This text of 57 F.2d 995 (Consolidated Indemnity & Ins. Co. v. WA Smoot & Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Consolidated Indemnity & Ins. Co. v. WA Smoot & Co., 57 F.2d 995, 1932 U.S. App. LEXIS 4106 (4th Cir. 1932).

Opinion

PARKER, Circuit Judge.

This is an appeal by a surety company from a judgment in an action brought under the Hurd Act (28 Stat. 278, as amended [49 USCA § 279]) by persons who had furnished materials to a government contractor, whose bond had been signed by the surety company. The action was instituted Jan-. uary 27, 1931, and thereafter a number of claimants intervened. A jury trial was waived and the ease was heard by the Dis-triet Judge,'who found as a fact that the date of final settlement between the government and the contractor was July 9, 1930. - Judgment was rendered in favor of a number of the claimants, and from this judgment the surety company appealed. The questions raised by the assignments of error relate to the date of-final settlement, the contention' of the company being that the finding .of the trial judge with regard thereto is not sustained by the evidence.

The facts with regard to the final settlement are undisputed. Work under the eon-tract, which was the construction of barracks at Ft. Humphreys, Ya., was completed June 24,1930. On June 28,1930, the constructing quartermaster at Ft. Humphreys agreed with the contractor upon the balance remaining due under the contract and prepared a voucher for that amount which was signed by himself and the contractor. This voucher showed the amount due uuder the original contraet, the increases made in the contract price by change orders A, B, C, and D, the total of these amounts, the amount of previous payments and the balance remaining due and payable, which.was shown as oc038.56. As. prepared it was marked final payment on the contract. The contractor on the same day presented it govpayment to . the entiofficer of the War Department in Washington, hut the 20 refused to pay it because not accompanied by change order D, which added $39.68 to the contract price, The constructing quartermaster thereupon directed the disbursing officer to change the voucher so as to eliminate Brown-Ketcham the amount of change order D aid to designate it as being the tenth partial payment instead of final payment. This was done by striking out the word “final” on the face of the voucher and -writing “10th partial payment” above it, and by subtracting $39.68 from the total shown to be due under the voucher. The $39.68 was designated as “awaiting adjustment” Tlle voucher then showed:

Original Contract ...........................$160,394.09
Change Order A, increase dated 3/26/30.... 4,527.05
“ “ B, “ dated 4/10/30.... 454.00
" “ c, “ dated 4/28/30.... 288.57
«« « -n qq ña ’ ..................
Voucher Nos. on attached sheet.......$165,703.39
Previous payments ........................
Amount due and payable...............? 18,038.56
Less amount oí Change Order "D”
awaitins ^ustment .................
Total ....................................$ 17,998.8»

_ Check in the sum of $17,998.88 was then issue(l to the contractor,

On July 9,1930, the constructing quartermaster executed and delivered to the eon-tractor a voucher for final payment in the sum of $39.6S, the amount of change order D. This voucher was approved for payment on July 23d and cheek in payment óf same was issued on July 2'6th, being delayed because change order D had still not been reeeived by the disbursing officer. It appears, however, that this change order had been duly signed by the constructing quartermaster on '^rine 25th.

[i] On these facts we agree with appellant that the finding that the final settlement oe-eurred on July 9th is not supported by the evidence; but we think that the-evidence shows conclusively that it did occur on June 28th. Final settlement as used in the Hurd Act does not mean final payment. “It means the final determination by the proper governmental authority of the amount which the government is finally bound to pay or enti-tied to receive under the contract.” U. S., to Use of Stallings, v. Starr (C. C. A. 4th) 2:0 F.(2d) 803, 806; Illinois Surety Co. v. United States, U. S. 214, 36 S. Ct. 321, 60-L. Ed. 609; Arnold v. U. S. (C. C. A. 4th) 280 F. 338; U. S. to Use of Union Gas Engine Co. v. Newport Shipbuilding Corporation (C. C. A. 4th) 18 F.(2d) 556. As said by the Circuit Court of Appeals for the Second Circuit in U. Unitex rel. 240 Iron Works v. Robinson, 214 F. 38, 40-: “In determining the time when materialmen En.begin Corporait would not do to fix it at some day ‘after Secperformance’ merely, Defective work, damages for delay, and other matters might give the United States some claim which it might not decide to prosecute until some time after the work was turned over, apparently complete. The date was, *997 therefore, fixed relatively to ‘complete performance of the contract and final settlement thereof.’ We take it that these italicized words refer to the time when the proper government officer, who has the final discretion in sueh matters, after examination of the facts, satisfies himself that the government will accept the work, as it is, without making any claim against the contractor for unfinished or imperfect work, damages for delay or what not, and records that decision in some orderly way.”

The final settlement within the rule as thus stated occurred when the constructing quartermaster at Ft. Humphreys officially determined the balance due under the contract and recorded that determination by signing a voucher setting forth the balance. The fact that the voucher was changed before payment did not affect the matter. It still showed the balance due, and that only an insignificant portion of that balance was withheld awaiting adjustment. As a matter of fact, this portion of the balance had already been approved and payment was not made because the voucher was not accompanied by change order 0; hut, even if it had been subject to adjustment or change, this would have made no difference. As we said in the Starr Case, supra: “There may be a final settlement between the government and the contractor, so as to fix the rights of the creditor under the statute, notwithstanding the balance may be subject to change; for when the government has clearly indicated that it has no further claim against the surety, a final settlement within the purview of the act has taken place. U. S. v. Title Guaranty & Surety Co. (C. C. A. 7th) 254 F. 958; Robinson v. U. S. (C. C. A. 2d) 251 F. 461.”

It is argued that there was no showing that there had ever been a final settlement within the meaning of the Hurd Act because there was no evidence of a settlement in the general accounting office, as required by the Budget and Accounting Act of 1923. Act June 10, 1921, § 305 (31 USCA § 71). We are not impressed by this argument. Undoubtedly, where the Comptroller General actually makes the administrative determination of the amount due, as in Lambert Lumber Co. v. Jones Engineering & Construction Co. (C. C. A. 8th) 47 F.(2d) 74, his determination is the settlement within the meaning of the act.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
57 F.2d 995, 1932 U.S. App. LEXIS 4106, Counsel Stack Legal Research, https://law.counselstack.com/opinion/consolidated-indemnity-ins-co-v-wa-smoot-co-ca4-1932.