English Const. Co. v. United States

29 F. Supp. 526, 1939 U.S. Dist. LEXIS 2358
CourtDistrict Court, D. Delaware
DecidedSeptember 15, 1939
DocketNo. 7
StatusPublished
Cited by5 cases

This text of 29 F. Supp. 526 (English Const. Co. v. United States) is published on Counsel Stack Legal Research, covering District Court, D. Delaware primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
English Const. Co. v. United States, 29 F. Supp. 526, 1939 U.S. Dist. LEXIS 2358 (D. Del. 1939).

Opinion

NIELDS, District Judge.

September 25, 1928, a contract was made between the English Construction Company, Inc., plaintiff, and United States of America, defendant, known as contract “NOy-416” (Specification No. 5635) for repairs to boiler house at the Naval Academy (Engineering Experimental Station), Annapolis, Maryland. Plaintiff agreed to make repairs and defendant agreed to pay therefor-$18,497.

Plaintiff’s vice president and the manager of its Washington office was Dennis E. Cqnners. He was present during the performance of the contract. He testified that he was “a bricklayer by trade and I worked up to general contractor and superintendent”, and that he or his company, plaintiff, had been in the construction business about fifty years; that he had been engaged in the erection of post offices, court houses, public schools and armories at various places throughout the United States. During the protracted performance of the work there were numerous occasions of irritation which provoked charges and countercharges. It would be unprofitable to dwell upon these disputes. Suffice it to say, the controversy in this case does not relate to the quality of the completed work but only to claims of plaintiff for extra work and labor. The boiler house at the Naval Academy known as the Engineering Experimental Station had been partially destroyed by an explosion. The contract in suit covered the ••-epairs required to restore this boiler house. The issue in the case mainly concerns additional work and materials or extras furnished by plaintiff. The principal question is whether the allowances made for such extras were sufficient and whether the time allowed was adequate.

The claims set forth i-n plaintiff’s complaint fall into four groups:

First. A group of three claims abandoned by plaintiff.

Second. A group of three claims where no government change-order was given and no decision by the “Board” was made. The determination of the merit of these claims involves only questions of law.

Third. A group of three claims where change-orders were given and where the allowance made by defendant for the changes, both as to the amount of money and the time allowed, are alleged to be insufficient.

Fourth. A claim for recovery of the amount alleged to have been illegally deducted as liquidated damages for delay in the completion of the contract.

These groups will be considered in their order.

First. In the seventh paragraph of the complaint plaintiff sets forth a bill of particulars of the extra and additional work performed and the reasonable value thereof. During the trial certain claims of plaintiff were abandoned. Item (b) is extra building of additional water table $30.25. Item (c) is extra labor and materials for additional roofing $127.05. Claims based on these items were abandoned by plaintiff. In paragraphs nine and ten of the complaint plaintiff claims damages in the amount of $1,000 on account of hindrance, obstruction, interference and delay on the part of the defendant. This claim was also abandoned.

Group second includes items (a), (f) and (h) of the bill of particulars.

(a) Extra painting of steel deck $1,026.08

(f) Unauthorized deduction for removal of airtight compartment and superheater....... 135.50

(h) Extra cost of additional lathing and plastering.......... 1,983.50

Respecting the above items it may be said generally, (a) depends upon the correct interpretation of the contract; (f) is •purely a question of law; and (h) depends upon the interpretation of a blueprint or a drawing which is part of the contract. With respect to these items no ruling of defendant could be final. Decision rests with the court.

(a) The first item in the bill of particulars is “(a) Extra Painting of steel deck $1,026.08”. This claim hinges upon the interpretation of the specifications of the contract.

“Section 6. Roofing and Sheet Metal Work”. 6-02 (a) provides: “Sheet steel * * * shall be * * * black, painted, or galvanized * * *. Black steel [528]*528shall be given a shop priming coat of red lead paint”.

“Section 9, Painting. 9-01 General requirements. The work includes cleaning and painting all new and existing structural steel work and steel windows and the under sides of steel roof decks if black .steel sheets, red lead primed, are used.”

“9-03. Painting. * * * All work shall be painted two coats (in addition to the shop or priming coat) of white lead zinc oxide paint colored as directed.”

Such being the pertinent provisions of the specifications, the following letters were exchanged between the parties.

December 8, 1928, plaintiff wrote defendant: “Referring to contract on boiler house at Annapolis, the specification calls that shop priming coat of red lead paint be given the steel roof decking. The usual method is to give this roof decking a baked on shop coat of red oxide paint, and we request that the same be accepted in lieu of priming coat as called for, as a baked on job, as you know will make a better job”.

December 12, 1928, defendant wrote plaintiff: “The Bureau approves the use of red iron oxide paint, baked on, for use as priming coat of paint on the steel roof deck being furnished by Ironclad Inc., for the work under the subject contract. It is understood that this paint and its application conform to the standard manufacturing practice for this class of work. The steel sheets will be subject to inspection before and after painting.”

February 25, 1929, defendant wrote plaintiff: “Two coats of field paint on the underside of the steel roof deck are required by the contract.”

It should be particularly noted that plaintiff requested the substitution of one priming coat for another according to plaintiff’s interpretation of Section 9 of the specifications. “It is therefore obvious”, says plaintiff, “that the only case where painting of the under side of the steel deck is required under the contract was the case where black steel sheets, red lead painted, were used”. On the contrary, it is obvious that when the Bureau of Yards and Docks authorized “the use of red iron oxide paint, baked on, for use as a priming coat of paint on the steel roof deck” it merely authorized plaintiff to substitute a baked on oxide coat as the priming coat. The contract prescribes two coats of field paint.

Item (a) of the bill of particulars for painting the steel deck’ is covered by the contract and is not an extra.

“(f) Unauthorized deduction for removal of airtight compartment and super-heater $135.50”.

The specifications provide:

“Section 1. General Clauses.
“1-02. General description. — The work includes removing certain damaged work; * * * and dismantling west air-tight border compartment.”
“Section 2. Removal of existing work.
“2-01. General requirements.— * * The contractor shall dismantle the roof and north and west walls of the west airtight boiler compartment; the door frame in the former i front wall of the compartment; and the stack, blower, and super-heater in the compartment.”
“Section 10. Bids.
“10-02. Item 1 — Price for the entire work, complete in accordance with the drawings and specifications”.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States Ex Rel. Strona v. Bussey
51 F. Supp. 996 (S.D. California, 1943)
S. J. Groves & Sons Co. v. Warren
135 F.2d 264 (D.C. Circuit, 1943)
English Const. Co. v. United States
43 F. Supp. 313 (D. Delaware, 1942)
General Steel Products Corp. v. United States
36 F. Supp. 498 (E.D. New York, 1941)

Cite This Page — Counsel Stack

Bluebook (online)
29 F. Supp. 526, 1939 U.S. Dist. LEXIS 2358, Counsel Stack Legal Research, https://law.counselstack.com/opinion/english-const-co-v-united-states-ded-1939.