the last of the work or labor, or furnished the last of the materials for which said claim is made, stating with substantial accuracy the amount claimed and the name of the party to whom the materials were furnished, or for whom the work or labor was done or performed. Such notice shall be served by mailing the same by registered mail, postage prepaid, in an envelope addressed to the Principal, Owner or Surety, at any place where an office is regularly maintained for the transaction of business, or served in any manner in which legal process may be served in the state in which the aforesaid project is located, save that such service need not be made by a public officer.
“ (b) After the expiration of one (1) year following the date on which principal ceased work on said Contract.”

The claims of defendants, Minneapolis-Honeywell Regulator Company, referred to as Minneapolis, John J. Nesbitt, Inc., referred to as Nesbitt and I. Burack, Inc., referred to as Burack, arise from the following circumstances:

King entered into a subcontract with the defendant Taggart Corporation, hereinafter referred to as Taggart, for the heating, ventilating and air conditioning portion of the work for the hospital. Taggart was to be paid $193,400 for the work and material. Taggart in turn purchased and caused to be delivered to the job materials and labor from the defendants, Minneapolis, Nesbitt and Burack. It is undisputed that all of these items were necessary to complete Taggart’s contract with King. Sometime in March of 1961 the defendant Taggart filed a voluntary petition under chapter 11 of the Bankruptcy Act (U. S. [15]*15Code, tit. 11, § 701 et seq.) and defaulted in the performance of its contract with King. The general contractor King thereupon contracted with another for the completion of the Taggart part of the job and agreed to pay upon a cost plus basis therefor.

The record evidences the fact that the Taggart job was completed and the new subcontractor was paid approximately $53,000 for labor and materials to complete the job. The hospital owed to King in all in May of 1961 approximately $138,500, plus retained funds of $59,000. When Taggart defaulted the defendants, Minneapolis, Nesbitt and Burack, along with other materialmen and subcontractors sought payment for the money owing to them for labor and materials supplied to the job. Defendant Minneapolis supplied work and material referred to as a pneumatic system of automatic temperature control, in the sum of $18,850. The last date upon which Minneapolis supplied any material for the job was March 2, 1961 and the last date it supplied work to the job was April 25, 1961. In April of 1961 there was $8,061.90 and interest owing to Minneapolis for labor and materials supplied by it to the job. The mechanics5 lien was filed in the Suffolk County Clerk’s office on May 12, 1961 and was served and received by general contractor King and hospital owner on May 16, 1961. Written requests for payment were made by Minneapolis to the Continental Casualty Company upon the bond in December, 1961. No payments were made. There is owing to Minneapolis a balance of $8,061.90 with interest from April 21, 1961. The lien of Minneapolis was discharged upon the filing of an undertaking pursuant to an order of this court dated December 6,1961 and which undertaking also included the lien of defendant Burack.

Defendant Nesbitt furnished ventilators in connection therewith and delivered the same to the job on or before December 21, 1960. Nesbitt billed Taggart for that item as of December 21, 1960. However, thereafter upon the written request of Taggart’s employee, Nesbitt delivered additional material to the job, to wit, one carton of felt pads to be used with the ventilators. These were delivered on January 19, 1961. The notice of lien, verified April 20, 1961, says that the last work and the last materials furnished to the job was December 21,1960. No additional sums were billed to the job by Nesbitt after the date of December 21, 1960 and the pads were noted as “no charge.55 There is ample proof to establish the delivery to the job of the felt pads on January 19, 1961 by Nesbitt at the request of the subcontractor, Taggart. There is no evidence to support a conclusion that such delivery of material by Nesbitt was merely intended to extend the time within which Nesbitt could give [16]*16notice of its claim. Nesbitt did not know in January, 1961 that Taggart was involved financially and could not complete its contract with King. No question about payment was presented until April, 1961.

The proof does support the claim of the defendant Nesbitt that the last delivery of materials made by it to the job was on January 19, 1961. The record also shows that there is owing to Nesbitt for work and materials supplied to the job the sum of $5,207 with interest and that no part thereof has been paid.

Defendant Burack furnished pipes, valves and miscellaneous material to the job and the last of the items so furnished were delivered on January 18, 1961. The materials so delivered are of a value of $1,276.53 and no part thereof has been paid and such claim is owing with interest.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lynbrook Glass & Architectural Metals Corp. v. Elite Associates, Inc.
215 A.D.2d 453 (Appellate Division of the Supreme Court of New York, 1995)
HNC Realty Co. v. Bay View Towers Apartments, Inc.
92 Misc. 2d 151 (New York Supreme Court, 1977)

Cite This Page — Counsel Stack

Bluebook (online)
41 Misc. 2d 12, 244 N.Y.S.2d 433, 1963 N.Y. Misc. LEXIS 1607, Counsel Stack Legal Research, https://law.counselstack.com/opinion/triangle-erectors-inc-v-james-king-son-inc-nysupct-1963.