Peerless Casualty Company v. United States of America, for the Use and Benefit of Bangor Roofing and Sheet Metal Co.

241 F.2d 811, 1957 U.S. App. LEXIS 4629, 35 Lab. Cas. (CCH) 71,856
CourtCourt of Appeals for the First Circuit
DecidedFebruary 27, 1957
Docket5142
StatusPublished
Cited by18 cases

This text of 241 F.2d 811 (Peerless Casualty Company v. United States of America, for the Use and Benefit of Bangor Roofing and Sheet Metal Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Peerless Casualty Company v. United States of America, for the Use and Benefit of Bangor Roofing and Sheet Metal Co., 241 F.2d 811, 1957 U.S. App. LEXIS 4629, 35 Lab. Cas. (CCH) 71,856 (1st Cir. 1957).

Opinion

HARTIGAN, Circuit Judge.

This is an appeal from a judgment entered by the United States District Court for the District of Maine on April 27, 1956, in an action brought by the United States of America, for the use and benefit of Bangor Roofing and Sheet Metal Company, under the Miller Act, 49 Stat. 793 (1935), 40 U.S.C.A. §§ 270a-270d, ordering that plaintiff-appellee recover of the defendants-appellants the sum of $8,185.89 plus interest and costs.

This case arises out of a subcontract, executed on August 17, 1950, between Bangor Roofing and Sheet Metal Company, the plaintiff-appellee, and T. W. Cunningham, Inc., one of the original defendants, 1 which stemmed from the principal contract of August 16, 1950 between T. W. Cunningham, Inc. and the United States of America, providing for *813 the construction of buildings and utilities at Caswell, Maine. The defendants-appellants, Peerless Casualty Company and General Reinsurance Corporation, are sureties for Cunningham on a payment bond “for the protection of all persons supplying labor and material in the prosecution of the work provided for in said contract,” pursuant to 40 U.S.C.A. § 270a (a) (2).

The sole issue presented is whether the plaintiff’s suit commenced by the filing of a complaint on September 25, 1953, was instituted within one year after the date of final settlement of the principal contract between Cunningham and the United States of America, as provided by 40 U.S.C.A. § 270b (b).

lt is set forth in 40 U.S.C.A. § 270c that where final settlement of a contract has been made, a certified statement by the Comptroller General of the date of such settlement shall be conclusive as to such date upon the parties. 2 In this case the Comptroller General certified August 28, 1952 as the date of final settlement. Since plaintiff instituted its suit approximately thirteen months after the certified settlement date, defendants made a motion for summary judgment which was denied by the district court in its opinion and order of October 28, 1955, stating that there was a genuine issue of material fact as to whether the date of final settlement, as certified by the Comptroller General, was supported by substantial evidence. Thereafter, the district court, with the consent of all the parties, held a hearing on the merits in order to ascertain the proper date of final settlement. The entire matter was submitted to the district court on various affidavits, exhibits and depositions.

The pertinent facts, as found by the district court, are as follows: The contract between Cunningham and the Government, which was to have been completed by April 5, 1951, was not fully performed until February 15, 1952. On December 27, 1951 the General Accounting Office sent a form questionnaire to the Corps of Engineers, United States Army, Office of the Division Engineer, Boston, Massachusetts, hereafter re-!'erred to as the Division Office, for the purpose of ascertaining the facts from which the date of final settlement could determined.

Before answering this questionnaire C. J. Murray, Chief of the Construction Division of the Division Office, on Au-&ust 28, 1952 signed an office memorandum, addressed to the Chief of Legal Branch of the same office, which stated aecount to date on the Cunningham contract, based on the contract and twelve change orders. The memorandum indicated a balance due the contractor, Cunningham, of $20,984.52 and an offsetting amount^ due the Government of $37,500 for liquidated damages for failure to complete the work on schedule, leaving a net amount due the Government of $16,515.48. On the basis of ^is memorandum, the Division Office in a ^e^:er dated August 29, 1952 recommended August 28, 1952 as the date of üual settlement, explaining that on this date the amount of the balance administratively found due the Government from the contractor under the contract was approved by C. J. Murray, Chief, Construction Division, New Eng-^an<* Division, Corps of Engineers.” (Emphasis in original.)

Subsequent to August 28, 1952 the Government reversed its previous posi *814 tion and waived its claim for liquidated dámages by a modification to the contract whereby February 15, 1952, and not some other prior date, was accepted as the completion date of the Caswell Project. Accordingly, a new account was prepared and approved, which indicated a balance due the contractor, Cunningham, of $20,984.52.

The first manifestation of a change of attitude on the part of the Government was a letter, dated September 4, 1952, and signed by the contracting officer of the Division Office, informing Cunningham that the Caswell Project “has been accomplished in a satisfactory manner and is accepted as of February 15,1952.” A formal order, referred to as Change Order Thirteen, bearing the date of January 2, 1952 and establishing February 15, 1952 as the date of completion of the contract, was approved by the Chief Administrative Assistant to the contracting officer on September 17, 1952.

This order, expressly providing for acceptance by Cunningham, was received by Cunningham on September 24, 1952 and acceptance thereof was mailed on September 26, 1952 to the Division Office, arriving at the Division Office on September 29, 1952. On September 30,1952 a final pay voucher, bearing that date, was executed, authorizing payment to Cunningham of $20,984.52, “as per estimate attached.” The attached estimate, like the pay voucher, was designated “final” and both corresponded numerically — twentieth pay estimate and twentieth pay voucher, but the pay estimate was undated. The pay estimate recited that the contract completion date of February 15, 1952 was determined as per Change Order Thirteen and indicated that C. J. Murray had approved"'the account as the “Contracting ■ Officer Representative.” The pay voucher and the attached pay estimate were mailed on September 30, 1952 to Cunningham and, upon being properly signed by Cunningham, they were returned on October 3, 1952 to the Division Office: Payment was made to Cunningham on October 9, 1952.

The General Accounting Office was first requested to provide a certificate of the date of final settlement of the Caswell Project by one not a party to this action in the spring of 1953. Before determining the final settlement date, the General Accounting Office made further inquiry beyond its questionnaire of December 27, 1951 by means of a letter, dated July 28, 1953, in which it requested the Division Office to furnish a copy of “the document approve^., by C. J. Murray on August 28, 1952, together with any additional information which may be required to clarify the circumstances under which payment was ■made by the Government subsequent,to a determination that a balance was -chm the Government.” 3 ,

The Division Office, in its reply ■ of August 4, 1953, rather than enclosing the August 28, 1952 memorandum, submitted a copy of the undated final pay estimate, the original of which had'been attached to the final pay voucher of September 30, 1952, and mistakenly identified it as the document that was approved by C. J. Murray on August 28, 1952 in establishing “the amount' óf balance due the contractor from the Government

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Northern California Power Agency v. Morton
396 F. Supp. 1187 (District of Columbia, 1975)
Frank v. Assessors of Skowhegan
329 A.2d 167 (Supreme Judicial Court of Maine, 1974)
Baldwin-Lima-Hamilton Corporation v. Aetna Casualty & Surety Co.
307 A.2d 169 (Supreme Court of Connecticut, 1972)
Golden West Construction Company v. United States
304 F.2d 753 (Tenth Circuit, 1962)
Jefferson Construction Co. v. United States
283 F.2d 265 (First Circuit, 1960)
United States v. Montgomery
269 F.2d 752 (Third Circuit, 1959)
United States ex rel. Soda v. Montgomery
170 F. Supp. 433 (M.D. Pennsylvania, 1959)
United States v. Standard Accident Insurance
257 F.2d 78 (Third Circuit, 1958)

Cite This Page — Counsel Stack

Bluebook (online)
241 F.2d 811, 1957 U.S. App. LEXIS 4629, 35 Lab. Cas. (CCH) 71,856, Counsel Stack Legal Research, https://law.counselstack.com/opinion/peerless-casualty-company-v-united-states-of-america-for-the-use-and-ca1-1957.