United States Ex Rel. Hargis v. Maryland Casualty Co.

64 F. Supp. 522, 1946 U.S. Dist. LEXIS 2785
CourtDistrict Court, S.D. California
DecidedFebruary 21, 1946
Docket4589
StatusPublished
Cited by28 cases

This text of 64 F. Supp. 522 (United States Ex Rel. Hargis v. Maryland Casualty Co.) is published on Counsel Stack Legal Research, covering District Court, S.D. California primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States Ex Rel. Hargis v. Maryland Casualty Co., 64 F. Supp. 522, 1946 U.S. Dist. LEXIS 2785 (S.D. Cal. 1946).

Opinion

*523 YANKWICH, District Judge.

On September 21, 1943, M. J. Ruddy, Sr., and M. J. Ruddy, Jr., comprising the partnership of Ruddy and Son, entered into a contract with the United States of America for performing certain public works, namely, air field facilities at the Materials Test Base, Muroc, California. The contract which was duly executed by the contracting parties, bears the designation and number of W-509 eng 5584.

The contractor executed a bond under the provisions of 40 U.S.C.A. § 270a— known as the Miller Act — with themselves as principals and the defendant Maryland Casualty Company, a Maryland corporation, as surety. In the performance of this contract, the contractor employed M. E. Whitney as a subcontractor to do a certain portion of the work. Whitney earned $67,-769.87. The contractor, before the completion of the work and according to the provisions of the contract to be referred to, paid to or expended for Whitney the sum of $60,878.73. This left a balance of $6791.14 in the hands of the contractor. As against this sum, the unpaid claims of Whitney’s creditors amounted to $14,-681.44.

Elmer S. Hargis, the use plaintiff, rented to Whitney a tractor and equipment which was used in the performance of his subcontract. The Agreed Statement of Facts states that the rental value is the sum of $1710.00, against which there is a set-off of $71.85, leaving a balance of $1638.15. This is the maximum amount of liability of the defendants, if any liability exists.

The contract between the contractor and the subcontractor contained the following provisions:

“Subcontractor agrees specifically to perform the following designated work: Furnish and place 16,700 sq. yds. of 9 inch concrete pavement, furnish and deliver to job site 143 cu. yds. (more or less) concrete mix, all above items to be in accordance with Government specifications and measures as outlined in contractor’s prime contract with the Government.
“Payment and Acceptance of Said Work. The total price to be paid subcontractor for said work shall be the unit price of $3.90 per sq. yd., and $12.00 per cu. yd. payable in lawful money of the United States of America, which shall be paid as follows: Contractor agrees to pay all accrued material, freight, equipment rental and transportation charges, payrolls and incidental charges to be deducted from final settlement of total amount due under this contract, provided, however, that 10% of said total contract price shall not be due and payable until 35 days after the actual completion of contractor’s contract, and acceptance thereof by the owners or their agents. And it is further agreed that the unit price of 380 ft. of double conduit shall cost $1.05 per ft., also that the contractor shall add to the amount of the total weekly gross payroll 6.685 per $100,00 to cover accrued workmen’s compensation insurance, social security taxes and deductions, plus 5% handling and bookkeeping charges, also that the final payment shall not become due until 35 days after the actual completion of contractor’s contract, and acceptance thereof by the owners or their agents.”

The following facts are also stipulated in conjunction with the clause just quoted, which are contained in Paragraph IV of the Stipulation.

“Ruddy and Son, did in fact, pay directly for all labor upon the job carried on said Whitney’s payroll, and did pay for all other materials and other services rendered to said Whitney in connection with said job, insofar as any payment was made. It was the custom and the practice of Whitney to present the bills of his suppliers to M. J. Ruddy for his approval. On or about the 15th day of February, 1944, the subcontractor wrote to the plaintiff stating the gross amount of plaintiff’s bill in the sum of $1710.00, which was the total of the amount of bills that had been submitted to the plaintiff by Whitney up to February 15, of 1944. The subcontractor Whitney made a charge against Hargis in the sum of $71.85 for certain oils, greases, and service to the tractor, and claimed that the net balance due to Hargis was $1,638.15.”

The Agreed Statement of Facts contains the following reservations:

“That by entering into this stipulation, the defendants do not concede the materiality of the matters set forth in paragraphs 4, 8, 9, 10 and 15 hereof, but contend that said matters are immaterial and irrelevant and should not be considered'by the Court.
“That the matters set forth in paragraph 4 hereof are included only for the *524 purpose of explaining the procedure followed by M. J. Ruddy and Son in making payment for the benefit of the subcontractor, M. E. Whitney, and for no other purpose.”

In view of this reservation, it is necessary to set forth the paragraphs so numbered other than Paragraph IV, which has already been reproduced. They read:

“VIII. That plaintiff also received a carbon copy of a letter, dated May 4, 1944, on the letterhead of M. J. Ruddy and Son, addressed to Herman E. Weigis and the Fidelity and Casualty Company of New York, containing a notation at the bottom: ‘cc: Copy to Mr. Whitney’s creditors on Job No. 5584.’
“IX. That plaintiff received a letter, on the letterhead of M. J. Ruddy and Son, addressed to M. E. Whitney, dated May 9, 1944, signed by Aubrey H. Y’Blood, Office Manager, containing a notation at the bottom ‘cc: Elmer Hargis, .130 West Foothill Blvd., Monrovia, California,’ in which he stated that the invoice of Hargis, dated April 1, 1944, in the amount of $2281.00 was transmitted to M. E. Whitney and asked for Whitney’s approval to pay.
“X. That under date of May 9th another letter was sent from M. J. Ruddy and Son to the plaintiff requesting plaintiff’s approval as to the charge contained in the letter of M. E. Whitney to the plaintiff herein, dated February 15, 1944.”
“XV. That one Mr. Moore, who was the Superintendent for M. J. Ruddy and Son on the Muroc Job, had knowledge that the tractor was working on the job, and also knew the agreed rate that was to be charged for said equipment.”

The three invoices attached to the complaint and the letter of May 9, 1944, addressed to Whitney, another letter dated May 18, 1944, and the telegram of March 30, 1944, are also reproduced in full.

*525

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Archer v. Rockingham County
548 S.E.2d 788 (Court of Appeals of North Carolina, 2001)
Chicago Rigging Co. v. Uniroyal Chemical Co., Inc.
718 F. Supp. 696 (N.D. Illinois, 1989)
US, METAL MFG., INC. v. Federal Ins. Co.
656 F. Supp. 1194 (D. Arizona, 1987)
Noland Co. v. Armco, Inc.
445 A.2d 1079 (Court of Special Appeals of Maryland, 1982)
UNITED STATES, ETC. v. PW Parker, Inc.
504 F. Supp. 1066 (D. Maryland, 1980)
United States v. Lee A. Limbs, Jr.
524 F.2d 799 (Ninth Circuit, 1975)
United States v. Limbs
356 F. Supp. 1004 (D. Arizona, 1973)
Fidelity & Deposit Co. v. Harris
360 F.2d 402 (Ninth Circuit, 1966)
State Ex Rel. Komac Paint & Wallpaper Store v. McBride
392 P.2d 577 (New Mexico Supreme Court, 1964)
Triangle Erectors, Inc. v. James King & Son., Inc.
41 Misc. 2d 12 (New York Supreme Court, 1963)
McWaters & Bartlett v. United States
272 F.2d 291 (Tenth Circuit, 1959)

Cite This Page — Counsel Stack

Bluebook (online)
64 F. Supp. 522, 1946 U.S. Dist. LEXIS 2785, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-ex-rel-hargis-v-maryland-casualty-co-casd-1946.