United States ex rel. Korosh v. Otis Williams & Co.

30 F. Supp. 590, 1939 U.S. Dist. LEXIS 1834
CourtDistrict Court, D. Idaho
DecidedDecember 9, 1939
DocketNos. 1076, 1078
StatusPublished
Cited by16 cases

This text of 30 F. Supp. 590 (United States ex rel. Korosh v. Otis Williams & Co.) is published on Counsel Stack Legal Research, covering District Court, D. Idaho primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States ex rel. Korosh v. Otis Williams & Co., 30 F. Supp. 590, 1939 U.S. Dist. LEXIS 1834 (D. Idaho 1939).

Opinion

CAVANAH, District Judge.

These two cases were consolidated for trial and will be considered and disposed of in this opinion as they involve a consideration of practically • the same questions of law.

Case 1076.

The plaintiff seeks to recover $4,220.10 on its first cause of action and $205.80 on its second cause of ¡action in which it assert that as a partnership they furnished material, labor and supplies for the prosecution of the work required by a certain contract entered into between the United States and Otis Williams Company et al., on the 14th day of July 1936, in the' construction of a diversion dam and canal headworks, earth-work and canal lining and structures for the cross-cut canal as covered by schedules 1 and 2 of specifications-683 on the Upper Snake River project in Idaho; that the defendants Williams Company and Sturgill and Company as principals and the defendant Surety Company as surety executed and delivered to the United States a payment bond in the penal sum of $62,365.37 by the ■ terms of which they bound themselves for the payment of all labor and materials used in the construction of the work and that full payment for the same has not been made; that prior to April 1, 1937 defendant Nelson entered into a subcontract with Williams Company and Sturgill and Company for completing a part of the work required by the original contract and on April 1, 1937 employed plaintiff to furnish all necessary labor and do all necessary drilling and blasting of all of the solid rock in the construction of the canal between station 2-48.7 and station 350, excepting the work theretofore done between station 121-50 and 171-17.72, in the manner required by the original contract, and to furnish plaintiff compressors, jack-hammers, drill steel, use of trucks etc., without charge, and' that plaintiff would be at the expense of all drill steel, gas,- oil, grease and explosives at cost price to-Nelson, and Indus[592]*592trial Insurance, State Employment Compensation, Federal Old Age Pension, as might be required and for such services, plaintiff was to receive 47 cents per cubic yard of solid rock removed, and that Nelson would pay to the plaintiff 90 per cent' of all sums earned by it in accordance with the monthly estimates of the quantities of work performed, less any ledger account which Nelson may have against the plaintiff for drill steel, gas,- oil, grease, explosives, labor, Industrial Insurance, State Employment Compensation; Old Age Pensions, advances etc., retaining 10 per cent of the money so earned by the plaintiff until the work was finished; that immediately following April 1, 1937, the plaintiff commenced work and prosecuted it to the end, and it was finished about December 6, 1937; that the plaintiff drilled, blasted and removed 51,831 cubic yards of rock and for which they were entitled to receive $24,360.54; that Nelson furnished to plaintiff sundry items of materials etc., which were charged against plaintiff, amounting to $12,446.31 and that there was paid to it on account of work $7,694.-16 leaving a balance claimed to be due plaintiff of $4,220.10; that of the $7,694.16 so paid, Williams Company paid $2,000; that in the month of November 1937, when the work was only partially performed, plaintiff became alarmed at the conduct of Nelson and threatened to discontinue work and the defendants Williams Company and Sturgill and Company requested plaintiff to continue the work and finish the same; that to evidence a portion of the amount then due, Nelson gave a promissory note for $1,767.64 due December 20, 1937, and which was not paid; that within 90 days following the date upon which the last of the work was performed, the original contractor knew the amount claimed by the plaintiff and details of the obligation, and that within 90 days after the material and labor had been furnished the plaintiff made demand for payment.

In the second cause of action plaintiff asserts that during July, August, September and October 1937, at the request of Williams Company, one of the original contractors, plaintiff performed work consisting of drilling and blasting, and apart from the work claimed in their first cause of action, of a balance of $205.80 which they allege has not been paid.

The defendant Williams Company and the defendant United States Fidelity & Guaranty Company are the defendants who answer the complaint and they deny that the plaintiff is entitled to recover and present several affirmative defenses which require the consideration of the sufficiency of the complaint and evidence when in disposing of them. These defenses appear to be:

(a) That the complaint fails to state a claim against defendants upon which relief can be granted. The answer to this defense must be in the negative as it is thought that the allegations of the complaint state facts sufficient to require a denial of that defense.

(b) That the right of action which plaintiff attempts to set forth was commenced after the expiration of one year after the date of final settlement of the contract pleaded, and they rely upon section 270b and 270c of Title 40 U.S.C.A. The plaintiff contends that the date of final settlement was March 1, 1938, while defendants assert that it was on January 24, 1938. Suit was commenced February 27, 1939. The Comptroller General fixed March 1, 1938 as the date of final settlement. This issue presents the statute of limitations and the constitutionality of a part of the statute. The defendants contend that the cause of action is barred, as more than one year has lapsed since the final settlement was made. This statute in question provides:

“Every suit instituted under this section shall be brought in the name of the United States for the use of the person suing, in the United States District Court for any district in which the contract was to be performed and executed and not elsewhere, irrespective of the amount in controversy in such suit, but no such suit shall be commenced after the expiration of one year after the date of final settlement of such contract. * * * ”

“The Comptroller General is authorized and directed to furnish, to any person making application therefor who submits an affidavit that he has supplied labor or materials for such work and payment therefor has not been made or that he is being sued on any such bond, a certified copy of such bond and the contract for which it was given, which copy shall be prima facie evidence of the contents, execution, and delivery of the original, and, in case final settlement of such contract has been made, a certified statement of the date of such settlement, which, shall [593]*593be conclusive as to such date upon the parties. Applicants shall pay for such certified copies and certified statements such fees as the Comptroller General fixes to cover the cost of preparation thereof.”

It appears without any substantial contradiction in the evidence that the final settlement was on March 1, 1938 as determined by the Comptroller General, but defendants urge that the statute authorizing the Comptroller General to determine the date of final settlement is unconstitutional as it contravenes the 5th Amendment of the Constitution, U.S.C.A., depriving them of a property right without due process of law.

It will be remembered that when we come to consider the contract in question and the statute referred to under which it is made, it gives to the Comptroller General authority to determine the date of final settlement of a contract, and the parties thereto have agreed that such authority to determine the date of final settlement would be vested in the Comptroller General.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
30 F. Supp. 590, 1939 U.S. Dist. LEXIS 1834, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-ex-rel-korosh-v-otis-williams-co-idd-1939.