Baldwin-Lima-Hamilton Corporation v. Aetna Casualty & Surety Co.

307 A.2d 169, 163 Conn. 331, 1972 Conn. LEXIS 777
CourtSupreme Court of Connecticut
DecidedJuly 5, 1972
StatusPublished
Cited by7 cases

This text of 307 A.2d 169 (Baldwin-Lima-Hamilton Corporation v. Aetna Casualty & Surety Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Baldwin-Lima-Hamilton Corporation v. Aetna Casualty & Surety Co., 307 A.2d 169, 163 Conn. 331, 1972 Conn. LEXIS 777 (Colo. 1972).

Opinion

*332 Ryan, J.

TMs is an action brought by the plaintiff, the Baldwin-Lima-Hamilton Corporation, hereinafter referred to as Baldwin, on a payment bond issued by the defendants The Aetna Casualty and Surety Company, a Connecticut corporation, and the American Employers’ Insurance Company and The Employers’ Fire Insurance Company, both Massachusetts corporations, seeking payment of the balance due for materials furnished on a construction contract. The referee, acting as the court, rendered judgment for the defendants and the plaintiff has appealed to this court.

This action arose out of the construction of a bridge over Bridgeport harbor on the Connecticut Turnpike. The contract for the superstructure of the bridge was executed on January 31, 1956, by the highway commissioner for the state and by Terry Contracting, Inc., of the city of New York, hereinafter referred to as Terry. At the same time Terry filed the bond in question with the state. This was a payment bond required by statute for the protection and payment of subcontractors and material-men on public works projects of the state. The defendants were sureties on the bond. In its substituted complaint the plaintiff alleged that between June 14, 1957, and December 17, 1957, it sold and delivered to Terry steel which was used in the bridge construction and that Terry has refused to pay the bill due in the sum of $534,328.18 and, accordingly, the conditions of the bond were breached; that this sum is due and owing from the defendants; that although demand has been made on the defendants they have failed and refused to pay. It was also alleged that on October 14, 1963, judgment was rendered against Terry on a counterclaim filed by the plaintiff in a suit brought by Terry in the Supreme *333 Court in the state of New York. The amount of the judgment was $530,000 plus interest of $175,960, a total of $705,960. The defendants have stipulated as to the essential factual allegations of the complaint, but interposed two special defenses, one of which is pertinent to this appeal wherein they allege that the statutory period during which the plaintiff could have brought this action has expired since this suit was not commenced within one year from the date of “final settlement” by the state of the Terry contract. Rev. 1949, §§ 7215, 7216. The defendants contend that a document entitled “Certified Statement of Date of Final Settlement of Contract” executed by the attorney general of the state conclusively establishes the “final settlement date” as April 14, 1960. The plaintiff’® reply in avoidance alleges that April 14, 1960, is not the final settlement date since Terry, the contractor, had made a claim for extra work which was pending on that date and which was not finally refused by the state until April 3,1961.

The gravamen of the plaintiff’s appeal is an attack on the conclusions of the referee. The plaintiff contends that the attorney general’s certification of April 14, 1960, as the date of final settlement is erroneous as a matter of law, and, in such a case, the court is not bound to accord the certificate conclusive effect. To review these claims it is necessary to examine the provisions of §§ 7214-7216 of the 1949 Revision (now §§49-41 — 49-43 of the General Statutes) which were in effect at the time the contract was made in the present ease together with some of the additional subordinate facts from which the referee reached his conclusions.

Sections 7214 — 7216 are designed to protect subcontractors and materialmen on public works proj *334 sets. Section 7214 requires that on any contract for the construction of any public work in this state, the general contractor must furnish to the state a payment bond with surety in the amount of the contract. Section 7215 permits those furnishing labor and materials to sue on the bond if they have not been paid within sixty days from the date on which the last of their labor was performed or materials supplied. Subsection (b) of § 7215 provides that “no such suit shall be commenced after the expiration of one year after the date of final settlement of such contract.” 1 Section 7216 establishes the procedure whereby the attorney general will furnish to those authorized to sue under the provisions of § 7215 a certified statement of the date of final settlement of the contract. It provides that this statement “shall be conclusive as to such date upon the parties.”

The referee found that none of the documents which comprise the contract between Terry and the state, including the payment bond, contains a reference to or definition of the term “final settlement.” After the contract was signed, the highway department altered the method by which it determined the final settlement date of a contract, equating it with the date of the final estimate. This was never made a part of the Terry contract. Previously, the attorney general had equated “final settlement” with final payment. On April 14, 1960, the engineer of contracts and construction of the highway department approved the final estimate in the Bridgeport harbor-project. On April 25, 1960, the state issued a “final *335 payment” check to Terry. Terry obtained permission from the state to cash this cheek subject to a claim for extra work which it alleged it had performed. On December 30, 1960, Terry submitted its claim for extras which was denied by the state on April 3,1961.

The referee also found that in February and March, 1959, the plaintiff notified the defendant and the highway department that it had not been paid and that it might be necessary for it to file a claim under the payment provision of the bond. On March 10, 1959, the plaintiff wrote to the attorney general and asked for a copy of the bond. This was obtained two weeks later. After the institution of this action and at the request of the defendant, the attorney general, on May 3, 1962, determined that April 14, 1960, was the date of final settlement of the Terry contract a.nd certified this as provided for in § 7216. This date coincides with the date of approval of the final estimate on the Terry contract by the highway department. Prior to the commencement of this action, the plaintiff was not notified that a final settlement date had been established. The certificates of final settlement are issued on request but there was no evidence that the plaintiff had requested the certificate before starting this action.

The statutes involved in this case are similar to the federal statutes popularly known as the Miller Act. 40 U.S.C. §§ 270a-270d. For this reason the decisions of the federal courts relative to the Miller Act are helpful. International Harvester Co. v. L. G. DeFelice & Son, Inc., 151 Conn. 325, 333, 197 A.2d 638. In the recent case of Pittsburgh Plate Glass Co. v. Dahm, 159 Conn. 563, 271 A.2d 55, we adopted the long-standing federal definition of “final settlement” which was then found in both the state and *336

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Borelli v. Town of Ansonia, No. Cv 00-044491s (Jun. 6, 2001)
2001 Conn. Super. Ct. 7758 (Connecticut Superior Court, 2001)
Montanaro v. Gorelick, No. Cv97 034 86 88 (Mar. 21, 2001)
2001 Conn. Super. Ct. 3935 (Connecticut Superior Court, 2001)
Tine v. Baker, No. 11 66 45 (Mar. 27, 2000)
2000 Conn. Super. Ct. 3839 (Connecticut Superior Court, 2000)
O & G Industries, Inc. v. Town of New Milford
640 A.2d 110 (Supreme Court of Connecticut, 1994)
Dan Beard, Inc. v. Cosmar Construction, No. Cv92 03 99 03 (May 25, 1993)
1993 Conn. Super. Ct. 5113 (Connecticut Superior Court, 1993)
O & G Industries, Inc. v. Town of New Milford
617 A.2d 938 (Connecticut Appellate Court, 1992)
Antonio Carro, Inc. v. Jura Construction, Inc.
107 P.R. Dec. 808 (Supreme Court of Puerto Rico, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
307 A.2d 169, 163 Conn. 331, 1972 Conn. LEXIS 777, Counsel Stack Legal Research, https://law.counselstack.com/opinion/baldwin-lima-hamilton-corporation-v-aetna-casualty-surety-co-conn-1972.