United States Fidelity & Guaranty Co. v. United States

65 F.2d 639, 1933 U.S. App. LEXIS 3104
CourtCourt of Appeals for the Ninth Circuit
DecidedJune 5, 1933
DocketNo. 6973
StatusPublished
Cited by5 cases

This text of 65 F.2d 639 (United States Fidelity & Guaranty Co. v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States Fidelity & Guaranty Co. v. United States, 65 F.2d 639, 1933 U.S. App. LEXIS 3104 (9th Cir. 1933).

Opinion

SAWTELLE, Circuit Judge.

This is an appeal from a judgment against the appellant surety company in an action brought against it by certain material-men and labor claimants, in the name of the United States, on a contractor’s bond. The action was brought under the Materialmen’s Act, also known as the Hurd Act (40 USCA § 270). The ease was tried before the court without a jury.

Appellant was the surety on a bond of one Rhivers, who had contracted, under date of June 16, 1926, with the United States Department of Agriculture for the improvement of a road in the Sawtooth National Forest, State of Idaho. The bond was in the amount of $11,438, in favor of the United States and all persons furnishing labor or materials to the contractor, and,was conditioned on the faithful performance of the contract by Rhivers.

Rhivers began work under the contract on July 1,1926, but within two months abandoned the job. Thereupon appellant employed the Elliott Trucking Company to proceed with the work required under the Rhiv-ers contract. The Elliott Trucking Company commenced work about October 1, 1926, and proceeded for about one month, when it also ceased and did not thereafter resume the work.

In June, 1927, the United States annulled the Rhivers contract for failure to complete the work or proceed therewith as required by the contract.

In August, 1927, the United States contracted with one Cavanagh to finish the work, and he completed it in July, 1928.

August 24, 1928, the Acting Chief Engineer of the Bureau of Public Roads of the United States Department of Agriculture authorized the District Engineer at Ogden, Utah, to make payment of final voucher due under the contract to contractor Cavanagh.

November 6, 1928, the Chief of the Bureau of Public Roads of the United States Department of Agriculture, at Washington, D. C., made claim, by letter, against appellant for the difference ($9,361.95) between the actual cost of the work and what it would have cost at the bid prices under the Rhivers contract. In this letter it is said: “The Rhivers contract has now been completed and we are in receipt of a statement of the final cost which shows that the claim which the Government has against your company is $9,361.95.” Hereinafter we will again refer to this letter in connection with a controversy over the date of “final settlement” of the contract in question. Conferences and negotiations concerning the claim were thereafter had between the Bureau of Public Roads and appellant, and correspondence relating thereto also passed between the Secretary of Agriculture and the Attorney General. In a letter dated January 20, 1930, the Acting Secretary of Agriculture requested the Attorney General to bring suit against appellant to recover the amount of the claim. Apparently the Attorney General referred the matter to the United States attorney for the state of Maryland, and finally, on- June 10, 1930, appellant paid the claim.

This action was commenced on May 1, 1931, in the name of the United States, for the use and benefit of creditors of Rhivers and the Elliott Trucking Company, who had furnished labor and materials. Other- creditors of these contractors intervened in the action.

Appellant alleged in its answer that “final settlement” of the contract, within the meaning of the law, occurred more than one year prior to the commencement of the action, and that the cause of action was therefore barred by the one-year period of limitations contained in the statute under which the action was brought. The court overruled appellant’s motion for dismissal and judgment of nonsuit, based on the ground that the evidence failed to show that the suit was commenced within one year after the complete performance of the contract and final settlement thereof. The court found and concluded that final settlement of the contract occurred on June 10,1930, the date of payment by appellant of the claim of the government under the defaulted Rhivers contract, and accordingly that the action commenced on May 1, 1931, was not barred.

The question thus presented for our consideration is whether or not “final settlement” of the contract occurred within one year of the date of the commencement of the action.

As stated by appellant, “The controversy here revolves around the question of ‘final settlement,’ and what it means within the purview of the statute; appellees seem to [641]*641contend that it means the date when ‘final payment’ is made to the government, or by the government, of the balance due to either party, arising out of the construction contract; appellant contends that it is the date when the proper departmental officers, in the course of their regular departmental duties, determine the status between the government and the contractor, without any reference to actual agreements or understandings between the parties to the contract; in this instance, a determination by the acting chief engineer of the Bureau of Public Roads, as well as by the Chief of the Bureau of Public Roads in the course of their duties, as well as a recognition and. acceptance of that determination by the acting Secretary of Agriculture.”

The statute in question -reads, in part, as follows: “If no suit should be brought by the United States within six months from the completion and final settlement of said contract, then the person or persons supplying the contractor with labor and materials shall, upon application therefor, and furnishing affidavit to the department under the direction of which said work has been prosecuted that labor or materials for the prosecution of such work has been supplied by him or them, and payment for which has not been made, be furnished with a certified copy of said contract and bond, upon which he or they shall have a right of action, and shall be, and are hereby, authorized to bring suit in the name of the United States in the district court of the United States in the district in which said contract was to be performed and executed, irrespective of the amount in controversy in such suit, and not elsewhere, for his or their use and benefit, against said contractor and his sureties, and to prosecute the same to final judgment and execution: Provided, That where suit is instituted by any of such creditors on the bond of the contractor it shall not be commenced until after the complete performance of said contract and final settlement thereof, and shall be commenced within one year after the performance and final settlement of said contract, and not later.”

The contention of appellant, that “final settlement” of the- contract relates to the time when the amount due thereunder is determined by the appropriate administrative authority, ráther than the date of “final payment” of such amount, is supported by the case of Illinois Surety Co. v. United States, to Use of Peeler, 240 U. S. 214, 36 S. Ct. 321, 60 L. Ed. 609. In that ease the statute we are considering, and in particular the words “final settlement” as used therein, were construed by the Supreme Court. That was an action on a contractor’s bond given by the Illinois Surety Company to secure the faithful performance of a contract to erect .a post office building. The statute, it will be noted, provides not only that an action on the surety bond by creditors of the contractor must be commenced within one year from the date of completion and final settlement of the contract, but also that such an action may not be commenced unless within six months prior thereto the United States has failed to bring suit on the bond.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
65 F.2d 639, 1933 U.S. App. LEXIS 3104, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-fidelity-guaranty-co-v-united-states-ca9-1933.